A | B | C | D | E | F | G | H | I | J | K | L | M | N | O | P | Q | R | S | T | U | V | W | X | Y | Z | |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1 | ID | Name | Duration | Start | Finish | Predecessors | Resources | |||||||||||||||||||
2 | 1 | SMARC Pilot | 215days? | 1/12/2021 | 09/27/2022 | |||||||||||||||||||||
3 | 2 | Planning Phase | 59days | 1/12/2021 | 02/21/2022 | |||||||||||||||||||||
4 | 3 | Prototype Outcome Review | 1day | 1/12/2021 | 1/12/2021 | |||||||||||||||||||||
5 | 4 | Scope Definition | 3days | 2/12/2021 | 6/12/2021 | 3 | ||||||||||||||||||||
6 | 5 | Document and Agree project objectives | 5days | 4/2/2022 | 10/2/2022 | 3 | ||||||||||||||||||||
7 | 6 | Project Risk/ /Issues/Dependancies Identification | 5days | 11/2/2022 | 02/17/2022 | 5 | ||||||||||||||||||||
8 | 7 | Establishing Project Control Mechanisms - (Governance, Output, Reporting, Metrics) | 1day | 02/18/2022 | 02/18/2022 | 6 | ||||||||||||||||||||
9 | 8 | Define Stakeholder Map | 1day | 02/21/2022 | 02/21/2022 | 7 | ||||||||||||||||||||
10 | 9 | Document project plan and business case | 5days | 2/12/2021 | 8/12/2021 | 3 | ||||||||||||||||||||
11 | 10 | Project plan and Business case approval | 1day | 9/12/2021 | 9/12/2021 | 9 | ||||||||||||||||||||
12 | 11 | Analysis, requirements and design | 19days | 02/22/2022 | 03/18/2022 | 2 | ||||||||||||||||||||
13 | 12 | User Consultation | 2days | 02/22/2022 | 02/23/2022 | 4 | ||||||||||||||||||||
14 | 13 | Feature Identification | 3days | 02/24/2022 | 02/28/2022 | 12 | ||||||||||||||||||||
15 | 14 | Identify potential suppliers | 2days | 02/22/2022 | 02/23/2022 | 4 | ||||||||||||||||||||
16 | 15 | High level Solution Design - Pilot | 4days | 1/3/2022 | 4/3/2022 | 13 | ||||||||||||||||||||
17 | 16 | Order SMARC Components | 10days | 7/3/2022 | 03/18/2022 | 15 | ||||||||||||||||||||
18 | 17 | Data Collection + Evaluation | 2days | 1/3/2022 | 2/3/2022 | 13 | ||||||||||||||||||||
19 | 18 | Detailed Design | 10days | 7/3/2022 | 03/18/2022 | 15 | ||||||||||||||||||||
20 | 19 | Development and Testing | 45days | 03/21/2022 | 05/20/2022 | |||||||||||||||||||||
21 | 20 | Sprint 1- Build Physical Units | 27days | 03/21/2022 | 04/26/2022 | 18 | ||||||||||||||||||||
22 | 21 | Sprint Planning | 1day | 03/21/2022 | 03/21/2022 | 18 | ||||||||||||||||||||
23 | 22 | Sprint Backlog | 25days | 03/22/2022 | 04/25/2022 | 21 | ||||||||||||||||||||
24 | 23 | Unit Testing | 25days | 03/22/2022 | 04/25/2022 | 21 | ||||||||||||||||||||
25 | 24 | Standups | 25days | 03/22/2022 | 04/25/2022 | 21 | ||||||||||||||||||||
26 | 25 | Sprint Review | 0.5day | 04/26/2022 | 04/26/2022 | 22 | ||||||||||||||||||||
27 | 26 | Sprint Retrospective | 0.5day | 04/26/2022 | 04/26/2022 | 25 | ||||||||||||||||||||
28 | 27 | Sprint 2 - Develop and Train ML code for device recognition | 20days | 03/21/2022 | 04/15/2022 | 18 | ||||||||||||||||||||
29 | 28 | Sprint Planning | 3days | 03/21/2022 | 03/23/2022 | 18 | ||||||||||||||||||||
30 | 29 | Sprint Backlog | 15days | 03/24/2022 | 04/13/2022 | 28 | ||||||||||||||||||||
31 | 30 | Standups | 15days | 03/24/2022 | 04/13/2022 | 28 | ||||||||||||||||||||
32 | 31 | Sprint Review | 1day | 04/14/2022 | 04/14/2022 | 29 | ||||||||||||||||||||
33 | 32 | Sprint Retrospective | 1day | 04/15/2022 | 04/15/2022 | 31 | ||||||||||||||||||||
34 | 33 | Sprint 3 - Develop supporting systems | 19days | 04/15/2022 | 11/5/2022 | 31 | ||||||||||||||||||||
35 | 34 | Sprint Planning | 3days | 04/15/2022 | 04/19/2022 | 18 | ||||||||||||||||||||
36 | 35 | Sprint Backlog | 15days | 04/20/2022 | 10/5/2022 | 34 | ||||||||||||||||||||
37 | 36 | Standups | 15days | 04/20/2022 | 10/5/2022 | 34 | ||||||||||||||||||||
38 | 37 | Sprint Review | 0.5day | 11/5/2022 | 11/5/2022 | 35 | ||||||||||||||||||||
39 | 38 | Sprint Retrospective | 0.5day | 11/5/2022 | 11/5/2022 | 37 | ||||||||||||||||||||
40 | 39 | Testing | 7days | 12/5/2022 | 05/20/2022 | 23 | ||||||||||||||||||||
41 | 40 | Systems Integration Testing | 2days | 12/5/2022 | 05/13/2022 | 38 | ||||||||||||||||||||
42 | 41 | User Acceptance testing | 2days | 05/16/2022 | 05/17/2022 | 40 | ||||||||||||||||||||
43 | 42 | End-to-end testing | 1day | 05/18/2022 | 05/18/2022 | 41 | ||||||||||||||||||||
44 | 43 | Pre-production testing | 2days | 05/19/2022 | 05/20/2022 | 42 | ||||||||||||||||||||
45 | 44 | Environment Planning and Deployment | 10days | 03/21/2022 | 1/4/2022 | 18 | ||||||||||||||||||||
46 | 45 | Plan (virtual) Environments | 5days | 03/21/2022 | 03/25/2022 | |||||||||||||||||||||
47 | 46 | Deploy virtual environments | 5days | 03/28/2022 | 1/4/2022 | 45 | ||||||||||||||||||||
48 | 47 | Implementation | 1day? | 05/23/2022 | 05/23/2022 | 43 | ||||||||||||||||||||
49 | 48 | SMARC units made available to Consumers | 1day? | 05/23/2022 | 05/23/2022 | |||||||||||||||||||||
50 | 49 | SMARC App, API's and Website deployment | 1day | 05/23/2022 | 05/23/2022 | |||||||||||||||||||||
51 | 50 | SMARC system Go-Live | 1day | 05/24/2022 | 05/24/2022 | 49 | ||||||||||||||||||||
52 | 51 | Pilot Operations and maintenance | 90days | 05/24/2022 | 09/26/2022 | 47 | ||||||||||||||||||||
53 | 52 | Software Patches/Model Updates (as required) | 90days | 05/24/2022 | 09/26/2022 | |||||||||||||||||||||
54 | 53 | Physical Unit repair/troubleshooting | 90days | 05/24/2022 | 09/26/2022 | |||||||||||||||||||||
55 | 54 | Other component maintenance | 90days | 05/24/2022 | 09/26/2022 | |||||||||||||||||||||
56 | 55 | Pilot End | 1day | 09/27/2022 | 09/27/2022 | 51 | ||||||||||||||||||||
57 | 56 | SMARC Production (Indicative Only) | 320days | 09/27/2022 | 12/18/2023 | |||||||||||||||||||||
58 | 57 | Post Pilot Review | 5days | 09/27/2022 | 3/10/2022 | 51 | ||||||||||||||||||||
59 | 58 | Product Enhancements | 70days | 4/10/2022 | 9/1/2023 | 57 | ||||||||||||||||||||
60 | 59 | Initial Production Rollout | 235days | 10/1/2023 | 4/12/2023 | 58 | ||||||||||||||||||||
61 | 60 | Production Rollout review: market and system performance analysis | 10days | 5/12/2023 | 12/18/2023 | 59 | ||||||||||||||||||||
62 | 61 | End-of-life and Decommissioning | 816days? | 08/25/2021 | 9/10/2024 | |||||||||||||||||||||
63 | 62 | Decommission Individual SMARC Device (as required) | 1day | 09/25/2024 | 09/25/2024 | |||||||||||||||||||||
64 | 63 | Decomission SMARC System | 10days | 09/26/2024 | 9/10/2024 | 62 | ||||||||||||||||||||
65 | ||||||||||||||||||||||||||
66 | ||||||||||||||||||||||||||
67 | ||||||||||||||||||||||||||
68 | ||||||||||||||||||||||||||
69 | ||||||||||||||||||||||||||
70 | ||||||||||||||||||||||||||
71 | ||||||||||||||||||||||||||
72 | ||||||||||||||||||||||||||
73 | ||||||||||||||||||||||||||
74 | ||||||||||||||||||||||||||
75 | ||||||||||||||||||||||||||
76 | ||||||||||||||||||||||||||
77 | ||||||||||||||||||||||||||
78 | ||||||||||||||||||||||||||
79 | ||||||||||||||||||||||||||
80 | ||||||||||||||||||||||||||
81 | ||||||||||||||||||||||||||
82 | ||||||||||||||||||||||||||
83 | ||||||||||||||||||||||||||
84 | ||||||||||||||||||||||||||
85 | ||||||||||||||||||||||||||
86 | ||||||||||||||||||||||||||
87 | ||||||||||||||||||||||||||
88 | ||||||||||||||||||||||||||
89 | ||||||||||||||||||||||||||
90 | ||||||||||||||||||||||||||
91 | ||||||||||||||||||||||||||
92 | ||||||||||||||||||||||||||
93 | ||||||||||||||||||||||||||
94 | ||||||||||||||||||||||||||
95 | ||||||||||||||||||||||||||
96 | ||||||||||||||||||||||||||
97 | ||||||||||||||||||||||||||
98 | ||||||||||||||||||||||||||
99 | ||||||||||||||||||||||||||
100 |