B | C | D | F | G | H | I | J | K | L | M | N | O | P | Q | R | S | T | U | V | W | X | Y | Z | AA | AB | AC | AD | AF | AG | AH | AI | AJ | AK | AL | AM | AN | AO | AP | AQ | AR | ||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1 | Country | Hydropower plant name | River | Community; District | Type: Existing before 2005/Rehabilitation/Conversion/Greenfield (built or planned after 2005)/Cancelled/Duplicate/Unclear/Additional row: Multiple financing sources | Location co-ordinates (WGS84) | Name of the protected/high biodiversity value area | Protection/Recognition status | Inside protected area / Outside protected area with direct impact | Existing capacity (MW) | Predicted additional capacity (MW) | Generation in MWh | Project sponsor | Investor | Investor Country | Ultimate owner of investor | Public/Private | No of hydros in cascade or concession | Date of concession | Length of concession (years) | Concession End Date | Subcontractors/Consultants | Development phase (potential, planned; offered for investment; concession awarded; under construction; operational<5years; operational 5-10years; operational>10years; cancelled, unclear) | Date when put into operation | Total project costs - Currency | Total project costs - Amount (mil.) | Total project costs - EUR equivalent (mil.) | Financed by own resources in EUR | MDB finance - Name of MDB | MDB finance - Status (Planned/Approved/Signed/Invested/Completed/Cancelled) | MDB finance - Type | MDB finance (mil. EUR) | Commercial banks - Name | Commercial banks - Status (Planned/Signed/Invested/Completed/Cancelled) | Commercial banks - Amount (in mil. EUR) | Other public financing (special funds, government agencies, regional development banks) - Name of special fund | Other public financing (special funds, government agencies, regional development banks) - Status (Planned/Signed/Invested/Completed/Cancelled) | Other public financing (special funds. government agencies. regional development banks) - Amount (in mil. EUR) | Assistance column construction financing | Remarks | Info Source | |
2 | Albania | Devoll cascade / Banje (also Banja) | Devoll | Banja village; Gostime Commune; Elbasan District | Greenfield | 0.00 | 70 | 255 GWh | Devoll Hydropower Sh.A. | Statkraft AS | Norway | 100% | private | 3 | 2008 | Norplan (Norway), Alstom (France), Sweco (Sweden), AF-Consult Switzerland; Limak Construction Group (Turkey); Norconsult (Norway) | operational<5 | 2016 | EUR | 535 | Not identified | Originally developed under JV between Statkraft and EVN. In March 2013, Norwegian Statkraft AS and Austrian EVN AG signed an agreement by which Statkraft acquired EVN’s 50 percent stake in Devoll Hydropower ShA. Investments in a group company, Statkraft Markets B.V., Amsterdam/Netherlands, were increased by EUR 51.2 million in 2013. The investment in Statkraft Markets B.V. was made to provide financing for a power plant construction by one of its subsidiaries: Devoll Hydropower Sh. A., Tirana/Albania. Workers protests against working conditions in August 2014: http://www.devollhydropower.al/new/?p=8441. This was the second time within 3 months Banja hydropower plant workers protested against low wages and fulfilling the conditions at work. When the decision was taken to boycott work, workers were threatened by police officers called by representatives of the firm "Limak. CDM project "The total investment of the Devoll project is estimated to approximately EUR 500 million" | http://www.statkraft.de/Statkraft/Documents/de/Investor%20Relations/Anual%20Report%202013%20Statkraft%20Markets%20GmbH_Web%20Vers._ENGLISH.pdf; http://www.balkaneu.com/premier-albania-inaugurates-biggest-projects-hydro-power/; https://www.youtube.com/watch?v=SBEivRbz3ec; http://www.devollhydropower.al/new/?page_id=7754; https://cdm.unfccc.int/Projects/DB/DNV-CUK1324294885.32/view; http://www.statkraft.com/media/press-releases/Press-releases-archive/2013/statkraft-aquires-evns-shares-in-devoll-hydropower-sha/; http://tr.ebrd.com/tr13/index.php/en/country-assessments/1/albania; http://www.limak.com.tr/sectors/construction/projects/dams http://balkangreenenergynews.com/statkraft-opened-its-first-hydropower-plant-in-albania/ | |||||||||||||||||||
3 | Albania | Ashta 2 (former Bushati) | Drin | Shkoder | Greenfield | Buna River – Velioja Protected landscape | National strict protected area Emerald | Inside | 32.20 | 0 | Energji Ashta Shpk | Verbund; EVN AG | Austria | Republic of Austria (51%) | private | 2 | 2008 | 35 | Austrian Hydro Power AG (Austria); Poyry (Finland); Andritz Hydro (Austria); Porr AG (Austria) | operational 5-10 | 2012 | 160 | EUR | Multilateral Investment Guarantee Agency (MIGA) | Signed | guarantee | 121.40 | BAWAG P.S.K. Bank | Completed | 140 | Yes | In February 2001, Albania’s power utility KESH contracted the China Water & Electricity Corporation (CWE) to build a HPP at Bushati, on a turnkey basis. The CWE plan would affect the levels of Lake Shkodra. In August 2001, the government suspended the CWE contract for an independent assessment of the plan’s technical, environmental, financial, and economic feasibility by the German engineering firm Lahmeyer International. In 2001 the Export-Import Bank of China (China Exim Bank) pledged to provide buyer's credit worth more than US$100 million for Bushati HPP. CDM project Original currency MDB finance: 159.4 mil. USD The overall volume of €140 million will be borne equally between VERBUND International Finance B.V. and BAWAG PSK Bank für Arbeit und Wirtschaft und Österreichische Postsparkasse Aktiengesellschaft, and the sub-participating banks Raiffeisen Landesbank Oberösterreich Aktiengesellschaft and Kommunalkredit Austria Aktiengesellschaft. The term will be ten years. On July 15, 2013, the Company received a new loan from Raiffeisen Bank International for a sum of 70 million Euro and slammed the debt with Bawag P.S.K Bank for the same amount. New borrowing holds the variable interest rate, currently 3.38%. Borrowing is payable in thirty-five quarterly installments starting on October 15, 2013. On the same date, another borrowing agreement with the same terms and conditions were signed with Verbund International Finance GmbH. Loans are jointly guaranteed by the respective Groups owned by the Owner of the Company, and for these guarantees the Company pays them, a 2% charge on the remaining loan amount. | Verbund Annual Financial Report 2011-2012; http://www.miga.org/projects/index.cfm?pid=1052; http://media-newswire.com/release_1074872.htmlů http://www.premiereservices.al/assets/vendor/pdf/HEC.pdf; https://openknowledge.worldbank.org/bitstream/handle/10986/10545/488270BRI0IFCS1hta0Hydropower1FINAL.pdf?sequence=1; http://www.chinadaily.com.cn/epaper/html/cd/2001/200102/20010209/20010209005_3.html; https://cdm.unfccc.int/filestorage/U/8/1/U81WCZ9ARPBNQMEI64DSY5O2K3VLHF/5662%201%20Revised%20PDD.pdf?t=S2h8bnA5bGVtfDD8wfJ3Dgz3vAoVdI9zix5c http://www.energji-ashta.al/?id=21&l=17 | |||||||||
4 | Albania | Ashta 2 (former Bushati) | Drin | Shkoder | Additional row: Multiple financing sources | Buna River – Velioja Protected landscape | National strict protected area Emerald | Inside | Energji Ashta Shpk | Verbund; EVN AG | operational 5-10 | International Finance Corporation (IFC) | Completed | advisory services | Yes | http://www.ifc.org/wps/wcm/connect/27748785-ef2c-45f4-add0-2bd0094ef342/PPPStories_Albania_AshtaHydropower.pdf?MOD=AJPERES | ||||||||||||||||||||||||||
5 | Albania | Badelonje | Vjosa | Greenfield | Germenj-Shelegure-Leskovic-Piskal park | National strict protected area | Outside | 0.00 | 30 | not identified | not identified | potential | None | HPP is just outside the protected area but impoundment will influence Emerald site (Germenj-Shelegure-Leskovic-Piskal park) | http://energjia.al/2014/05/17/a-ja-vlen-te-sakrifikojme-vjosen, http://www.ecoalbania.org/wp-content/uploads/2017/05/HPPs_al_final-report_me-kapak.pdf | |||||||||||||||||||||||||||
6 | Albania | Bele-Topojan concession / Bele 2 | Luma | Bele; Kukes | Greenfield | 0.00 | 11 | "Alb-Energy" shpk | KADRIA 23.66%, ALB-BUILDING 76.34% | private | 5 | 2008 | 35 | Cheng Hsiung International (China), Hydro Energia (Italy) | operational<5 | 2015 | see Bele 1 | Not identified | On 23.4.2015 electricity productionlicense transferred from Alb-Energy shpk to Euron Energy Group shpk for Bele 2 and Topojan 1 Long term loan registered - ALL 502429166 in 2015. Short term part of the long term loan - ALL 133260343 . Overdraft at Raiffesen bank - ALL 191405 Later in 2016, the loan taken from Raiffesen bank. | http://mobile.ikub.al/LIGJE/Per-miratimin-e-kontrates-se-Koncesionit-te-formes-Bot-Te-lidhur-ndermjet-ministriSe-se-Ekonomise-Tregtise-dhe-Energjetikes-dhe-bashkimit-te-shoqerive-euron-shpk-Kadria-shpk-dhe-; http://ppi-re.worldbank.org/data/project/euron-kukes-hpp-6658Teuta-konstruksion-shp-812030044.aspx?cookiesEnabled=false; https://it-it.facebook.com/hydroenergiaitalia/posts/330282740444590; http://www.ere.gov.al/doc/VENDIM_NR.54_2015-1.pdf http://www.qkb.gov.al/umbraco/Surface/SearchSurface/DownloadDocument?documentCode=7DA9ADF0-455F-43D7-BC14-14E3FBB94F77 | ||||||||||||||||||||||
7 | Albania | Beleshova cascade / Belesova 1 (also Belesove 1) | Belesoves | Berat | Greenfield | 0.00 | 0.28 | Korkis-2009 shpk | not identified | private | 2 | 2009 | operational<5 | 2012 | ProCredit Bank (Albania) | Invested | Yes | Litigation case at the Tirana civil court in April 2015: Ramazan Toska; Aurel Toska; Shoqeria Belesova 1 Sh.p.k.; Shoqeria Silva 2003 Sh.p.k.; Shoqeria Korkis Sh.p.k. / Shoqeria Permbarimore Private Executores Litium Sh.p.k; Procredit Bank Sh.a.; Z.V.R.P.P. Tirane; Av. Shtetit | http://ere.gov.al/doc/ere_annual_report_2011_en_web.pdf; https://webcache.googleusercontent.com/search?q=cache:3jNJs_kLn0UJ:gjykataeapelittirane.al/%3Ffq%3Dkerkim%26gj%3D%26menu%3D2%26kid%3D13%26start%3D12760+&cd=1&hl=en&ct=clnk&gl=cz, http://www.albeiti.org/regjistri-i-koncensioneve-hidroenergjitike/ | |||||||||||||||||||||||
8 | Albania | Bishnica cascade / Bishnica 2 | Bishnice | Pogradec | Greenfield | 2.40 | 0 | HEC Bishnica 1,2 shpk | not identified | private | see Bishnica 1 | 2008 | 35 | GUGLER Water Turbines GmbH (Austria) | operational 5-10 | 2010 | Not identified | http://www.ere.gov.al/doc/V_E_N_D_I_M_23.2010.pdf, http://www.albeiti.org/regjistri-i-koncensioneve-hidroenergjitike/ | ||||||||||||||||||||||||
9 | Albania | Bleteza | Seman | Gramsh | Greenfield | 0.00 | Claubel sh.pk | not identified | private | planned | N/A | None | http://www.rtklive.com/sq/news-single.php?ID=159411 | |||||||||||||||||||||||||||||
10 | Albania | Bogova (also Bogove or Bogoves) (Wonder Power) | Bogova | Skrapar | Rehabilitation | Regional Park | Other protected area | Inside | 2.50 | 0 | Wonder Power shpk | not identified | private | operational>10 | 1988 | Not identified | Wonder Power Sh.A was advised by Haxhia & Hajdari attorneys in regard of a conflict between shareholders. Mr. Sadik Llapashtica - AdministratorWonder Power sha.a September 2003 – March 2014 | http://www.chambersandpartners.com/europe/firm/161201/haxhia-hajdari; https://al.linkedin.com/pub/sadik-llapashtica/3a/1a8/320; http://en.wonder-sha.com/rreth-nesh-2/; https://cdm.unfccc.int/filestorage/q/v/UVZTEC5X7L1JRNS09PYABQM6WH3F24.pdf/PDD.pdf?t=NE98bnA5bW84fDAr54gQFSu8W0HfXct1TF2f, http://www.albeiti.org/regjistri-i-koncensioneve-hidroenergjitike/, https://www.wbif.eu/content/stream//Sites/website/library/WBEC-REG-ENE-01-BR-1-Role-of-hydropower-04.12b.pdf, http://www.ere.gov.al/doc/rap_vjet_2009_derguar_ne_kuvend.pdf | ||||||||||||||||||||||||
11 | Albania | Bratila 1 | Devoll | Greenfield | 0.00 | 115 | none yet | none yet | potential | N/A | None | http://aea-al.org/wp-content/uploads/2014/07/study_on_assessment_of_res_potentials_in_albania.pdf, http://www.politiko.al/2017/07/potencialet-e-reja-per-energji-nga-uji-era-dhe-dielli/#http://www.politiko.al/wp-content/uploads/2017/07/energjia.jpg | ||||||||||||||||||||||||||||||
12 | Albania | Bushtrica concession / Bushtrica 1 (also Bushtrice) | Caje | Librazhd | Greenfield | Shebenik-Jabllanice National Park | National Park Other protected area | Inside | 0.00 | 4.2 | Doko sh.pk | not identified | private | 2017 | concession awarded | N/A | None | Concession for Bushtrica 1 previously recorded as being held by Fatjon shpk.; Spahiu Gjanc shpk;, Ani shpk; Keanxho shpk; Fusha shpk.; Avel shpk; IRZ shpk; Construction Management Alleance Albania shpk; 2A Power obtained in 2009, assumed it is the same plant but with a new tender. Only Bustrica 1 announced as having a new concessionaire, not others in the cascade. | http://aea-al.org/albanias-shala-river-is-also-granted-concession-hpp-100-million-usd-investment/, http://www.albeiti.org/wp-content/uploads/2016/02/Regjistri-i-kocensioneve-n%C3%AB-sektorin-e-hidroenergjitik.pdf, http://open.data.al/sq/corporates/view/id/REF-09833- | |||||||||||||||||||||||
13 | Albania | Borjes cascade / Cernaleve | Borjes | Cernaleve; Kukes | Duplicate | not identified | not identified | 4 | 2009 | operational<5 | Unclear | Not identified | Possibly duplicate with Cernaleve 1 and 2 | http://www.albeiti.org/regjistri-i-koncensioneve-hidroenergjitike/ | ||||||||||||||||||||||||||||
14 | Albania | Curraj-Epshem | Curraj | Tropoje | Existing | Curraj | Other protected area (protected landscape or nature monument) | Inside | not identified | not identified | operational>10 | 1969 | N/A | https://www.wbif.eu/content/stream//Sites/website/library/WBEC-REG-ENE-01-BR-1-Role-of-hydropower-04.12b.pdf | ||||||||||||||||||||||||||||
15 | Albania | Dishnice | Dishnica | Dishnice; Korce | Greenfield | 0.20 | Dishnica Energy shpk (also Dishnica Energji shpk) | not identified | private | 1 | 2009 | Cheng Hsiung International Corporation (China) | operational 5-10 | 2010 | Not identified | http://www.ere.gov.al/doc/Annual_Report_2010_ENG.pdf | ||||||||||||||||||||||||||
16 | Albania | Dragobia (also Dragobi) (old) | Valbona | Valbone; Tropoje | Existing | Valbona Valley National Park | National park | Inside | not identified | not identified | operational>10 | 1969 | N/A | https://www.wbif.eu/content/stream//Sites/website/library/WBEC-REG-ENE-01-BR-1-Role-of-hydropower-04.12b.pdf | ||||||||||||||||||||||||||||
17 | Albania | Dragot-Tepelena (Dragoti) | Vjosa | Tepelene | Greenfield | Vjosa | Other protected area (protected landscape or nature monument) | Inside | 0.00 | 130 | none yet | none yet | potential | N/A | Not identified | The HPP is to impact the Uji I Ftohte-Tepelene Nature Monument and the Zheji Natural Park. | http://aea-al.org/wp-content/uploads/2014/07/study_on_assessment_of_res_potentials_in_albania.pdf, http://www.monitor.al/soegrah-ja-25-hec-et-qe-propozohen-te-ndertohen-ne-vjose-kapaciteti-458-mw/, http://www.politiko.al/2017/07/potencialet-e-reja-per-energji-nga-uji-era-dhe-dielli/#http://www.politiko.al/wp-content/uploads/2017/07/energjia.jpg | |||||||||||||||||||||||||
18 | Albania | Dukagjin cascade / Dukagjin 1 | Shala | Shkoder | Duplicate | not identified | not identified | Not identified | See Shale cascade • In 2007 the consortium comprised of Interenergo Albania shpk presented the government with the feasibility studies for "Dukagjin 1", "Dukagjini 2" and "Dukagjini 3" as an unsolicited proposal. • Through Decision no. 757, dated 07.11.2007 "On the definition of contracting authority for the construction of hydropower stations" Dukagjin 1 "," 2 Dukagjini "and" Dukagjini 3 ", the Council of Ministers decided to start the bidding procedures for the project proposed by the Concessionaire. Through the decision no. 757, dated 07.11.2007 the Contracting Authority invited the participants to submit their offers for the use of all Shala River, without limiting the number of the plants that will be built. • Following the completion of further studies on the economic, technical and environmental construction and operation of cascade hydropower plants in Shale River, concessionaire has submitted its bid dated 22.04.2008, proposing the construction of six (6) hydropower plants on the river Shale and the end of the competitive selection procedure has been rated as the best bidder. • Concession for Shala river cascade was awarded based on the unsolicited proposal procedure. • A concessionary contract dated the 2nd June, 2009 between the Ministry of Economy, Trade and Energy of the Republic of Albania, and the Contractor in the form of “BOT” for the Construction of works comprising the Design, Financing, Construction, Ownership, Operation, Maintenance and Transfer of a Hydro-power Plant Cascade on Shala River, Republic of Albania Concession failure penalties: Penalty holder: concessionare for the construction of the HPPs Gur Dukagjin 1 and Dukagjin 2; name blacked out in the document Total penalty amount:185,385,187 Currency:LEK Reason:"pay the penalty by the concessionaire for a term not dorёzim the project / implementation in amount LEK 185,385,187 (242,275,519 0.005% x 10 LEK x 362 days)" Penalty issued: December 2012 | http://renewables.seenews.com/news/albania-licenses-22-hpps-as-producers-of-renewable-energy-351682; http://www.klsh.org.al/web/pub/ministrin_e_ekonomis_441_1.pdf; http://www.energjia.gov.al/files/userfiles/Strategjike/Lista_totale_e_HEC-eve_ne_prodhim_deri_fund_2014.pdf; http://www.qbz.gov.al/doc.jsp?doc=docs/Vendim%20Nr%20698%20Dat%C3%AB%2011-06-2009.htm, http://www.albeiti.org/regjistri-i-koncensioneve-hidroenergjitike/ | ||||||||||||||||||||||||||||||||
19 | Albania | Dukagjin cascade / Dukagjin 2 | Shala | Shkoder | Duplicate | not identified | not identified | Not identified | See Shale cascade • In 2007 the consortium comprised of Interenergo Albania shpk presented the government with the feasibility studies for "Dukagjin 1", "Dukagjini 2" and "Dukagjini 3" as an unsolicited proposal. • Through Decision no. 757, dated 07.11.2007 "On the definition of contracting authority for the construction of hydropower stations" Dukagjin 1 "," 2 Dukagjini "and" Dukagjini 3 ", the Council of Ministers decided to start the bidding procedures for the project proposed by the Concessionaire. Through the decision no. 757, dated 07.11.2007 the Contracting Authority invited the participants to submit their offers for the use of all Shala River, without limiting the number of the plants that will be built. • Following the completion of further studies on the economic, technical and environmental construction and operation of cascade hydropower plants in Shale River, concessionaire has submitted its bid dated 22.04.2008, proposing the construction of six (6) hydropower plants on the river Shale and the end of the competitive selection procedure has been rated as the best bidder. • Concession for Shala river cascade was awarded based on the unsolicited proposal procedure. • A concessionary contract dated the 2nd June, 2009 between the Ministry of Economy, Trade and Energy of the Republic of Albania, and the Contractor in the form of “BOT” for the Construction of works comprising the Design, Financing, Construction, Ownership, Operation, Maintenance and Transfer of a Hydro-power Plant Cascade on Shala River, Republic of Albania Concession failure penalties: Penalty holder: concessionare for the construction of the HPPs Gur Dukagjin 1 and Dukagjin 2; name blacked out in the document Total penalty amount:185,385,187 Currency:LEK Reason:"pay the penalty by the concessionaire for a term not dorёzim the project / implementation in amount LEK 185,385,187 (242,275,519 0.005% x 10 LEK x 362 days)" Penalty issued: December 2012 | http://www.klsh.org.al/web/pub/ministrin_e_ekonomis_441_1.pdf; http://www.qbz.gov.al/doc.jsp?doc=docs/Vendim%20Nr%20698%20Dat%C3%AB%2011-06-2009.htm, http://www.albeiti.org/regjistri-i-koncensioneve-hidroenergjitike/ | ||||||||||||||||||||||||||||||||
20 | Albania | Dukagjin cascade / Dukagjin 3 | Shala | Shkoder | Duplicate | not identified | not identified | Not identified | See Shale cascade • In 2007 the consortium comprised of Interenergo Albania shpk presented the government with the feasibility studies for "Dukagjin 1", "Dukagjini 2" and "Dukagjini 3" as an unsolicited proposal. • Through Decision no. 757, dated 07.11.2007 "On the definition of contracting authority for the construction of hydropower stations" Dukagjin 1 "," 2 Dukagjini "and" Dukagjini 3 ", the Council of Ministers decided to start the bidding procedures for the project proposed by the Concessionaire. Through the decision no. 757, dated 07.11.2007 the Contracting Authority invited the participants to submit their offers for the use of all Shala River, without limiting the number of the plants that will be built. • Following the completion of further studies on the economic, technical and environmental construction and operation of cascade hydropower plants in Shale River, concessionaire has submitted its bid dated 22.04.2008, proposing the construction of six (6) hydropower plants on the river Shale and the end of the competitive selection procedure has been rated as the best bidder. • Concession for Shala river cascade was awarded based on the unsolicited proposal procedure. • A concessionary contract dated the 2nd June, 2009 between the Ministry of Economy, Trade and Energy of the Republic of Albania, and the Contractor in the form of “BOT” for the Construction of works comprising the Design, Financing, Construction, Ownership, Operation, Maintenance and Transfer of a Hydro-power Plant Cascade on Shala River, Republic of Albania | http://www.qbz.gov.al/doc.jsp?doc=docs/Vendim%20Nr%20698%20Dat%C3%AB%2011-06-2009.htm | ||||||||||||||||||||||||||||||||
21 | Albania | Dunice HPPS cascade / Dunice | Kalivac/Dolisti or Dunice | Greenfield | 2.87 | Hec Dunice shpk | not identified | private | 5 | 2009 | concession awarded | N/A | Not identified | HEC-i DUNICE Shpk was a plaintiff in a 22.07.2013 litigation case involving Ministry of Economy, Trade and Energy and Trebinje community demanding indemnification for cancelling the concession contract. Concession failure penalties: Penalty holder: concessionare for the construction of the HPPs Trebinja 1, Trebinja 2, Potgozhan, Kalivac and Dunice; name blacked out in the document Total penalty amount:see Trebinje 1 Currency:see Trebinje 1 Reason:pay LEK 11,939,820 (00:05% x 175,585,602 ALL (value from the investment without committing x 136 day (for the period 17/08/2011 to 31/12/2011) Penalty issued: December 2012 | http://www.albeiti.org/regjistri-i-koncensioneve-hidroenergjitike/, http://www.azht.gov.al/files/news_files/Dokumenti_i_rregullores_i_miratuar_vendimi_nr_2.pdf, http://www.ere.gov.al/doc/Njoftim_09.02.2018.pdf | |||||||||||||||||||||||||||
22 | Albania | Gostime cascade / Egnatia Shushice | Gostime (also Gostima) | Librazhd | Greenfield | Regional Park | Other protected area | Inside | 65.63 | Vëllezërit Tola; Arti shpk; GPA Konstruksion shpk | not identified | private | 11 | 2013 | Cheng Hsiung International Corporation (China) | concession awarded | N/A | Not identified | The former Prime Minister, Ilir Meta, was accused by the then Minister of Economy, Dritan Prifti, of asking him to favour a business in the tender procedure for the Egnatia Shushice hydropower concession. As a reward they would be paid with EUR 700,000 and a 7 percent share in the plant. Ilir Meta was also accused of taking a EUR 1 million bribe together with Dritan Prifti for favouring a business in a tender of crude oil. A year after the scandal, the same company involved in the corruption scandal - “Vëllezërit Tola” owned by Agim Rrapaj - won the concession. Gostime river falls under the Managed Nature Reserve. Egnatia Association and a group of specialists have proposed that this area be expanded. Citizens of Gaferr and Sopot villages protesting against construction of HPPS due to the concerns over interference with the Shebenik-Jabllanice National Park. In January 2014 Librazh Municipality annulated concessions for 11 HPPs. the project was offered for investment | http://www.senior-a.al/index.php/wp6-small-grants-to-env-csos-networks/16-newsinformation/wp6-newsinformations/122-vazhdon-shakterrimi-i-lumit-te-gostimes-ne-gaferr-te-librazhdit; http://www.senior-a.al/index.php/wp6-small-grants-to-env-csos-networks/16-newsinformation/wp6-newsinformations/198-librazhd-anullohen-11-hec-e; http://www.arkivalajmeve.com/Ndertimi-i-HEC-it-banoret-e-Zerqanit-vijojne-protestat.1047531326/; https://www.youtube.com/watch?v=X1-tluM4jTs&feature=share; http://top-channel.tv/lajme/artikull.php?id=279549ů http://gazeta-shqip.com/lajme/2012/08/25/mbyllet-pas-5-vjetesh-tenderi-i-video-skandalit/ | ||||||||||||||||||||||
23 | Albania | Elbasan 1 | Unclear | not identified | not identified | unclear | N/A | No information found | ||||||||||||||||||||||||||||||||||
24 | Albania | Drin River cascade / Fierza (also Fierze) | Drin | Tropoja (also Tropoje) | Rehabilitation | 500.00 | Korporata Elektroenergjitike Shqiptare sh.a (KESH) | not identified | public | operational>10 | 1978 | International Development Agency (IDA) | Signed | see Drin River cascade / Komani | Swiss Agency for Development & Co-operation (SDC) | Yes | Rehabilitation of Komani, Fierza and Vau i Dejes HPPS was financed under: 1/ World Bank's Energy Community of South East Europe APL Program – the APL 5 for Albania Dam Safety Project (a part of a larger Dam Safety program financed in parallel by other international financial institutions (IFIs) such as SECO-Switzerland, KfW Germany, the European Bank for Reconstruction and Development (EBRD), and the Government of Albania). 2/ World Bank's DAM SAFETY - ADDITIONAL FINANCING | http://www.worldbank.org/projects/P110481/energy-community-south-east-europe-apl-program-apl-5-albania-dam-safety?lang=enhttps://www.wbif.eu/content/stream//Sites/website/library/WBEC-REG-ENE-01-BR-1-Role-of-hydropower-04.12b.pdf | ||||||||||||||||||||||||
25 | Albania | Drin River cascade / Fierza (also Fierze) | Existing | not identified | not identified | International Bank for Reconstruction and Development (IBRD) | Signed | see Drin River cascade / Komani | Kreditanstalt für Wiederaufbau (KfW) | Yes | https://www.wbif.eu/content/stream//Sites/website/library/WBEC-REG-ENE-01-BR-1-Role-of-hydropower-04.12b.pdf | |||||||||||||||||||||||||||||||
26 | Albania | Drin River cascade / Fierza (also Fierze) | Existing | not identified | not identified | European Bank for Reconstruction and Development (EBRD) | Completed | credit | 1.45 | Yes | https://www.wbif.eu/content/stream//Sites/website/library/WBEC-REG-ENE-01-BR-1-Role-of-hydropower-04.12b.pdf | |||||||||||||||||||||||||||||||
27 | Albania | Gizavesh | Librazhd | Greenfield | Shebenik-Jabllanice National Park | National park | Inside | 0.50 | 0 | Dosku Energy shpk | not identified | private | 2011 | 30 | 27.07.2041 | operational 5-10 | 2011 | Not identified | http://www.ere.gov.al/doc/%281%29ere_annual_report_2011.pdf, http://www.ere.gov.al/doc/Raporti_Vjetor_2016.pdf | |||||||||||||||||||||||
28 | Albania | Gjanc | Osumi or Leshnje | Korce | Rehabilitation | 2.96 | 0 | Spahiu Gjanc shpk. | Mr. Dalip Spahiu | 100% | private | Kossler Gmbh (part of Voith Siemens) (Austria); Schubert Gmbh (Austria); SGA jsc (Albania) | operational>10 | 1991 | Not identified | Built in 1988-1991; put in operation in 1991 as state property administered by KESH. Spahiu-Gjanc Ltd in 2003-2007 invested in the full technical rehabilitation of the hydro power plant and in the 2011 – 2013 in the total rehabilitation and expansion of the 7km long water intake channel Feasiblity study for the expansion of the Gjanc HPP undertaken in February 2012 Financial offer for sale of the Gajnc HPP issued in March 2013 In possible conflict for water with the Gjanci reservoir which ensures irrigation of Korca lowland | http://www.premiereservices.al/assets/vendor/pdf/Finacial-Offer-Gjanc-HPP.pdf; http://www.southeast-europe.net/document.cmt?id=243 | |||||||||||||||||||||||||
29 | Albania | Grabove (also Grabova) | Graboves | Gramsh | Unclear | Agna Group | not identified | private | 12 or 7 or 5 | SGA jsc (Albania) | potential | N/A | 45 | None | SGA jsc part of consortium | http://www.agnagroup.com/new/foto/uploads/File/Projekti%20GRABOVES.pdf | ||||||||||||||||||||||||||
30 | Albania | Gur Shpat cascade / Gur Shpat 1 (Gurshpat 1) | Greenfield | Shkumbin tributary | Other protected area (protected landscape or nature monument) | Inside | 0.80 | 0 | Gurshpate Energy shpk | not identified | private | 2 | 2009 | 35 | operational<5 | 2015 | Not identified | On November 17, 2014, 8 people were charged with the attack against police during the July protests in the village of Polis (Librazhd) against the Gur Shpat 2 HPP. The protesters called for halting the construction of Gur Shpat 1 HPP that has taken away drinking water and water for irrigation. The village has no running water and uses wells. On August 10, 2013 around 600 citizens of Polis and other villages protested against the construction of the second Gur Shpat 2 HPP complaining the project will take away the water supply for subsistance agriculture. They also complained they had not been informed of the concession and the planned developments. Gur shpat 1 was approved by the Municipality in 2006 under the condition that the project moves 15 meters from the irrigation canal. Gur shpat 1 has affected fishermen as it leaves little water in the basin. Allegedly, the Gur Shpat 2 was not approved by the Municipal council. Allegedly, villagers accused of protests against Gur Shpat 2 were left in jail for months without standing a trial, they were beaten and emerged bloodied from prison. Allegedly, the village of Polis had a fund of 35 million LEKE for the construction of a drinking water supply, out of which 4 million LEKE were used for equipment and material. THe project was however suspended. Concession failure penalties: Penalty holder: "concessionare for the construction of the HPPs Gur Shpat 1 and Gur Shpat 2; name blacked out in the document" Total penalty amount: 1,331,000 Currency:LEK Reason:"pay penalty in the amount of 1,331,000 LEK (0.005 % X 176,738,773 LEK x 149 days)" Penalty issued: December 2012 | http://www.arkivalajmeve.com/Nje-HEC-i-dyte-ne-perroin-e-Gur-Shpatit-protestojne-banoret-Ska-uje.1047421181/; https://ekolevizja.wordpress.com/2014/11/17/burg-per-fshataret-qe-mbrojne-ujin/; http://www.klsh.org.al/web/pub/ministrin_e_ekonomis_441_1.pdf, https://www.wbif.eu/content/stream//Sites/website/library/WBEC-REG-ENE-01-BR-1-Role-of-hydropower-04.12b.pdf, http://www.ere.gov.al/doc/Raporti_Vjetor_2016.pdf | |||||||||||||||||||||||
31 | Albania | Gur Shpat cascade / Gur Shpat 2 (Gur Shpat 2) | Greenfield | Shkumbin tributary | Other protected area (protected landscape or nature monument) | Inside | 0.80 | 0 | Gurshpate Energy shpk | not identified | private | see Gur Shpat 1 | 2009 | 35 | operational<5 | 2015 | Not identified | On November 17, 2014, 8 people were charged with the attack against police during the July protests in the village of Polis (Librazhd) against the Gur Shpat 2 HPP. The protesters called for halting the construction of Gur Shpat 1 HPP that has taken away drinking water and water for irrigation. The village has no running water and uses wells. On August 10, 2013 around 600 citizens of Polis and other villages protested against the construction of the second Gur Shpat 2 HPP complaining the project will take away the water supply for subsistance agriculture. They also complained they had not been informed of the concession and the planned developments. Gur shpat 1 was approved by the Municipality in 2006 under the condition that the project moves 15 meters from the irrigation canal. Gur shpat 1 has affected fishermen as it leaves little water in the basin. Allegedly, the Gur Shpat 2 was not approved by the Municipal council. Allegedly, villagers accused of protests against Gur Shpat 2 were left in jail for months without standing a trial, they were beaten and emerged bloodied from prison. Allegedly, the village of Polis had a fund of 35 million LEKE for the construction of a drinking water supply, out of which 4 million LEKE were used for equipment and material. The project was however suspended. Concession failure penalties: Penalty holder: "concessionare for the construction of the HPPs Gur Shpat 1 and Gur Shpat 2; name blacked out in the document" Total penalty amount: see Gur Shpat 1 Reason:"pay penalty in the amount of 1,331,000 LEK (0.005% X 176,738,773 LEK x 149 days)" Penalty issued: December 2012 | http://www.arkivalajmeve.com/Nje-HEC-i-dyte-ne-perroin-e-Gur-Shpatit-protestojne-banoret-Ska-uje.1047421181/; https://ekolevizja.wordpress.com/2014/11/17/burg-per-fshataret-qe-mbrojne-ujin/; http://www.klsh.org.al/web/pub/ministrin_e_ekonomis_441_1.pdf, https://www.wbif.eu/content/stream//Sites/website/library/WBEC-REG-ENE-01-BR-1-Role-of-hydropower-04.12b.pdf, http://www.ere.gov.al/doc/Raporti_Vjetor_2016.pdf | |||||||||||||||||||||||
32 | Albania | Bistrica 1 and 2 cascade / Bistrica 1 | Bistrica | Delvine; Vlore; Saranda | Rehabilitation | 22.50 | Hec Bistrica 1 dhe 2 sha | Kurum International sha (owned by Kurum Holding A.S.) | Turkey | 100 % | private | 2 | 2011 | 30 | 05.12.2041 | operational>10 | 1970 | 106 | International Finance Corporation (IFC) | Signed | credit | see Bistrica 2 | Odeabank, Banka Kombetare Tregtare, Raiffeisen Bank Albania | Invested | Black Sea Trade and Development Bank | 18 (BSTDB); 27 (FMO) | Yes | see Bistrica 2 | http://ifcext.ifc.org/IFCExt/spiwebsite1.nsf/78e3b305216fcdba85257a8b0075079d/ec98d972d9675d2385257b5c005f80b4?opendocument; http://ifcext.ifc.org/IFCExt/Pressroom/IFCPressRoom.nsf/0/DADCA1B9C06638CB85257C4700354AE5; http://www.google.cz/url?sa=t&rct=j&q=&esrc=s&source=web&cd=1&cad=rja&uact=8&ved=0CCAQFjAA&url=http%3A%2F%2Fwww.cao-ombudsman.org%2Fcases%2Fdocument-links%2Fdocuments%2FCAOComplaint.pdf&ei=lWbwVO6iBsGBUeylgYAB&usg=AFQjCNERrqFHwxcns-j_-HjW99xtgkSM9g&sig2=BQtZ7amXYoQbrwvO5xcWuw&bvm=bv.87269000,d.d24; https://webcache.googleusercontent.com/search?q=cache:yNK3GadtiRIJ:www-wds.worldbank.org/external/default/WDSContentServer/WDSP/IB/2013/05/27/000445729_20130527123345/Rendered/INDEX/751730AR0Alban0Box0377295B00PUBLIC0.txt+&cd=14&hl=en&ct=clnk&gl=cz; http://www.offene-entwicklungshilfe.de/sector/71/230/; http://telegraf.al/aktualitet/pas-privatizimit-kurum-heq-nga-puna-punonjesit-e-hec-eve-bistrica-1-dhe-2 | |||||||||||||
33 | Albania | Bistrica I and II cascade / Bistrica 2 | Bistrica | Delvine; Vlore; Saranda | Rehabilitation | Other protected area | Inside | 5.00 | Hec Bistrica 1 dhe 2 sha | Kurum International sha (owned by Kurum Holding A.S.) | Turkey | 100 % | private | 2011 | 30 | 05.12.2041 | operational>10 | 1970 | 120 | International Finance Corporation (IFC) | Signed | credit | 33.00 | Odeabank, Banka Kombetare Tregtare, Raiffeisen Bank Albania | Invested | Netherlands Development Finance Company (FMO) | see Bistrica 1 | Yes | Original currency MDB finance: 44.91 mil. USD Uleza, Shkopeti, Bistrica I, and Bistrica II HPPS were privatized through an international competitive bid in December 2012. Kurum International sha won the bid by offering a total amount of EUR 109.5 million. Privatisation involved sale of 100% of the share capital of the energy companies held by the Ministry of Economy Trade and Energy to Kurum International. Through this Project, Kurum International contemplates reducing its electricity purchase costs (a significant production cost item). As of April 30, 2013, HEC Bistrica 1 & Bistrica 2 SH.A. operates as a subsidiary of Kurum International Sh. A. Kurum International sha purchased 100 percent of the shares "HEC Bistrica 1 and Bistrica 2" shkp worth EUR 52,000,000 (fifty two million). The debt facility includes a €33 million loan for IFC’s own account and €73 million of financing syndicated to a diverse group of commercial banks and developmental finance institutions. The financing includes B Loans of €27 million from FMO (Netherlands Development Finance Company), and €14 million from Odeabank. It includes parallel loans of €18 million from the Black Sea Trade and Development Bank, €7 million from Banka Kombetare Tregtare and €7 million from Raiffeisen Bank Albania. IFC has consulted the Government of Albania for the sale and privatization of the HPPs of Ulëz, Shkopet, Bistrica 1 and Bistrica 2. According to a GoA document, “GoA has hired the IFC as its financial advisor for the implementation of this transaction.” IFC will receive a success fee equal to 420.000 Euros for the sale of Bistrica 1 & 22 and 430.000 Euros as a success fee for the sale of Ulëz Shkopet. Bistrica 1 and 2 were supported under the World Bank's IBRD/IDA Trust Funds: Assessments of Bistrica 1, Bistrica 2 are listed among Active Bank-executed trust fund (BETF) Grants in, FY11 - FY13 Q2; ID:TF011752 under PPIAF program, Grant agreement date: 02/02/2012; Closing date: 09/30/2012; Costs: 0.07 In 2008, BMZ provided ODA loan of 347.778 USD for the Electricity supply South Albania Bistrica II project. In 2008, KfW provided ODA loan of 4.464.255 USD for the Electricity supply South Albania Bistrica II project.Projects focused on the rehabilitation of two major Hydro Power Plants in Bistrica and the respective expansion of the transmission and distribution grid. In August 2013 workers protested against the privatisation and dismissal of 25 workers from the job. They complained the firing of workers constitutes a violation of the collective agreement, the Labour Code and of the Constitution of Albania. Other employees, through their reactions, have noted that they have been harassed to sign a form for dismissal. Rehabilitation in 2013. | http://ifcext.ifc.org/IFCExt/spiwebsite1.nsf/78e3b305216fcdba85257a8b0075079d/ec98d972d9675d2385257b5c005f80b4?opendocument; http://ifcext.ifc.org/IFCExt/Pressroom/IFCPressRoom.nsf/0/DADCA1B9C06638CB85257C4700354AE5; http://www.google.cz/url?sa=t&rct=j&q=&esrc=s&source=web&cd=1&cad=rja&uact=8&ved=0CCAQFjAA&url=http%3A%2F%2Fwww.cao-ombudsman.org%2Fcases%2Fdocument-links%2Fdocuments%2FCAOComplaint.pdf&ei=lWbwVO6iBsGBUeylgYAB&usg=AFQjCNERrqFHwxcns-j_-HjW99xtgkSM9g&sig2=BQtZ7amXYoQbrwvO5xcWuw&bvm=bv.87269000,d.d24; https://webcache.googleusercontent.com/search?q=cache:yNK3GadtiRIJ:www-wds.worldbank.org/external/default/WDSContentServer/WDSP/IB/2013/05/27/000445729_20130527123345/Rendered/INDEX/751730AR0Alban0Box0377295B00PUBLIC0.txt+&cd=14&hl=en&ct=clnk&gl=cz; http://www.offene-entwicklungshilfe.de/sector/71/230/; http://telegraf.al/aktualitet/pas-privatizimit-kurum-heq-nga-puna-punonjesit-e-hec-eve-bistrica-1-dhe-2 | ||||||||||||
34 | Albania | Vegjel | Unclear | not identified | not identified | unclear | N/A | No information found | ||||||||||||||||||||||||||||||||||
35 | Albania | Shkopetit 1+2 (see Ulze and Shkopet cascade) | Duplicate | not identified | not identified | unclear | N/A | Duplicate: see Ulze and Shkopet cascade | http://www.albeiti.org/regjistri-i-koncensioneve-hidroenergjitike/ | |||||||||||||||||||||||||||||||||
36 | Albania | Holte | Duplicate | Devoll tributary | Other protected area (protected landscape or nature monument) | Inside | not identified | not identified | N/A | Possibly duplicate with Holta Kabash and Holta Porocan | http://www.albeiti.org/regjistri-i-koncensioneve-hidroenergjitike/ | |||||||||||||||||||||||||||||||
37 | Albania | Kalivac | Vjosa | Greenfield | 111 | 366622.856 | SHOQERIA KONCENSIONARE AYEN - ALB | Ayen Enerji [BIST:AYEN] and Fusha Sh.p.k. | Turkey | AYDINER INSAAT ANONIM STI | private | 35 | concession awarded | N/A | 125.3 | Deutsche Bank | Cancelled | None | The ministry broke off a concession contract for the Kalivac power plant with the Italian company BEG which agreed to build a 108 MW hydropower plant in 2012 but failed to complete the project. BEG filed law suits against a number of local subcontractors. Capacity: 90 (Ministry). 130 (Bechetti). 108 (Enel). Deutsche Bank funded the works for two years, until 2009, and then left. As a result Kalivac HPP project suffered a blockage in loans that Deutsche Bank had committed to deliver and that forced BEG to refinance the project directly. As of November 2012, BEG paid cca EUR 80,000,000.00 for the realization of the project and amount to about 40% of the total work. BEG sued Deutsche Bank. Lack of employment contracts, salaries and social security has forced workers on the Kalivac HPP to stage protests, supported by the residents of the village on December 7, 2013. According Astrit Dervish, head of the municipality of Krahës, construction of HPP for years has caused problems in the lives of residents. Police arrested four citizens for illegal rally. | https://balkangreenenergynews.com/albania-published-tender-for-hpp-kalivac/ https://invest-in-albania.org/consortium-wins-bid-kalivac-hpp-vjosa-river/ http://www.energjia.gov.al/al/njoftime/deklarata-per-shtyp/shpallja-e-rezultatit-te-procedures-konkurruese-per-ndertimin-e-hec-it-kalivac https://www.kap.org.tr/en/sirket-bilgileri/ozet/872-ayen-enerji-a-s http://open.data.al/opencorporate/agreements/Fituesi_Kalivac.pdf http://www.begspa.com/eng/idroelettrico.htm; http://www.corriere.it/notizie-ultima-ora/Economia/Enel-Beg-Cerroni-Becchetti-chiede-430mln-sentenza-Albania/23-05-2012/1-A_001599062.shtml; http://www.pietrangeli.com/kalivac-gravity-dam-design-hydropower-albania-europe#; http://www.seaconsult.eu/dmdocuments/cv_sea_en_2013.pdf; http://www.news.balkanenergy.com/files/EnergyNews_2007_III_2.pdf; http://www.manliocerroni.it/wp-content/uploads/2014/06/21giugnorispostabeg.pdf http://www.ilgiornale.it/news/politica/becchetti-litaliano-quante-ombre-sul-re-delle-antenne-1076258.html; http://www.lanotiziagiornale.it/tirana-non-vede-le-inchieste-sberla-di-cerroni-allenel-gli-affari-del-re-delle-discariche-in-albania-passo-avanti-nel-contenzioso-da-430-milioni/; http://www.latuavoce.it/notizie/stampabile.asp?id=51698; http://www.google.cz/url?sa=t&rct=j&q=&esrc=s&source=web&cd=8&ved=0CFQQFjAH&url=http%3A%2F%2Fvizionplus.al%2Ftepelene-punetoret-ne-proteste-per-pagat%2F&ei=KDLwVJamCISrU92DgLAJ&usg=AFQjCNGiAS_K1QorLFHrJgHqv8F0Wo5Euw&sig2=tCE9qYJ6xwXsuDf8wcgJMw&bvm=bv.87269000,d.d24&cad=rja; https://www.youtube.com/watch?v=lPxb6eCJpj0; http://abkons.com/en/kalivac-green-energy/ | ||||||||||||||||||||||
38 | Albania | Kaludh | Vjosa | Unclear | Vjosa | National strict protected area Emerald | Inside | 75 | not identified | not identified | unclear | N/A | https://www.energy-community.org/portal/page/portal/ENC_HOME/DOCS/36341/0633975AA1057B9CE053C92FA8C06338 | |||||||||||||||||||||||||||||
39 | Albania | Kelcyre (also Kelcyra) | Vjosa | Existing | Vjosa | Other protected area (protected landscape or nature monument) | Inside | 0.00 | 0 | not identified | not identified | operational>10 | 1978 | N/A | The HPP has impact on the Zheji Natural Park. | https://www.wbif.eu/content/stream//Sites/website/library/WBEC-REG-ENE-01-BR-1-Role-of-hydropower-04.12b.pdf | ||||||||||||||||||||||||||
40 | Albania | Klos | Shengjin | Fan; Lezhe; Mirdite | Greenfield | 1.52 | 0 | Malido-Energji shpk | not identified | private | 1 | 2009 | 30 | 22.10.2039 | operational<5 | 2012 | Not identified | http://www.energjia.gov.al/files/userfiles/Strategjike/Lista_totale_e_HEC-eve_ne_prodhim_deri_fund_2014.pdf | ||||||||||||||||||||||||
41 | Albania | Drin River cascade / Komani (also Koman) | Drin | Shkodra (also Shkoder) | Rehabilitation | 0.00 | 600 | Korporata Elektroenergjitike Shqiptare sh.a (KESH) | not identified | public | operational>10 | 1985 | European Bank for Reconstruction and Development (EBRD) | Signed | credit | 12.70 | Swiss Agency for Development & Co-operation (SDC) | Yes | Rehabilitation of Komani, Fierza and Vau i Dejes HPPS was financed under: 1/ World Bank's Energy Community of South East Europe APL Program – the APL 5 for Albania Dam Safety Project (a part of a larger Dam Safety program financed in parallel by other international financial institutions (IFIs) such as SECO-Switzerland, KfW Germany, the European Bank for Reconstruction and Development (EBRD), and the Government of Albania). 2/ World Bank's DAM SAFETY - ADDITIONAL FINANCING | http://www.worldbank.org/projects/P110481/energy-community-south-east-europe-apl-program-apl-5-albania-dam-safety?lang=en | ||||||||||||||||||||||
42 | Albania | Drin River cascade / Komani (also Koman) | Existing | not identified | not identified | International Development Agency (IDA) | Signed | Kreditanstalt für Wiederaufbau (KfW) | Yes | Original currency MDB finance: portion of 35.30 mil. USD. project financed along other projects under the Energy Community of South East Europe APL Program - APL 5 for Albania DAM SAFETY | http://www.worldbank.org/projects/P110481/energy-community-south-east-europe-apl-program-apl-5-albania-dam-safety?lang=en | |||||||||||||||||||||||||||||||
43 | Albania | Drin River cascade / Komani (also Koman) | Existing | not identified | not identified | International Bank for Reconstruction and Development (IBRD) | Signed | Yes | Original currency MDB finance: portion of 21.6 mil. USD. project financed along other projects under the Energy Community of South East Europe APL Program - APL 5 for Albania DAM SAFETY | http://www.worldbank.org/projects/P110481/energy-community-south-east-europe-apl-program-apl-5-albania-dam-safety?lang=en | ||||||||||||||||||||||||||||||||
44 | Albania | Kryezi 1 and Kryezi i Eperm cascade / Kryezi 1 | Perroi i madh | Gjegjan; Puke; Shkoder | Greenfield | 0.60 | 0 | Bekim Energjetik shpk | not identified | private | 2 | 2009 | 35 | operational<5 | 2013 | Not identified | http://www.ere.gov.al/doc/Annual_Report_2013.pdf | |||||||||||||||||||||||||
45 | Albania | Kukur 2 | Duplicate | not identified | not identified | unclear | N/A | N/A | Duplicate: see Kukur cascade / Kukur 2 | http://www.albeiti.org/regjistri-i-koncensioneve-hidroenergjitike/ | ||||||||||||||||||||||||||||||||
46 | Albania | Lajthize and Mullias concession / Lajthize | Lajthize | Greenfield | 0.00 | 4.485 | Merga shpk | not identified | private | 3 | 2009 | unclear | N/A | None | Not clear if concession still valid, not listed in 2016 EITI report. | http://www.albeiti.org/wp-content/uploads/2014/03/EITI-FINAL_2013-2014_FINAL_ALB.pdf | ||||||||||||||||||||||||||
47 | Albania | Lanabregas 1+2 | Existing | 5.00 | 0 | HPP Lanabregas | Ujesjelles-Kanalizime Tirane | 100 | public | 2009 | 30 | 25/03/2039 | operational>10 | Unclear | N/A | The Albanian Public Water Supply Company acquired Lanabregas HPP for EUR 15 million in May 2012 | http://www.energetika.net/eu/novice/oil-and-oil-derivatives/albanian-public-water-supply-company-acquires-hec-lanabregas; http://www.ikub.al/LIGJE/1201300165/Article-PeR-LICENCIMIN-E-SHOQeRISe-HEC-LANABREGAS-SHA-Ne-AKTIVITETIN-E-PRODHIMIT-Te-ENERGJISe-ELEKTRIKE-NGA-HEC-LANABREGAS.aspx | |||||||||||||||||||||||||
48 | Albania | Lubonje | Lubonja | Korce | Greenfield | 0.30 | 0 | Elektro Lubonje shpk (also Elektro Lubonja shpk) | not identified | private | 1 | 2009 | Cheng Hsiung International Corporation (China) | operational 5-10 | 2010 | Not identified | http://www.ere.gov.al/doc/Raporti_Vjetor_2016.pdf, http://www.ere.gov.al/doc/Annual_Report_2010_ENG.pdf | |||||||||||||||||||||||||
49 | Albania | Lure cascade (also Lura) / Lure 1 | Water intake: +1057.89 Molla lura River | Lure; Diber | Greenfield | Lura | National strict protected area Emerald | Inside | 6.54 | Erdat Lura shpk | Erdat | Italy | Etea Rinnovabili | private | 3 | 2009 | Euro Lines shpk (Albania); Andritz Group (Austria); Etea Group (Italy); Eltech srl (Italy) | operational 5-10 | 2012 | Banca Intesa | Invested | 7.5 | Yes | The plant is located outside of the national park, however with direct impacts on it as it takes water from the Big Lake located in the core zone of the Lura NP. Controversial deforestation linked with the project. Loan taken via several daughter companies of Etea group. Project designer Dekliada mentions that the project is financed by the EBRD. | http://www.eurolinesalbania.com/#!project/cngp; http://dekliada-alb.al/en/lure-cascade-hpp http://www.qkb.gov.al/umbraco/Surface/SearchSurface/DownloadDocument?documentCode=E8DDD8B3-1A5A-42A4-A8D3-A3DF8BB39E2D http://dekliada-alb.al | |||||||||||||||||
50 | Albania | Lure cascade (also Lura) / Lure 2 | Water intake: +878 Molla lura River | Lure; Diber | Greenfield | Lura | National Park | Outside | 4.02 | Erdat Lura shpk | Erdat | Etea Rinnovabili | private | see Lure 1 | 2009 | Euro Lines shpk (Albania); Andritz Group (Austria); Etea Group (Italy); Eltech srl (Italy) | operational 5-10 | 2012 | Banca Intesa | Invested | Yes | See Lure 1 | See Lure 1 | |||||||||||||||||||
51 | Albania | Lure cascade (also Lura) / Lure 3 | Water intake: +878 Arre molla River | Lure; Diber | Greenfield | Lura | National Park | Outside | 5.66 | Erdat Lura shpk | Erdat | Etea Rinnovabili | private | see Lure 1 | 2009 | Euro Lines shpk (Albania); Andritz Group (Austria); Etea Group (Italy); Eltech srl (Italy) | operational 5-10 | 2012 | Banca Intesa | Invested | Yes | See Lure 1 | See Lure 1 | |||||||||||||||||||
52 | Albania | Mallkasterra (also Mallkaster) | Zalli i Okshtunit | Greenfield | 0.00 | 30.65 | Mix Tecnic, 2 T, Perxhola,Albadi, UDSA , ME-AJ, shpk | not identified | 10 | 2009 | unclear | N/A | None | Not clear if concession still valid, it is not mentioned on eg. the EITI 2016 list. | http://www.ecoalbania.org/wp-content/uploads/2017/05/HPPs_al_final-report_me-kapak.pdf | |||||||||||||||||||||||||||
53 | Albania | Devoll cascade / Moglice | Devoll | Moglice commune; Korca District | Greenfield | 0.00 | 172 | 455 | Devoll Hydropower Sh.A. | Statkraft AS | Norway | 100% | private | see Banje | 2009 | Norplan (Norway), Alstom (France), Sweco (Sweden), AF-Consult Switzerland; Limak Construction Group (Turkey); Norconsult (Norway) | under construction | N/A | EUR | 300 | 300 | Not identified | "Originally developed under JV between Statkraft and EVN. In March 2013, Norwegian Statkraft AS and Austrian EVN AG signed an agreement by which Statkraft acquired EVN’s 50 percent stake in Devoll Hydropower ShA. Investments in a group company, Statkraft Markets B.V., Amsterdam/Netherlands, were increased by EUR 51.2 million in 2013. The investment in Statkraft Markets B.V. was made to provide financing for a power plant construction by one of its subsidiaries: Devoll Hydropower Sh. A., Tirana/Albania. Workers protests against working conditions in August 2014: http://www.devollhydropower.al/new/?p=8441. This was the second time within 3 months Banja hydropower plant workers protested against low wages and fulfilling the conditions at work. When the decision was taken to boycott work, workers were threatened by police officers called by representatives of the firm ""Limak. CDM project Rockslide kills three working on Albania's Moglice hydropower project in June 2014 Norwegian company Statkraft has so far invested EUR 150 million in the construction of Moglice hydro power plant....Additional EUR 150 million will be invested before completion, | http://www.statkraft.de/Statkraft/Documents/de/Investor%20Relations/Anual%20Report%202013%20Statkraft%20Markets%20GmbH_Web%20Vers._ENGLISH.pdf; http://www.limak.com.tr/sectors/construction/projects/dams http://balkangreenenergynews.com/statkraft-invested-eur-150-million-construct-hpp-moglice/ | ||||||||||||||||||
54 | Albania | Lajthize and Mullias concession / Mullias | Mullias | Greenfield | 0.00 | see Lajthize | Merga shpk | not identified | private | see Lajthize | 2009 | unclear | N/A | None | Not clear if concession still valid, it is not mentioned on eg. the EITI 2016 list. | http://www.albeiti.org/wp-content/uploads/2016/02/Regjistri-i-kocensioneve-n%C3%AB-sektorin-e-hidroenergjitik.pdf | ||||||||||||||||||||||||||
55 | Albania | Murdhar 1 and 2 cascade / Murdhar 1 | Murdhari or Zallit | Greenfield | 0.00 | 2.68 | HydroEnergy shpk | SOL spa | Italy | 75% | private | 2 | 2009 | Unitec Studio Projekt Ltd (Albania) | operational<5 | 2014 | Not identified | http://www.sol.it/english/bil2013.pdf; http://www.sol.it/english/bil2011.pdf, http://www.ere.gov.al/doc/Annual_Report_2014.pdf, https://www.wbif.eu/content/stream//Sites/website/library/WBEC-REG-ENE-01-BR-1-Role-of-hydropower-04.12b.pdf | ||||||||||||||||||||||||
56 | Albania | Peqin | Greenfield | 0.00 | 4.1 | HEC Peqin shpk | not identified | private | 1 | 2009 | potential | N/A | None | On November 11, 2011, the Ministry of Economy cancelled concession deal with HEC-I Peqin for the construction and upgrade of hydro power plant as the concessionaire failed to meet the contractual obligations. However it still appears on later EITI lists of concessions. | http://renewables.seenews.com/news/albania-cancels-12-hydro-power-plant-concession-deals-209853, http://www.albeiti.org/wp-content/uploads/2016/02/Regjistri-i-kocensioneve-n%C3%AB-sektorin-e-hidroenergjitik.pdf, http://www.albeiti.org/regjistri-i-koncensioneve-hidroenergjitike/ | |||||||||||||||||||||||||||
57 | Albania | Permet | Vjosa | Unclear | Vjosa | Other protected area (protected landscape or nature monument) | Inside | not identified | not identified | unclear | N/A | No information found | ||||||||||||||||||||||||||||||
58 | Albania | Skavica cascade / Skavica 1 | Drin | Unclear | 0.00 | 130 | not identified | not identified | planned | N/A | 538 | European Bank for Reconstruction and Development (EBRD) | Planned | credit | N/A | In September 2014, KESH met with Turkish companies "Suzer Group" and "Nurol Holding" about possible investment in the Skavica HPP. Tassara-Geoteca Progetti-Kinglor Consortium listed as a promoter of the project in some documents. The current scheme probably consists of two plants (see also Skavica 2). EBRD is a lead MDB administering the WBIF grant for developing appropriate studies. | http://www.skyscrapercity.com/showthread.php?t=326771; http://aea-al.org/wp-content/uploads/2014/07/study_on_assessment_of_res_potentials_in_albania.pdf; http://gazetamendimi.com/dy-kompani-turke-te-gatshme-te-investojne-per-hec-skavica/; http://www.jci-plant.or.jp/010jci/pdf/H21_ENE-1-B-albania-Report.pdf https://www.wbif.eu/wbif-projects/details?code=PRJ-ALB-ENE-008&ogtitle=Skavica%20Hydro%20Power%20Plant&ogdescription=PRJ-ALB-ENE-008&ogimage=Sites/website/projects/PRJ-ALB-ENE-008/Skavica%20HPP.bmp | |||||||||||||||||||||||||
59 | Albania | Picar 1 | Gurra or Reza e Kolonjes | Kolonje | Greenfield | Other protected area | Inside | 0.20 | 0 | Peshku Picar 1 shpk | not identified | private | 1 | 2009 | operational 5-10 | 2011 | Not identified | 2011 assumed date based on ERE reports | http://www.ere.gov.al/doc/Raporti_Vjetor_2016.pdf, http://www.albeiti.org/regjistri-i-koncensioneve-hidroenergjitike/, http://www.ere.gov.al/doc/Annual_Report_2013.pdf | |||||||||||||||||||||||
60 | Albania | Pocem | Vjosa | Greenfield | KOVLU ENERGJI | ÇINAR-SAN HARFIYAT NAKLIYAT INSAAT TURIZM SANAYI VE TICARET LIMITED SIRKETI AYEN ENERJI | Turkey | planned | N/A | Not identified | On 3/5/2017 Albanian Administrative Court ruled that the EIA as well as the public consultation process, was highly deficient. | http://open.data.al/opencorporate/agreements/Pocem.pdf https://www.euronatur.org/en/news/detail/news/dam-project-stopped-for-the-present/ | ||||||||||||||||||||||||||||||
61 | Albania | Prelle | Urake | Mat; Diber | Greenfield | 14.97 | 0 | PRELL ENERGY | Endi-E | Italy, Albania | G & C HYDROPOWER | private | 2013 | operational<5 | 2016 | Banca Intesa | Invested | 8 | Not identified | Seems there was an older version of the project with 2 plants | http://azure.ikub.al/LIGJE_CATEGORY/17/12/20/MBI-LICENCIMIN-E-SHOQeRISe-PRELL-ENERGY-SHPK-Ne-AKTIVITETIN-E-PRODHIMIT-Te-ENERG-0078.aspx http://www.opencorporates.al/sq/nipt/l17610901s http://www.qkb.gov.al/umbraco/Surface/SearchSurface/DownloadDocument?documentCode=68FDBDF9-77B8-44C7-8FE6-FE1AD3854AB4, http://www.ere.gov.al/doc/Raporti_Vjetor_2016.pdf, http://www.albeiti.org/regjistri-i-koncensioneve-hidroenergjitike/ | |||||||||||||||||||||
62 | Albania | Qukes concession - Qukes 3 | Shkumbin | Elbasan | Greenfield | Shkumbin | Other protected area (protected landscape or nature monument) | Inside | 0.00 | 2.9 | Qukes Power | not identified | private | 9 | 2011 | concession awarded | N/A | Not identified | Qukes 1 and 2 are in another concession. Not clear whether concession is still valid, plants do not seem to have been built | http://www.albeiti.org/regjistri-i-koncensioneve-hidroenergjitike/ | ||||||||||||||||||||||
63 | Albania | Qukes concession - Qukes 4 | Shkumbin | Elbasan | Greenfield | Shkumbin | Other protected area (protected landscape or nature monument) | Inside | 0.00 | 2.9 | Qukes Power | not identified | private | 9 | 2011 | concession awarded | N/A | Not identified | http://www.albeiti.org/regjistri-i-koncensioneve-hidroenergjitike/ | |||||||||||||||||||||||
64 | Albania | Qukes concession - Qukes 5 | Shkumbin | Elbasan | Greenfield | Shkumbin | Other protected area (protected landscape or nature monument) | Inside | 0.00 | 10.8 | Qukes Power | not identified | private | 9 | 2011 | concession awarded | N/A | Not identified | http://www.albeiti.org/regjistri-i-koncensioneve-hidroenergjitike/ | |||||||||||||||||||||||
65 | Albania | Qukes concession - Qukes 6 | Shkumbin | Elbasan | Greenfield | Shkumbin | Other protected area (protected landscape or nature monument) | Inside | 0.00 | 4.9 | Qukes Power | not identified | private | 9 | 2011 | concession awarded | N/A | Not identified | http://www.albeiti.org/regjistri-i-koncensioneve-hidroenergjitike/ | |||||||||||||||||||||||
66 | Albania | Qukes concession - Qukes 7 | Shkumbin | Elbasan | Greenfield | Shkumbin | Other protected area (protected landscape or nature monument) | Inside | 0.00 | 6.6 | Qukes Power | not identified | private | 9 | 2011 | concession awarded | N/A | Not identified | http://www.albeiti.org/regjistri-i-koncensioneve-hidroenergjitike/ | |||||||||||||||||||||||
67 | Albania | Qukes concession - Qukes 8 | Shkumbin | Elbasan | Greenfield | Shkumbin | Other protected area (protected landscape or nature monument) | Inside | 0.00 | 6.6 | Qukes Power | not identified | private | 9 | 2011 | concession awarded | N/A | Not identified | http://www.albeiti.org/regjistri-i-koncensioneve-hidroenergjitike/ | |||||||||||||||||||||||
68 | Albania | Qukes concession - Qukes 9 | Shkumbin | Elbasan | Greenfield | Shkumbin | Other protected area (protected landscape or nature monument) | Inside | 0.00 | 15 | Qukes Power | not identified | private | 9 | 2011 | concession awarded | N/A | Not identified | http://www.albeiti.org/regjistri-i-koncensioneve-hidroenergjitike/ | |||||||||||||||||||||||
69 | Albania | Qukes concession - Qukes 10 | Shkumbin | Elbasan | Greenfield | Shkumbin | Other protected area (protected landscape or nature monument) | Inside | 0.00 | 4.98 | Qukes Power | not identified | private | 9 | 2011 | concession awarded | N/A | Not identified | http://www.albeiti.org/regjistri-i-koncensioneve-hidroenergjitike/ | |||||||||||||||||||||||
70 | Albania | Qukes concession - Qukes 11 | Shkumbin | Elbasan | Greenfield | Shkumbin | Other protected area (protected landscape or nature monument) | Inside | 0.00 | 5.4 | Qukes Power | not identified | private | 9 | 2011 | concession awarded | N/A | Not identified | http://www.albeiti.org/regjistri-i-koncensioneve-hidroenergjitike/ | |||||||||||||||||||||||
71 | Albania | Qukes concession - Qukes 12 | Shkumbin | Elbasan | Greenfield | Shkumbin | Other protected area (protected landscape or nature monument) | Inside | 0.00 | 3.3 | Qukes Power | not identified | private | 9 | 2011 | concession awarded | N/A | Not identified | http://www.albeiti.org/regjistri-i-koncensioneve-hidroenergjitike/ | |||||||||||||||||||||||
72 | Albania | Radove | Carshove | Kolonje | Greenfield | Powerhouse: 40.137266, 20.551491; Intake: 40.138697, 20.550883 | Bredhi i Hotovës-Dangelli | National park Emerald | Inside | 2.00 | 0 | MTC Energy shpk | not identified | private | 1 | 2009 | operational<5 | 2014 | Raiffeisen Bank (Albania) | Invested | Yes | The plant is located at the proximity of the boundary of the Bredhi Hotoves NP - the rivers constituted the natural boundary of the NP. On 15.11.2013 MTC Energy shpk applied for electricity generation license for the Radove HPP. First year of generation appears to be 2014 based on ERE reports. Concession failure penalties: Penalty holder: concessionare for the construction of the HPP Radove; name blacked out in the document Total penalty amount:2,575,217 Currency:LEK Reason:"Pay LEK 2,575,217 (2,547,400 LEK (00:05% x 188 million LEK x 271 days (3/9 / 2009- 06.02.2010) plus interest LEK 28217)" Penalty issued: December 2012 | http://www.klsh.org.al/web/pub/ministrin_e_ekonomis_441_1.pdf; http://www.google.cz/url?sa=t&rct=j&q=&esrc=s&source=web&cd=1&ved=0CCMQFjAA&url=http%3A%2F%2Fere.gov.al%2Fdoc%2FNjoftim_15.11.2013.doc&ei=haHvVITqBcv_ygOVkoCABA&usg=AFQjCNGz-IWcyl3-0SJQOD2IWOmCJMHPgQ&sig2=UvrXdHHOI-hSEbD2283klw&bvm=bv.86956481,d.d2s&cad=rja, http://www.ere.gov.al/doc/Annual_Report_2014.pdf http://www.qkb.gov.al/umbraco/Surface/SearchSurface/DownloadDocument?documentCode=90CEE90F-FB7B-4C56-BA36-2E89FDC93F3B | |||||||||||||||||||
73 | Albania | Langarice Cascade / Rajan 2 | Water source: +641.65 Langarica river + water from Hpp Osnat | Korce | Greenfield | 0.00 | 2.4 | Rajan Energy shpk | Emmecidue Srl | Italy | 100% | private | 12 | 2009 | 35 | concession awarded | N/A | None | Not clear whether concession is still valid, it is in latest EITI report but not much other news. | http://www.asha.gov.al/wp-content/uploads/2014/06/28.Vendim.301-dt.18.04.2014.pdf; http://dekliada-alb.al/en/langarica-cascade-hpp, http://akm.gov.al/assets/vnm-rajan-2.pdf, http://www.albeiti.org/regjistri-i-koncensioneve-hidroenergjitike/ | ||||||||||||||||||||||
74 | Albania | Sasaj | Kalasa; Tatzati | Saranda | Greenfield | Protected Landscape | Other protected area | Inside | 8.60 | 0 | Energo-Sas shpk | Agna Group | Albania | 100% | private | 2006 | 30 | 2036 | Hydroprojekt (Czech Republic); Wonder-Studio (Albania); Wonder sha (Albania); SGE (China) | operational<5 | 2012 | EUR | 8.5 | 8.5 | Raiffeisen Bank (Albania) | Completed | Yes | Works on Sasaj date back to 1978 and are connected with the construction of the Saranda coastal Irrigation system built on the river intake of Kalasa (Tatzati stream). Channel to the entrance of the tunnel, tunnel Sasaj, derivation channel were built. Sasaj tunnel 3.5 km in length, the tunnel is cut through the mountain from the Kalasa river to the coastal slopes continuing in a large canal. Sasaj HPP is to improve electricity supply to south coast tourist resorts. It was planned to be multipurpose - combining irrigation with power generation. WB document dated October 2012 notes CEZ Group (100% / Czech Republic) is the project sponsor. With decision No. 11/6 date 10.07.2006 of Urbanism Department of Lukova Commune, has been approved the destination of construction site and the right of way of Sasaj HPP works. Through an Agreement among Lukova Commune, Sasaj village and “ENERGO-SAS” company dated 26.11.2008, the project got a community approval. The residents of Lukjova objected to the establishment of the HPP in the village of Lukove, because the project sponsored by another company intended to exploit the steepness of the slopes and excesss water of Sasaj properties of residents which substantially damaged agricultural lands. Sasaj HPP is different frm the project submitted under the World Bank's Coastal Zone Management project due to the lack of an accord over land ownership. Instead, the project sponsor received unanimous support from Sasaj village community. A petition was carried out by the Lukova inhabitants, addressed to the Albanian and international institutions concerning the proposed hydro-electric plant in Sasaj Village. The World Bank answered that "While the objections raised in respect of this proposal [the HPP] may well be valid, they are not pertinent to the proposed South Coast Planning Regulations. The Consultants have commented on this proposal in the Engineering Report." An agreement was reached between the Concessionaire and Village of Sasaj on 26.11.2008. Also this support is confirmed and in the presence of municipal authorities Lukove, at the meeting of common in the village Sasaj to date. 12.28.2008 (minutes of the meeting tripartite: Community, the Municipal Presidency Lukove and concessionaire) HPP construction in the territory of the village Lukove was not allowed by the villagers. After protracted negotiations, because they could not convince Lukove residents, project sponsor moved the HPP 500 meters west Piqerasi territories. Residents say that there was no transparency. Violations of technical safety regulations caused flooding hundreds of hectares of agricultural lands in the village of Bunecit in 2013. Residents of Lukove seek financial compensation. The mayor of Lukjova villages submitted a lawsuit against owners Bunecit HPP to the Attorney. | http://energjia.al/tag/peruron/; http://gazetatelegraf.com/hec-i-i-bunecit-u-demton-tokat-banoret-denoncojne-ne-prokurori/ů http://km.gov.al/index.php?fq=brenda&m=news&lid=16532&gj=gj2; http://ppi-re.worldbank.org/data/project/energo-sas-sasaj-shpp-7408, http://siteresources.worldbank.org/INTALBANIA/Resources/Q&A_Southern_Coast_Development_Plan1.pdf | |||||||||||||
75 | Albania | Seke | Uraka | Greenfield | 0.00 | 11.2 | Seka Hydropower | not identified | private | 1 | 2013 | concession awarded | N/A | Not identified | http://www.albeiti.org/regjistri-i-koncensioneve-hidroenergjitike/ | |||||||||||||||||||||||||||
76 | Albania | Selenice | Vjosa | Selenice | Greenfield | none yet | none yet | potential | None | Old project, not being actively pushed at time of writing. | http://www.oranews.tv/videogaleri/vlore-selenica-pa-uje-banoret-botet-shperndahen-ne-zona-selektive/, http://balkanrivers.net/en/key-areas/vjosa-river | |||||||||||||||||||||||||||||||
77 | Albania | Selice | Unclear | not identified | not identified | unclear | N/A | No information found | ||||||||||||||||||||||||||||||||||
78 | Albania | Selita | Tirana | Existing | 5.00 | 0 | not identified | not identified | public | operational>10 | 1952 | N/A | https://www.wbif.eu/content/stream//Sites/website/library/WBEC-REG-ENE-01-BR-1-Role-of-hydropower-04.12b.pdf | |||||||||||||||||||||||||||||
79 | Albania | Vlore | Shushica | Vlore | Unclear | not identified | not identified | unclear | N/A | No information found | ||||||||||||||||||||||||||||||||
80 | Albania | Skavica cascade / Skavica 2 | Drin | Unclear | 350 | not identified | not identified | planned | N/A | European Bank for Reconstruction and Development (EBRD) | Planned | N/A | In September 2014, KESH met with Turkish companies "Suzer Group" and "Nurol Holding" about possible investment in the Skavica HPP. Tassara-Geoteca Progetti-Kinglor Consortium listed as a promoter of the project. | http://www.skyscrapercity.com/showthread.php?t=326771; http://aea-al.org/wp-content/uploads/2014/07/study_on_assessment_of_res_potentials_in_albania.pdf; http://gazetamendimi.com/dy-kompani-turke-te-gatshme-te-investojne-per-hec-skavica/; http://www.jci-plant.or.jp/010jci/pdf/H21_ENE-1-B-albania-Report.pdf | ||||||||||||||||||||||||||||
81 | Albania | Skoran | Unclear | not identified | not identified | unclear | N/A | No information found | ||||||||||||||||||||||||||||||||||
82 | Albania | Sllabinje cascade / Sllabinje (also Sllabinja or Slabinja or Slabinje or Sllabinje 1) | Shkumbini (also Shkumbin) | Korca | Greenfield | 13.80 | 0 | Power Elektrik Slabinje shpk | not identified | private | 1 | 2008 | operational 5-10 | 2012 | Not identified | Concession failure penalties: Penalty holder: concessionaire for the construction of HPP Sllabinje; name blacked out in the document Total penalty amount: 18,905,045 Currency: LEK Reason: "pay penalties in the amount of 18,905,045 LEK (0.05% x difference of outstanding investment (total value 1,290,117,500 LEK - LEK 1,089,000,000 value of investments to more dated 31/12/2010 with no. 10758 protocol, dated 13/12/2010) x 188 days (from 26/5 / 2010- 31/12/2010)." Penalty issued: December 2012 The company took a loan from Raiffeisen Bank in 2016. | http://www.klsh.org.al/web/pub/ministrin_e_ekonomis_441_1.pdf http://www.qkb.gov.al/umbraco/Surface/SearchSurface/DownloadDocument?documentCode=C657AF04-43E8-4311-A4A7-05E7B41D497E | |||||||||||||||||||||||||
83 | Albania | Smokthina (also Smokthine or Lepenice) | Shushica (also Sushice) | Vlore | Rehabilitation | 9.20 | 0 | Albanian Green Energy shpk | Essegei spa (owned by Alpiah srl holding company (Italy)) | Italy | operational>10 | 2004 | Not identified | With ERE’s decision no.2 of date 27.01.2003, ERE has withdrawn the license of “Essegei-Shqipëri” company for not fulfilling the license conditions and managing incapacities and Essegei-Shqipëri Smokthina company is appointed as administrator, to undertake the use of licensed equipments and this company will fulfill all the obligations defined in the license. With ERE’s Board of Commissioner’s decisions no.69 and no.70, dated 12.12.2007, ERE has transferred the licenses from the concessionary companies of Essegei Shqipëri Smokthina and Hydroelectric Company of Albania to Albanian Green Energy and Balkan Green Energy companies. On 09.09.2013 the Tirana District Court confirmed that it registered the civil cause Act no. 171 depositing date 04.06.2009,and registration date 05.06.2009 with complainant Mr. Grigor Zoraqi; defendants: Giorando Gorini, Aldo Francescheti, Essegei spa Company, Albanian Green Energy company, Balkan Green Energy company, the Economy, Trade and Energy Ministry and Energy Regulator Authority. ERE 2009 report says commissioned in 1974 http://www.ere.gov.al/doc/rap_vjet_2009_derguar_ne_kuvend.pdf | http://mobile.ikub.al/Lajme/LIGJE_CATEGORY/PeR-KUALIFIKIMIN-E-IMPIANTIT-PRODHUES-PeR-HEC-SMOKTHINA-Te-SHOQeRISe-ALBANIAN-GREEN-ENERGY-SHPK-SI-BURIM-I-RINOVUESHeM-ENERGJIE-1309110102.aspx; http://www.alltravels.com/albania/all-regions/bratraj/photos/current-photo-1332607; http://renewables.seenews.com/news/albania-licenses-smokthina-hpp-as-producer-of-renewable-energy-351678; https://cdm.unfccc.int/filestorage/q/v/UVZTEC5X7L1JRNS09PYABQM6WH3F24.pdf/PDD.pdf?t=NE98bnA5bW84fDAr54gQFSu8W0HfXct1TF2f | |||||||||||||||||||||||||||
84 | Albania | Stojan | . | Greenfield | 0.00 | 1.4 | El-Er Energy shpk | not identified | private | 1 | 2008 | unclear | N/A | None | On 26 July 2014 the Ministry of Energy and Industry initiated proceeding in cancellation of 14 concessionary contracts for the construction of 30 HPPs approved by Berisha's administration, including the Stojan HPP. However it still appears in a later concession list so it is not clear what the situation is. | http://gazeta-shqip.com/lajme/2014/07/26/anulohen-kontratat-e-koncesioneve-per-30-hec-e/, http://www.panorama.com.al/koncesionet-anulohen-14-kontrata-per-hec-e/, http://www.albeiti.org/regjistri-i-koncensioneve-hidroenergjitike/ | ||||||||||||||||||||||||||
85 | Albania | Thane and Mollas concession / Thane | Shishtavecit and Rekes | Fier Shegan; Fier | Greenfield | 0.00 | 3.9 | Delia Group shpk | not identified | private | 2 | 2008 | 35 | concession awarded | N/A | None | Concession failure penalties: Penalty holder: concessionare for the construction of the HPPs Thane and Mollas; name blacked out in the document Total penalty amount:26,020,055 Currency:LEK Reason:"pay penalties calculated in value when 26,020,055 LEK (for 499 days x0.005% x 1,042,888,000 ALL)." Penalty issued: December 2012 | http://www.deliagroup.com.al/index.php/en/projects, http://www.albeiti.org/regjistri-i-koncensioneve-hidroenergjitike/ | ||||||||||||||||||||||||
86 | Albania | Zaje-Turaj-Xhaferraj-Kollovoz-Novosejë-Meshtekën concession / Turaj | Shishtavecit and Rekes (also Reka-Topojan) | Kukes | Greenfield | Mali I Dajtit National Park | National Park | Inside | 0.00 | 2.92 | Reka sh.p.k; Albakonstruksion sh.p.k; Xhoino sh.p.k | not identified | private | 6 | 2012 | concession awarded | N/A | Not identified | http://www.albeiti.org/regjistri-i-koncensioneve-hidroenergjitike/, http://www.ere.gov.al/doc/Raporti_Vjetor_2016.pdf | |||||||||||||||||||||||
87 | Albania | Ujanik 2 | Ujanik | Greenfield | Other protected area | Inside | 2.5 | HP Ujaniku Energy | not identified | private | 1 | 2011 | operational<5 | 2016 | Not identified | Due-dilligence report prepared by Abkons in February-April 2015. | http://abkons.com/bkt/; http://www.qbz.gov.al/botime/fletore_zyrtare/2015/PDF-2015/194-2015.pdf, http://www.ere.gov.al/doc/Raporti_Vjetor_2016.pdf | |||||||||||||||||||||||||
88 | Albania | Ulzes (also Ulze or Ulza) | Mat | Duplicate | Other protected area | Inside | 25.00 | 0 | not identified | not identified | operational>10 | 1958 | N/A | https://www.wbif.eu/content/stream//Sites/website/library/WBEC-REG-ENE-01-BR-1-Role-of-hydropower-04.12b.pdf | ||||||||||||||||||||||||||||
89 | Albania | Ura e Prenit | Bushtrica | Librazhd | Greenfield | 0.00 | 29 | Bushtrica Energy 2009 | not identified | concession awarded | N/A | None | http://www.albeiti.org/regjistri-i-koncensioneve-hidroenergjitike/ | |||||||||||||||||||||||||||||
90 | Albania | Valbone (also Valbona) | Valbona | Tropoje | Greenfield | Lugina e Valbones National Park | National park Emerald | Inside | 0.00 | 2.3 | T’Plani shpk | not identified | private | 1 | 2009 | under construction | N/A | Not identified | In the National Park, heavily opposed by locals and environmentalists. | https://al.linkedin.com/pub/sadik-llapashtica/3a/1a8/320; https://www.facebook.com/permalink.php?story_fbid=353672494789170&id=353424184814001, http://www.albeiti.org/regjistri-i-koncensioneve-hidroenergjitike/, http://www.journeytovalbona.com/wp-content/uploads/2016/01/FINAL-Opinion.pdf | ||||||||||||||||||||||
91 | Albania | Drin River cascade / Vau i Dejes | Drin | Shkodra (also Shkoder) | Rehabilitation | 250.00 | Korporata Elektroenergjitike Shqiptare sh.a (KESH) | not identified | public | operational>10 | 1971 | International Development Agency (IDA) | Signed | see Drin River cascade / Komani | Kreditanstalt für Wiederaufbau (KfW) | Yes | Rehabilitation of Komani, Fierza and Vau i Dejes HPPS was financed under: 1/ World Bank's Energy Community of South East Europe APL Program – the APL 5 for Albania Dam Safety Project (a part of a larger Dam Safety program financed in parallel by other international financial institutions (IFIs) such as SECO-Switzerland, KfW Germany, the European Bank for Reconstruction and Development (EBRD), and the Government of Albania). 2/ World Bank's DAM SAFETY - ADDITIONAL FINANCING | http://www.worldbank.org/projects/P110481/energy-community-south-east-europe-apl-program-apl-5-albania-dam-safety?lang=en | ||||||||||||||||||||||||
92 | Albania | Drin River cascade / Vau i Dejes | Existing | Korporata Elektroenergjitike Shqiptare sh.a (KESH) | not identified | International Bank for Reconstruction and Development (IBRD) | Signed | see Drin River cascade / Komani | Yes | https://www.wbif.eu/content/stream//Sites/website/library/WBEC-REG-ENE-01-BR-1-Role-of-hydropower-04.12b.pdf | ||||||||||||||||||||||||||||||||
93 | Albania | Drin River cascade / Vau i Dejes | Existing | not identified | not identified | European Bank for Reconstruction and Development (EBRD) | Completed | credit | see Fierza | Yes | https://www.wbif.eu/content/stream//Sites/website/library/WBEC-REG-ENE-01-BR-1-Role-of-hydropower-04.12b.pdf | |||||||||||||||||||||||||||||||
94 | Albania | Veleshica cascade / Veleshica 1 | Water source: 1550 in 2 axes by 0.5 m3/s | Greenfield | 5.67 | Veleshica Energy sh.p.k | Energia e Territorio sa ? | Italy | private | 8 | 2009 | 35 | planned | N/A | Not identified | On 15.07.2014 the Ministry of Culture approved a report on the reorganisation of the Veleshica cascade prepared by Agency Service for Archaeological Projects about archeological monitoring of the construction works. The report applied to Veleshica 1-6, and Sllove and Bjeshke promoted by Veleshica Energy shpk. On November 11, 2011, the Ministry of Economy cancelled concession deal with Veleshica Energy for the construction and upgrade of hydro power plant as the concessionaire failed to meet the contractual obligations. | http://www.balkans.com/open-news.php?uniquenumber=42618; http://www.ikub.al/LIGJE/911180053/Article-PeR-MIRATIMIN-E-KONTRATeS-Se-KONCESIONIT-Te-FORMeS-BOT-Te-LIDHUR-NDeRMJET-MINISTRISe-Se-EKONOMISe-TREGTISe-DHE-ENERGJETIKeS-DHE-BASHKIMIT-Te-SHOQeRIVE-ADVISOR-C-ENERGY-SHPK-POLISTAMP-SYSTEM-SRL-E-ENER.aspx; http://www.asha.gov.al/wp-content/uploads/2014/06/Vendimi-332-date-15.07.2014-HEC-Veleshica.pdf; http://renewables.seenews.com/news/albania-cancels-12-hydro-power-plant-concession-deals-209853; http://www.asha.gov.al/wp-content/uploads/2014/06/60.Vendim-332-dt.15.07.2014.pdf; http://dekliada-alb.al/en/veleshice-cascade-hpp | |||||||||||||||||||||||||
95 | Albania | Vertopit (also Vertop) | . | Greenfield | Osum tributary | National strict protected area Emerald | Inside | 0.00 | 1.52 | Hydro Salillari shpk | not identified | private | 1 | 2009 | Vaptech (Bulgaria) | operational<5 | 2016 | Not identified | http://www.ere.gov.al/doc/Raporti_Vjetor_2016.pdf | |||||||||||||||||||||||
96 | Albania | Vlaschuk | Devoll | Greenfield | none yet | none yet | potential | N/A | None | http://www.ecoalbania.org/wp-content/uploads/2017/05/HPPs_al_final-report_me-kapak.pdf | ||||||||||||||||||||||||||||||||
97 | Albania | Vukel cascade / Vukel 1 | Cem i Vuklit | Vukel | Greenfield | Cem i Vuklit | National strict protected area Emerald | Inside | 0.00 | not identified | not identified | potential | N/A | None | Appears on old list of concessions but not newer ones and in 2009 ERE report but with a different sponsor. | http://www.albania-smallhydropower.org/Lista%20e%20Koncesioneve%20per%20Hidrocentralet%20e%20Vegjel%20ne%20Shqiperi.pdf, http://www.ere.gov.al/doc/rap_vjet_2009_derguar_ne_kuvend.pdf | ||||||||||||||||||||||||||
98 | Albania | Vukel cascade / Vukel 2 | Cem i Vuklit | Vukel | Greenfield | Cem i Vuklit | National strict protected area Emerald | Inside | 0.00 | not identified | not identified | potential | N/A | None | Appears on old list of concessions but not newer ones and in 2009 ERE report but with a different sponsor. | http://www.albania-smallhydropower.org/Lista%20e%20Koncesioneve%20per%20Hidrocentralet%20e%20Vegjel%20ne%20Shqiperi.pdf, http://www.ere.gov.al/doc/rap_vjet_2009_derguar_ne_kuvend.pdf | ||||||||||||||||||||||||||
99 | Albania | Zalli i Bulqizes (also Vajkali or Vajkal) concession | Zalli i Bulqize | Ternove; Diber | Greenfield | 0.00 | 5.3 | Teodori 2003 | not identified | private | 4 | 2011 | concession awarded | N/A | None | http://www.albeiti.org/regjistri-i-koncensioneve-hidroenergjitike/, http://www.akbn.gov.al/wp-content/uploads/2014/10/Investime-Hec-e-Gusht-2015.pdf | ||||||||||||||||||||||||||
100 | Albania | Stebleve | Zalli i Okshtunit | Greenfield | Shebenik-Jabllanice National Park | National Park | Inside | 0.00 | 3.4 | Pure Energy Stebleva shpk | not identified | private | 1 | 2008 | unclear | N/A | Not identified | On November 11, 2011, the Ministry of Economy cancelled concession deal with Pure Energy Stebleva shpk for the construction and upgrade of hydro power plant as the concessionaire failed to meet the contractual obligations. On 26 July 2014 the Ministry of Energy and Industry initiated proceeding in cancellation of 14 concessionary contracts for the construction of 30 HPPs approved by Berisha's administration, including the Stebleve HPP. However the concession is still on the EITI concession list published in 2016. Concession failure penalties: Penalty holder: Concessionaire for the construction of HPP Stebleve; the name blacked out in the document Total penalty amount: Currency: LEK Reason: "pay duty in value from 47,504,895 LEK {595 days (25/12 / 2009-08.11.2011) x 0:05% / day x 159,680,320 ALL value from investments}." Penalty issued: December 2012 | http://renewables.seenews.com/news/albania-cancels-12-hydro-power-plant-concession-deals-209853; http://www.klsh.org.al/web/pub/ministrin_e_ekonomis_441_1.pdf; http://gazeta-shqip.com/lajme/2014/07/26/anulohen-kontratat-e-koncesioneve-per-30-hec-e/, http://www.albeiti.org/regjistri-i-koncensioneve-hidroenergjitike/, http://www.albeu.com/ekonomi/mete-zgjidh-12-kontrata-per-ndertimin-e-hec-ve-/51893/, http://www.panorama.com.al/koncesionet-anulohen-14-kontrata-per-hec-e/ |