A | B | C | D | E | F | G | ||
---|---|---|---|---|---|---|---|---|
1 | Sprints | Sprint 1 (3W) Week 14-16 02/04-21/04 | Sprint 2 (2W) Week 17-18 22/04-05/05 | Sprint 3 (2W) Week 19-20 06/05-19/05 | Sprint 4 (3W) Week 21-23 20/05-09/06 | Sprint 5 (2W) Week 24-25 10/06-23/06 | Sprint 6 (2W) Week 26-27 24/06-04/07 | |
2 | Sprint Goal | Concept Iteration | Core functionality | Level Blocking | Level Dressing & Finalising | Backup | Backup | |
3 | Game Design | Level Blocking | ||||||
4 | Programming | Character Controller | Level Loading | |||||
5 | Art | Finding Asset Packages | GUI Design | |||||
6 | Audio | Music | ||||||
7 | Project Management | ... | ||||||
8 | Milestones | Work in Progress 24/05 (W21) Playtest 07/06 (W23) | Final Game 04/07 (W27) |