2 | MSDII Task List | |||||||||||||||||||||||||
3 | Date | Task Type | Description | Owner | Due Date | Status | Completion Date | Comments | ||||||||||||||||||
4 | Week 1 | 8/26/2019 | Adminstrative | Develop detailed schedule for MSDII Phase 1 | EE | 8/26/2019 | Complete | 8/29/2019 | ||||||||||||||||||
5 | 8/26/2019 | Manufacture | 3D print driving gears for motors | EE | 8/27/2019 | Complete | 8/27/2019 | Oversize hole | ||||||||||||||||||
6 | 8/27/2019 | Meeting/Discussion | MSDII Class Meeting 1 | ALL | 8/27/2019 | Complete | 8/27/2019 | |||||||||||||||||||
7 | 8/27/2019 | Testing | Motor demonstration to team | DB | 9/3/2019 | Skipped | 8/27/2019 | Wire from Chris Papa (12 gauge) | ||||||||||||||||||
8 | 8/27/2019 | Purchasing | Receive ordered parts | DB | 8/27/2019 | Complete | 8/27/2019 | |||||||||||||||||||
9 | 8/27/2019 | Testing | Gear/Motor compatibility | EE | 8/27/2019 | Complete | 8/27/2019 | Need bigger hole | ||||||||||||||||||
10 | 8/27/2019 | Engineering | Review Pump manufacture method | EE | 8/27/2019 | Complete | 8/27/2019 | |||||||||||||||||||
11 | 8/27/2019 | Manufacture | Determine manufacture method for winding stand/109 | ALL | 8/27/2019 | Complete | 8/27/2019 | 3D print | ||||||||||||||||||
12 | 8/27/2019 | Adminstrative | Identify MSDII Risks and make risk table on confluence | ALL | 8/27/2019 | Complete | 8/27/2019 | |||||||||||||||||||
13 | 8/27/2019 | Adminstrative | Set Up Phase 1 Confluence | EE | 8/27/2019 | Complete | 8/28/2019 | |||||||||||||||||||
14 | 8/27/2019 | Documentation | Review Test Methods | ZC | 8/27/2019 | Complete | 8/27/2019 | |||||||||||||||||||
15 | 8/27/2019 | Adminstrative | Determine Demos for MSDII | ALL | 8/27/2019 | Complete | 8/27/2019 | Pump, Full system | ||||||||||||||||||
16 | 8/28/2019 | Meeting/Discussion | MSDII Team Meeting 1 | ALL | 8/27/2019 | Complete | 8/28/2019 | |||||||||||||||||||
17 | 8/28/2019 | Purchasing | Order remaining parts to be purchased from BOM | DB | 8/28/2019 | Complete | 9/3/2019 | |||||||||||||||||||
18 | 8/28/2019 | Engineering | Develop test method for strain gauge calibration | ZC | 8/29/2019 | Skipped | 8/29/2019 | Strain gauge calib. pushed to Phase 2 | ||||||||||||||||||
19 | 8/28/2019 | Engineering | Increase 100/101 pin holes to .063" dia for .0625" pins | CP | 8/28/2019 | Complete | 8/29/2019 | |||||||||||||||||||
20 | 8/28/2019 | Meeting/Discussion | Final review of design and documentation for manufacture | ALL | 8/29/2019 | Complete | 9/3/2019 | set up power supply | ||||||||||||||||||
21 | 8/28/2019 | Engineering | Release 100/101 to machines shop for manufacture in qty 2 each | JT | 8/28/2019 | Complete | 8/29/2019 | Files to machine shop | ||||||||||||||||||
22 | 8/28/2019 | Documentation | Review/add to risk table | ALL | 8/28/2019 | Complete | 8/29/2019 | |||||||||||||||||||
23 | 8/28/2019 | Engineering | Design/create Wheatstone Bridge for strain gauge | DB | 8/29/2019 | Skipped | 8/29/2019 | Pushed to Phase 2 | ||||||||||||||||||
24 | 8/29/2019 | Meeting/Discussion | MSDII Class Meeting 2 | ALL | 8/29/2019 | Complete | 8/29/2019 | |||||||||||||||||||
25 | 8/29/2019 | Engineering | Test driving gear/motor interface | EE | 8/29/2019 | Complete | 8/29/2019 | Increase mate diameter/thicken gear | 1 | Make Motor Operational | 9/3/2019 | |||||||||||||||
26 | 8/29/2019 | Engineering | Detailed Design Review of LTS/Stand | CP | 8/29/2019 | Complete | 9/3/2019 | |||||||||||||||||||
27 | 8/29/2019 | Engineering | Finalized Risk Table and on Confluence | EE | 8/29/2019 | Complete | 8/29/2019 | 2 | write programs for simple testplans | |||||||||||||||||
28 | 8/29/2019 | Engineering | Add "pseudocode" to Test Methods to help D.Bean program logic | ZC | 8/29/2019 | Complete | 8/29/2019 | |||||||||||||||||||
29 | 8/29/2019 | Documentation | Test methods documentation on correct Confluence Page | ZC | 8/29/2019 | Complete | 8/29/2019 | 3 | make hardware for testplans (wheatstone bridge and strain gauge) | |||||||||||||||||
30 | 8/29/2019 | Documentation | Design documentation table of correct Confluence Page | JT | 8/29/2019 | Complete | 8/29/2019 | 4 | write code to get data from Encoder and strain gauge | |||||||||||||||||
31 | 8/29/2019 | Purchasing | Order LTS Parts | ALL | 8/29/2019 | Complete | 9/3/2019 | Pushed to 9/3 | 5 | Design and Make setup for Power efficiency test plan (shunt resistor) | ||||||||||||||||
32 | 8/29/2019 | Adminstrative | Develop schedule up to week 6 demo in detail | EE | 8/30/2019 | Complete | 8/29/2019 | 6 | Check all code is written for operation and test plans | |||||||||||||||||
33 | 8/29/2019 | Engineering | Get Elijah mm unit stl's of 109 for 3D print | CP | 8/29/2019 | Complete | 8/29/2019 | 7 | Start User interface (write code to display data/ plots) | |||||||||||||||||
34 | Week 2 | 9/3/2019 | Meeting/Discussion | MSD Class Meeting 3 | ALL | 9/3/2019 | Complete | 9/3/2019 | 8 | Setup the hardware for the UI (mouse, monitor/computer) | ||||||||||||||||
35 | 9/3/2019 | Meeting/Discussion | Meet with Dr. Ghoneim | ALL | 9/3/2019 | Skipped | 9/3/2019 | 9 | Set up Application for the UI | 11/15 | ||||||||||||||||
36 | 9/3/2019 | Adminstrative | Confluence Clean Up and review prep | ALL | 9/3/2019 | Complete | 9/5/2019 | |||||||||||||||||||
37 | 9/3/2019 | Manufacture | Check on status of 100/101 manufacture | JT | 9/3/2019 | Complete | 9/3/2019 | In progress | ||||||||||||||||||
38 | 9/3/2019 | Engineering | Reduce LTS Rod Diameter to < ID of bushing | JT | 9/3/2019 | Complete | 9/3/2019 | 0.495, 0.490? Just so not 0.5 on 0.5" | ||||||||||||||||||
39 | 9/3/2019 | Adminstrative | Get workspace | DB | 9/3/2019 | Complete | 9/3/2019 | |||||||||||||||||||
40 | 9/3/2019 | Engineering | Final review of Design | CP | 9/3/2019 | Complete | 9/5/2019 | |||||||||||||||||||
41 | 9/3/2019 | Engineering | Rev documents updated on Confluece | CP | 9/3/2019 | Complete | 9/5/2019 | |||||||||||||||||||
42 | 9/3/2019 | Purchasing | Order remaining parts (if any outstanding) | DB | 9/3/2019 | Complete | 9/5/2019 | |||||||||||||||||||
43 | 9/3/2019 | Adminstrative | Estimate time of completion for pump assemblies | ALL | 9/3/2019 | Complete | 9/3/2019 | 9/12 | ||||||||||||||||||
44 | 9/3/2019 | Engineering | Vibes analysis | EE | 9/5/2019 | Skipped | 9/5/2019 | |||||||||||||||||||
45 | 9/3/2019 | Manufacture | Start print of winding stand/109 | EE | 9/5/2019 | Complete | 9/5/2019 | |||||||||||||||||||
46 | 9/3/2019 | Meeting/Discussion | Review Prep | ALL | 9/3/2019 | Complete | 9/5/2019 | |||||||||||||||||||
47 | 9/4/2019 | Meeting/Discussion | MSD Team Meeting 2 | ALL | 9/4/2019 | Complete | 9/3/2019 | |||||||||||||||||||
48 | 9/4/2019 | Engineering | Motor/Gear Interface Finalized | EE | 9/4/2019 | Complete | 9/3/2019 | |||||||||||||||||||
49 | 9/4/2019 | Documentation | Quad Chart for Review | JT | 9/4/2019 | Complete | 9/3/2019 | |||||||||||||||||||
50 | 9/4/2019 | Status Update | Status Update Final Prep | ALL | 9/4/2019 | Complete | 9/3/2019 | |||||||||||||||||||
51 | 9/4/2019 | Engineering | Motor Control Demo | DB | 9/4/2019 | Skipped | 9/3/2019 | |||||||||||||||||||
52 | 9/4/2019 | Engineering | Print 1 Solid gear | EE | 9/4/2019 | Skipped | 9/3/2019 | |||||||||||||||||||
53 | 9/5/2019 | Meeting/Discussion | MSD Class Meeting 4 | ALL | 9/5/2019 | Complete | ||||||||||||||||||||
54 | 9/5/2019 | Status Update | Status Update 1 | ALL | 9/5/2019 | Complete | ||||||||||||||||||||
55 | 9/5/2019 | Assembly | Winding Fixture Assembly | CP | 9/5/2019 | Complete | ||||||||||||||||||||
56 | 9/5/2019 | Engineering | Electrical Stuff | DB | 9/5/2019 | Complete | ||||||||||||||||||||
57 | 9/5/2019 | Purchasing | Receive ordered parts for LTS/Stands | JT | 9/5/2019 | Skipped | ||||||||||||||||||||
58 | 9/5/2019 | Adminstrative | Schedule Review | EE | 9/5/2019 | Skipped | ||||||||||||||||||||
59 | Week 3 | 9/9/2019 | Meeting/Discussion | MSD Team Meeting 3 | ALL | Complete | ||||||||||||||||||||
60 | 9/9/2019 | Engineering | Winding Fixture Complete | CP | In Progress | Delayed. Printer clogged | ||||||||||||||||||||
61 | 9/9/2019 | Assembly | Start Winding If Ends Complete | ALL | Skipped | |||||||||||||||||||||
62 | 9/9/2019 | Meeting/Discussion | Dr. Ghoneim? | ALL | Complete | |||||||||||||||||||||
63 | 9/9/2019 | Manufacture | Begin manufacture of 105 | JT | Skipped | PICS approval delay | ||||||||||||||||||||
64 | 9/9/2019 | Manufacture | Begin Manufacture of 107 | ZC | Skipped | |||||||||||||||||||||
65 | 9/9/2019 | Manufacture | Cut 104 to length | EE | Skipped | |||||||||||||||||||||
66 | 9/10/2019 | Meeting/Discussion | MSD Class Meeting 5 | ALL | Complete | |||||||||||||||||||||
67 | 9/10/2019 | Documentation | Begin MSD Report | JT | Complete | http://edge.rit.edu/edge/P19603/public/Final%20Documents/P19603_Vader_Rod_Feeder.pdf | ||||||||||||||||||||
68 | 9/10/2019 | Testing | Planar Fiber LayUp | EE | In Progress | |||||||||||||||||||||
69 | 9/10/2019 | Manufacture | Start Second half print of WF | EE | Complete | |||||||||||||||||||||
70 | 9/10/2019 | Manufacture | Manufacturing day | ALL | Skipped | |||||||||||||||||||||
71 | 9/11/2019 | Meeting/Discussion | MSD Team Meeting 4 | ALL | Complete | |||||||||||||||||||||
72 | 9/11/2019 | Assembly | Build Electrical Hardware Stand | ZC | Complete | |||||||||||||||||||||
73 | 9/11/2019 | Testing | Test Plan Programs Halfway done (Simple ones) | DB | Not Started | |||||||||||||||||||||
74 | 9/11/2019 | Engineering | Status update of pump ends | CP | Complete | |||||||||||||||||||||
75 | 9/11/2019 | Engineering | Drawings for LTS done | JT | Complete | |||||||||||||||||||||
76 | 9/12/2019 | Meeting/Discussion | MSD Class Meeting 6 | ALL | Complete | |||||||||||||||||||||
77 | 9/12/2019 | Meeting/Discussion | Expected Pump Winding Date/Maximum Lead Time | CP | Complete | |||||||||||||||||||||
78 | 9/12/2019 | Purchasing | Receive order parts | DB | Complete | |||||||||||||||||||||
79 | 9/12/2019 | Purchasing | Purchase Wires/Connectors | DB | Complete | |||||||||||||||||||||
80 | 9/12/2019 | Manufacture | Begin LTS manufacture | JT | Complete | |||||||||||||||||||||
81 | 9/12/2019 | Engineering | Wire up electrical hardware stand | DB | Complete | |||||||||||||||||||||
82 | Week 4 | 9/16/2019 | Meeting/Discussion | MSD Team Meeting 3 | ALL | Complete | ||||||||||||||||||||
83 | 9/16/2019 | Manufacture | LTS | JT | Complete | |||||||||||||||||||||
84 | 9/16/2019 | Manufacture | Stands/LTS/Rods | CP | Complete | |||||||||||||||||||||
85 | 9/16/2019 | Manufacture | Pump, Stands | ZC | Complete | |||||||||||||||||||||
86 | 9/16/2019 | Manufacture | Pump | EE | Complete | |||||||||||||||||||||
87 | 9/16/2019 | Testing | Test electrical stuff | DB | Complete | |||||||||||||||||||||
88 | 9/16/2019 | Meeting/Discussion | Dr. Ghoneim Meeting | ALL | Complete | |||||||||||||||||||||
89 | 9/17/2019 | Meeting/Discussion | MSD Class Meeting 5 | ALL | Complete | |||||||||||||||||||||
90 | 9/17/2019 | Testing | Angular Encoder Test | DB | In Progress | |||||||||||||||||||||
91 | 9/17/2019 | Testing | Strain gauge test | DB | Not Started | |||||||||||||||||||||
92 | 9/17/2019 | Manufacture | LTS Complete | JT | In Progress | |||||||||||||||||||||
93 | 9/17/2019 | Manufacture | Winding with Dr. Ghoneim | EE | Complete | |||||||||||||||||||||
94 | Complete | |||||||||||||||||||||||||
95 | 9/18/2019 | Meeting/Discussion | MSD Team Meeting 4 | ALL | Complete | |||||||||||||||||||||
96 | 9/18/2019 | Assembly | Strain Gauge Testing | DB | Skipped | |||||||||||||||||||||
97 | 9/18/2019 | Manufacture | Stand Hardware cut out and off to be welded | ZC | Complete | |||||||||||||||||||||
98 | Winding | ALL | Complete | |||||||||||||||||||||||
99 | Winding Fixture | Complete | ||||||||||||||||||||||||
100 | 9/19/2019 | Meeting/Discussion | MSD Class Meeting 6 | ALL | Complete | |||||||||||||||||||||