Actual Master Schedule of Premier Parc Project
2
3
ItemsDurationDate as ScheduleDate ActualCheckNotesStatus20192020202120222023
4
78910111212345678910111212345678910111212345678910111212345
5
Legal ProcessEIAR45 days
6
8/7/20208/7/2020OKdone
5/20 EIAR Submission
2020-07-152020-08-07
7
Certificate of Land Use Right
8
8/31/20208/22/2020OKdone1/9/20202020-07-312020-08-31
9
Approval on Investment Policy
(Get the confirmation from MOC/DOC)
10
8/31/2020pending/ may be needed or not neededpending11/11/20192020-04-27
5/19 HPC Report
2020-07-312020-08-31
11
Drainage system, water supply, power supply, comunication connections14 days
12
2020-8/1~158/19/2020OK1.2020.08.19-1538 UBND-QLDT Dau noi giao thong va thoat nuoc DA DM1 thuoc tuyen duong To Huu-Van Phuc
Letter No. 428.CTN-KH on Supplying Water from Hadong water supply company - 191227
Letter No. 02.BB-PC Agreement on supplying electricity with NTL electricity company - 200102
Comunications INFRA no need, need developer to supervise INFRA contractor.
done2020-8/1~15
13
Project Assignment (FLC → JSC)
14
10/31/2020ongoing2020-08-012020-10-31
15
Transfer of LURC (FLC JSC)15 days
16
2020-11/1~30ongoing
2020-11/1~30
17
InfraDesignInfra & Low-rise
Geological Survey
30 days
18
1/18/20201/18/2020OKneed stamped copiesdone12/20/20191/18/2020
19
High-rise
Geological Survey
35 days
20
3/8/2020check status2020-02-032020-03-08
21
Basic Design150 days
22
1/21/20201/21/2020OKdone8/25/20191/21/2020
23
Construction Design59 days
24
4/21/20204/21/2020OKdone2020-02-222020-04-21
25
ApprovalBD Verification15 daysapproved 28/7/2020, FLC got 20/8/2020
26
3/26/20203/23/2020OKReport No. 233/2020/BCTT-IPCVIETdone2020-02-222020-03-26
27
Fire Fighting47 days
28
9/15/2020KhaiHoan contract 19/8/2020ongoing2020-06-232020-08-082020-09-15
29
BD Approvalwhen can get BD stamped
30
9/8/20208/20/2020OKDoc No. 415/HDXD-QLDA 28/7/2020, received 20/8/2020. Need hardcopies stampeddone2020-03-272020-08-152020-09-08
31
CD Verification15 days
32
9/23/2020printing for submission ( hard copies by Aug. 15 days wait for approvalongoing
Pre-verification before getting BD approval as to FLC's information
2020-08/16~31
2020-09-23
33
CD Approval30 days
34
10/22/2020
2020-09/1~30
2020-10-22
35
Construction Permit15 days
36
11/7/2020
2020-10/1~15
2020-11-07
37
Construction180 days
38
39
40
5/15/20212020-10-162020-11-152021-04-152021-05-15
41
Low-riseDesignConcept Design10 days
42
2020-01-13~22
1/22/2020OK
2020-01-13~22
43
Basic Design65 daysverifying/ printing in week 19/8 ( printing Tuesdays), need 10days to approve from MoC
44
7/22/20207/22/2020OK1/13/20202020-04-102020-07-22
45
Construction Design60 days
46
9/30/20202020-07-222020-09-30
47
Landscape15 days
48
8/15/2020
2020-7/16~31
2020-08-15
Nam Song Hong: ( CX1/CX2/ shophouse)
49
ApprovalBD Verification30 days
50
8/25/2020check status ( planing as Mr. Sy informed in 25/8 finished prting to provide by VinaCoring), neeed architectrural plan approval by Nam Tu Liem PMU (Mr. Quan) prior to approve BD.2020-07-162020-08-25
51
BD Approval30 days
52
9/25/20202020-08-162020-09-25
53
CD Verification20 days
54
10/20/20202020-09-212020-10-20
55
CD Approval30 days
56
11/20/20202020-10-112020-11-20
57
Construction Permit15 days
58
12/10/2020
2020-11/11~25
2020-12-10
59
Construction150 days
villa construction period is 15M ( depend on selling plan )
60
3/15/2022
villa construction Period is 10M if all villa is constructed at the same time
61
480 days2020-12-162022-03-15
62
63
Club
House
DesignConcept Design10 days
64
8/10/2020
2020-01-13~22
2020-06-222020-07-102020-08-10
65
Basic Design25 days
66
2020-8/11~311/13/2020
2020-7/11~31
2020-8/11~31
Nhà văn hóa: check whether JV to operate this house or to handover to local government
67
Construction Design60 days
68
10/30/20202020-08-012020-09-202020-10-30
69
ApprovalBD Verification30 days
70
9/15/20202020-8/1~152020-09-15
71
Fire Fighting45 days
72
10/15/20202020-07-252020-09-152020-10-15
75
BD Approval30 days
76
10/15/20202020-08-162020-09-152020-10-15
77
CD Verification20 days
78
10/30/20202020-09-212020-10-30
79
CD Approval30 days
80
11/30/20202020-10-112020-11-30
81
Construction Permit15 days
82
12/15/2020
2020-11/11~26
2020-12-15
83
Construction
84
85
480 days2020-12-162021-12-25
86
12/25/2021
87
High-riseDesignBasic Design75 days
88
3/9/20212020-11-012021-01-152021-03-09
89
Construction Design30 days
90
2021-5/1~312021-5/1~31
91
Landscape15 days
92
2021-4/1~152021-4/1~15
93
ApprovalBD Verification20 days
94
2021-3/10~31
2021-3/10~31
95
Fire Fighting75 days
96
4/14/20202020-01-152020-04-14
99
BD Approval30 days
100
2021-4/1~302021-4/1~30
101
CD Verification20 days
102
2021-6/1~202021-6/1~20
103
CD Approval30 days
104
7/20/20212021-06-212021-07-20