DATEDESCRIPTION AMOUNT
2
3
FFE
4
3/31/2023FFE Equipment Purchases $ 17,906.69
5
3/8/2023FFE Equipment Purchases $ 22,191.01
6
2/10/2023FFE Equipment Purchases $ 5,095.21
7
1/12/2023FFE Equipment Purchases $ 13,719.28
8
12/8/2022FFE Equipment Purchases $ 32,228.31
9
11/11/2022FFE Equipment Purchases $ 9,509.80
10
11/2/2022Studio Curtains $ 9,550.00
11
10/16/2022FFE Equipment Purchases $ 12,257.39
12
9/29/2022Studio Lighting 4/4 $ 7,500.00
13
9/17/2022FFE Equipment Purchases $ 11,475.95
14
8/29/2022Studio Lighting 2/4 $ 13,690.10
15
8/29/2022Building Sign Deposit $ 3,000.00
16
8/29/2022Studio Lighting 2/4 $ 10,000.00
17
8/1/2022FFE Equipment Purchases $ 12,367.46
18
7/21/2022FFE Equipment Purchases $ 1,645.09
19
6/14/2022FFE Equipment Purchases $ 1,493.99
20
5/31/2022Studio Lighting 1/4 $ 33,000.00
21
6/14/2022Lighting Infrastructure Final payment $ 8,750.00
22
5/10/2022ECO Tints - Detinting Windows $ 750.00
23
5/13/2022FFE Equipment Purchases $ 2,508.87
24
2/7/2022Lighting Infrastructure Deposit $ 25,000.00
25
2/7/2022Security System Deposit $ 4,410.00
26
Total FFE $ 258,049.15
27
28
Building Contract
29
2/3/2023APPL 13 Jan 2022 $ 126,784.80
30
9/29/2022APPL 12 Aug 2022 $ 16,903.83
31
8/31/2022APPL 11 July 2022 $ 50,028.11
32
7/1/2022APPL 10 June 2022 $ 69,784.96
33
6/1/2022APPL 9 May 2022 $ 133,877.15
34
5/1/2022APPL 8 April 2022 $ 273,280.18
35
4/12/2022APPL 7 March 2022 $ 121,785.40
36
4/6/2022APPL 6 February 2022 $ 480,893.10
37
3/30/2022APPL 5 January 2022 $ 167,598.62
38
1/24/2022APPL 4 December 2022 $ 220,456.71
39
12/22/2021APPL 3 November 2021 $ 209,439.22
40
12/1/2021APPL 2 October 2021 $ 130,238.22
41
11/5/2021APPL 1 Sept 2021 $ 66,353.65
42
Total Building Contract paid $ 2,067,423.95
43
44
45
Total Change Orders
46
PCO 1 - Material escalation $ 27,221.25
47
PCO 2 - Roof Replacement $ 29,735.00
48
PCO 3 - 2 Structural LVL Posts $ 2,531.00
49
PCO 4 - Roof Abatement $ 11,259.00
50
PCO 5 - New Water Service $ 20,229.00
51
PCO 6 - Rot Repair $ 23,306.48
52
PCO 8 - 4 Structural LVL Posts $ 4,950.00
53
PCO 09 - Credit for Casework $ (6,800.00)
54
PCO 10 - Roof Rot Repair $ 9,500.00
55
PCO 11 - Framing Materials Overage
$ 16,347.58
56
PCO 12 - Door for Studio $ 6,789.20
57
PCO 13 - Rot Repair $ 5,998.80
58
PCO 14 - Revision to PCO 11 $ (1,551.00)
59
PCO 15 - Credit, Quiet Floor System
$ (3,346.00)
60
PCO 16 - Roof Rot Repair $ (6,320.00)
61
PCO 17 - Rot Repair $ 9,930.80
62
PCO 18 - Insulation Upgrade $ 979.00
63
PCO 20 - Control 115 Track Lighting
$ 1,254.00
64
PCO 21 - Added Power Requirements
$ 2,662.00
65
PCO 22 - Studio beam wraps $ 4,790.76
66
PCO 23 - Added header 2nd
floor
$ 4,771.00
67
PCO 24 - Reception Millwork $ 3,152.00
68
PCO 25 - Concrete Utility Pad $ 2,514.00
69
PCO 26 - Masonry Repointing $ 1,210.55
70
PCO 27 - BDA closet Framing $ 3,740.00
71
PCO 28 - Materials $ 13,069.47
72
PCO 29 - Temp Sub-Panels $ 1,320.00
73
PCO 30 - Electircal additions $ 2,107.51
74
PCO 31 - Lower Brick Painting $ 2,200.00
75
PCO 32 - Painting extras $ 2,310.00
76
PCO 34 - Painting additions $ 2,362.80
77
PCO 35 - Front façade painting $ 2,424.00
78
PCO 36 - BDA $ 44,000.00
79
PCO 37 - Sign Install $ 4,600.00
80
PCO 38 - Data Floor Boxes $ 907.59
81
PCO 39 - Elec Adds $ (344.41)
82
PCO 40 - T&M BDA Requirements $ 4,712.89
83
PCO 41 - HVAC 2nd Floor Work/Contingency Close out $ 731.73
84
PCO 42 -Price Escalation, Copper and Steal Pipe and Wire
$ 3,454.00
85
Total Aproved COs $ 258,710.00
86
87
88
89
Remaining Costs
90
91
92
Building Contract $ 1,820,778.00
93
Change Orders $ 258,710.00
94
Total Building $ 2,079,488.00
95
96
Payments $ 2,067,423.95
97
Balance Remaining $ 12,064.05
98
99
100
Additional Building Costs Due