| A | C | D | E | F | G | H | I | J | K | L | M | N | O | P | Q | R | S | T | U | V | W | X | Y | Z | ||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1 | Project: | |||||||||||||||||||||||||
2 | Originated By: | |||||||||||||||||||||||||
3 | Reviewed By: | |||||||||||||||||||||||||
4 | Approved By: | |||||||||||||||||||||||||
5 | Stage: | 1 | ||||||||||||||||||||||||
6 | Deliverable | References | Select (DBM) | Define (EDS) | Detailed Engineering | Execute | ||||||||||||||||||||
7 | Requirements | Status | Remarks | Requirements | Status | Remarks | Requirements | Status | Remarks | Requirements | Status | Remarks | ||||||||||||||
8 | Process | ● | ● | ● | ● | |||||||||||||||||||||
9 | Basis of Design (BOD) | ● | IFD | AOC scope | ● | IFD | AOC scope, update only | |||||||||||||||||||
10 | Battery Limit Table | 0000-TPL-PE-0009 | Covered in DBM document | ● | IFD | ● | IFC | |||||||||||||||||||
11 | Block Flow Diagram (BFD) | ● | IFR | ● | IFD | |||||||||||||||||||||
12 | Catalyst and Chemical Requirements | ● | IFR | Identification only | ● | IFD | ● | IFD | Update | |||||||||||||||||
13 | Emissions and Effluent Summary | ● | IFR | ● | IFA | ● | IFA | |||||||||||||||||||
14 | Equipment Sizing Report | ● | IFR | Calculations and Narrative | ● | IFA | Calculations and Narrative | ● | IFD | Update | ||||||||||||||||
15 | Flare System Simulation | ● | IFN | Aspen Flare System Analyzer V7.2 | ● | IFN | Aspen Flare System Analyzer V7.2 | |||||||||||||||||||
16 | Flare, Relief and Vent Report | ● | IFA | Includes flare load and relief summary tables | ● | IFD | Update | |||||||||||||||||||
17 | Hazard Assessment | ● | Based on plot plan and PFD | |||||||||||||||||||||||
18 | HAZOP Action/Parking Lot Close Out Report | 0000-GUI-PE-0001 | ● | IFA | ● | IFD | ● | IFD | As required | |||||||||||||||||
19 | HAZOP Review | 0000-GUI-PE-0001 | ● | Excludes vendor packages | ● | Vendor packages and BOP updates | ||||||||||||||||||||
20 | Hydraulic Analysis/Calculations | ● | IFR | Major piping and pipelines only | ● | IFD | ● | IFD | ||||||||||||||||||
21 | Line Sizing Summary Table | 0000-TPL-PE-0006 | ● | IFD | ● | IFD | Update | |||||||||||||||||||
22 | Mass & Energy Balance (M&EB) | 0000-TPL-PE-0002 | ● | IFR | ● | IFD | ● | IFD | Update | |||||||||||||||||
23 | Material Selection Process Input Table | 0000-TPL-PE-0005 | ● | IFD | Required for Material Selection Report | ● | IFD | Update | ||||||||||||||||||
24 | Piping & Instrumentation Diagrams (P&ID) | 0000-TPL-PE-0007 | ● | IFD | Lead Sheets provided by AOC | ● | IFC | ● | IFAB | |||||||||||||||||
25 | Process Description | ● | IFR | ● | IFA | |||||||||||||||||||||
26 | Process Flow Diagrams (PFD) | ● | IFR | Includes utility systems | ● | IFD | Includes utility systems | ● | IFD | Update | ||||||||||||||||
27 | Process Simulation | ● | IFN | HYSYS V7.2 Build 7263 | ● | IFN | HYSYS V7.2 Build 7263 | ● | IFN | HYSYS V7.2 Build 7263 | ||||||||||||||||
28 | Relief Valve Sizing Calculations | ● | IFD | ● | IFC | |||||||||||||||||||||
29 | Utility Balances | 0000-TPL-PE-0003 | ● | IFR | ● | IFD | ● | IFD | Update | |||||||||||||||||
30 | Piping / Pipeline | ● | ● | ● | ● | |||||||||||||||||||||
31 | Development Area Plan | ● | IFR | ● | IFD | ● | IFC | |||||||||||||||||||
32 | Heat Tracing Schedules and General Arrangements | ● | IFC | |||||||||||||||||||||||
33 | Hydro Test Plan | ● | IFA | ● | IFD | |||||||||||||||||||||
34 | Isometric Drawings | ● | IFC | |||||||||||||||||||||||
35 | Line Designation Table (LDT) | 0000-TPL-PE-0001 | ● | IFD | ● | IFC | ● | IFAB | ||||||||||||||||||
36 | Pipeline Alignment Drawings | ● | IFD | ● | IFC | ● | IFAB | |||||||||||||||||||
37 | Pipeline Bend Schedule | ● | IFD | ● | IFC | |||||||||||||||||||||
38 | Pipeline Crossing Plan (incl. drawings and crossing list) | ● | IFR | ● | IFD | ● | IFC | |||||||||||||||||||
39 | Pipeline Elevation/Profile Drawings | ● | IFD | ● | IFC | ● | IFAB | |||||||||||||||||||
40 | Pipeline Loop Detail | ● | IFR | Typical | ● | IFD | ● | IFC | ||||||||||||||||||
41 | Pipeline Material Take-off (MTO) | ● | IFE | Length, diameter, crossings | ● | IFE | ● | IFE | ||||||||||||||||||
42 | Pipeline ROW Cross-section | ● | IFR | ● | IFD | ● | IFC | |||||||||||||||||||
43 | Pipeline Shoe Drawings | ● | IFD | Typicals | ● | IFC | ||||||||||||||||||||
44 | Pipeline Specifications (CSA) | ● | IFD | As required | ● | IFC | ||||||||||||||||||||
45 | Pipeline Summary Map/Table | ● | IFR | ● | IFD | ● | IFD | Update | ● | IFAB | ||||||||||||||||
46 | Piping Material Take-off (MTO) | ● | IFE | ● | IFE | |||||||||||||||||||||
47 | Plot Plan | ● | IFR | ● | IFD | ● | IFC | ● | IFAB | |||||||||||||||||
48 | Stress Analysis | ● | IFA | Identification of lines to be analyzed | ● | IFD | ||||||||||||||||||||
49 | Tie-in List | 0000-TPL-PE-0008 | ● | IFD | ● | IFC | ● | IFAB | ||||||||||||||||||
50 | 3-D Model - 30% | ● | IFA | Primarily used for MTO purposes | ● | IFD | Update | |||||||||||||||||||
51 | 3-D Model - 60% | ● | IFD | |||||||||||||||||||||||
52 | 3-D Model - 90% | ● | IFC | ● | Updated as changes made | |||||||||||||||||||||
53 | Mechanical | ● | ● | ● | ● | |||||||||||||||||||||
54 | Equipment and Material Requisition | ● | IFD | Long lead items | ● | IFD | ||||||||||||||||||||
55 | Equipment Data Sheets | ● | IFR | Major Equip., process data only | ● | IFD | ● | IFC | Includes HVAC and specialty items | ● | IFAB | |||||||||||||||
56 | Equipment List | 0000-TPL-ME-0001 | ● | IFR | Major equipment only | ● | IFD | ● | IFD | ● | IFAB | |||||||||||||||
57 | HVAC Drawings | ● | IFC | |||||||||||||||||||||||
58 | Long Lead Items List (i.e., purchased prior to sanction) | ● | IFR | Includes instrumentation | ● | IFD | Includes instrumentation | |||||||||||||||||||
59 | Material Selection Diagrams (MSD) | ● | IFD | ● | IFD | Update | ||||||||||||||||||||
60 | Cathodic Protection Plan | ● | IFR | ● | IFA | |||||||||||||||||||||
61 | Cathodic Protection Drawings | ● | IFD | ● | IFC | |||||||||||||||||||||
62 | Material Selection Report | ● | IFR | Summary to support estimate | ● | IFD | ● | IFD | Update | |||||||||||||||||
63 | Speciality Items List | 0000-TPL-ME-0002 | ● | IFD | ● | IFD | Update | ● | IFAB | |||||||||||||||||
64 | Civil / Structural | ● | ● | ● | ● | |||||||||||||||||||||
65 | Berm, Pond and Drainage Drawings | ● | IFD | ● | IFC | ● | IFAB | |||||||||||||||||||
66 | Building List | ● | IFR | Major buildings only | ● | IFD | ● | IFD | ||||||||||||||||||
67 | Civil Material Take-off (MTO) | ● | IFR | Preliminary for Class 4 cost estimate | ● | IFE | ● | IFE | ||||||||||||||||||
68 | Earthwork Model | ● | IFN | ● | IFN | |||||||||||||||||||||
69 | Foundation / Pile Layout Drawings | ● | IFD | ● | IFC | ● | IFAB | Pile layout drawings only | ||||||||||||||||||
70 | Geotechnical Investigation | ● | IFR | For site selection | ● | IFA | Follow-up as required | |||||||||||||||||||
71 | Pit and Sump Drawings | ● | IFN | Typicals only | ● | IFC | ||||||||||||||||||||
72 | Road Plan / Profile Drawings | ● | IFR | Preliminary for Class 4 cost estimate | ● | IFD | Preliminary | ● | IFC | ● | IFAB | |||||||||||||||
73 | Survey Plan / Drawings | ● | Preliminary sketch plans | ● | Legal survey | ● | Update | ● | IFAB | |||||||||||||||||
74 | Site Clearing, Grading and Drainage Plan | ● | IFR | Preliminary for Class 4 cost estimate | ● | IFD | ● | IFC | ● | IFAB | ||||||||||||||||
75 | Structural Drawings (including Pipe supports) | ● | IFN | Typicals only | ● | IFC | ||||||||||||||||||||
76 | Structural Material Take-off (MTO) | ● | IFE | Preliminary steel quantities for the Class 3 estimate | ● | IFE | ||||||||||||||||||||
77 | Structural Model | ● | IFN | |||||||||||||||||||||||
78 | Electrical | ● | ● | ● | ● | |||||||||||||||||||||
79 | Area Classification Drawing | ● | IFD | Includes area classification worksheet | ● | IFC | ● | IFAB | ||||||||||||||||||
80 | Cables Schedules | ● | IFD | Preliminary based on plot plans | ● | IFC | ||||||||||||||||||||
81 | Control Equipment Layout in MCC's | ● | IFD | ● | IFC | |||||||||||||||||||||
82 | Electrical Equipment Data Sheets | ● | IFD | Major equipment only | ● | IFC | ● | IFAB | ||||||||||||||||||
83 | Electrical Equipment List | ● | IFD | ● | IFD | ● | IFAB | |||||||||||||||||||
84 | Electrical Load List | ● | IFR | Estimated total load | ● | IFD | Includes standy-by loads and EHT | ● | IFD | Update | ● | IFAB | ||||||||||||||
85 | Electrical Material Take-off (MTO) | ● | IFE | ● | IFE | |||||||||||||||||||||
86 | Fugitive Emissions Study | ● | IFA | Required for Area Classification | ||||||||||||||||||||||
87 | I/O List | ● | IFD | ● | IFC | ● | IFAB | |||||||||||||||||||
88 | MCC Building Layout | ● | IFD | ● | IFC | |||||||||||||||||||||
89 | Power System Study Report | ● | IFR | ● | IFA | Load flow, short circuit, motor starting | ||||||||||||||||||||
90 | Single Line Diagrams | ● | IFD | ● | IFC | ● | IFAB | |||||||||||||||||||
91 | Typical LV Motor Schematic | ● | IFN | ● | IFN | |||||||||||||||||||||
92 | Typical MV Motor Schematic | ● | IFN | ● | IFN | |||||||||||||||||||||
93 | Instrumentation and Control | ● | ● | ● | ● | |||||||||||||||||||||
94 | Control Narrative | ● | IFD | AOC scope | ● | IFAB | ||||||||||||||||||||
95 | Control Philosophy | ● | IFR | AOC scope | ● | IFD | AOC scope | |||||||||||||||||||
96 | Control System Engineering & Design | ● | IFD | AOC scope, estimates only | ● | IFD | AOC scope | |||||||||||||||||||
97 | I&C Material Take-off (MTO) | ● | IFE | ● | IFE | |||||||||||||||||||||
98 | I/O Assignment General & Packaged Equipment | ● | IFC | Including HVAC | ||||||||||||||||||||||
99 | Installation Detail Drawings | ● | IFC | |||||||||||||||||||||||
100 | Instrument Data Sheets | ● | IFD | Preliminary | ● | IFC | ● | IFAB | ||||||||||||||||||