2 | MONITORING PEMBAHASAN CO PADA PROYEK EPCC LAWE-LAWE FACILITIES RDMP RU-V BALIKPAPAN | ||||||||||||||||||||||||||||
3 | |||||||||||||||||||||||||||||
4 | No | CP/CN | Discripsi CO | No. Surat | Tgl Kirim | Tgl Pengajuan Ulang | No. Surat Revisi Terakhir | Nilai | Status | Rangkuman Hasil Pembahasan | |||||||||||||||||||
5 | Tgl | Tindak Lanjut | Target | Remark | |||||||||||||||||||||||||
6 | A. | Klaim ke Owner | |||||||||||||||||||||||||||
7 | 1 | CP-66 | Klaim atas Change in Law selama pandemi COVID-19 | 26076-JO-KPB-LT-01963 | 16-09-2020 | 1,515,323,416 | REJECTED | ||||||||||||||||||||||
8 | 2 | CP-02 | Klaim atas kompensasi biaya pembelian pipa 20 inch karena OWNER menginstruksikan pembelian dari lokal | 26076-JO-KPB-LT-00455 | 04/17/2021 | 18,647,778,861 | OWNER REVIEW | Pembahasan Jastek | |||||||||||||||||||||
9 | 3 | CP-07 | Klaim atas CP untuk Early Work Area 5 | 26076-JO-KPB-LT-00351 | 03-03-2021 | 11,425,249,522 | ACCEPTABLE IN PRINCIPLE | 3 s/d 4 Juli 2023 | MOM NR- /KPI37700/2023-S0 | ||||||||||||||||||||
10 | 1) Submit ulang revisi DED kepada Engineering KPB untuk mendapat aproval | 5 Juli 2023 | Close | ||||||||||||||||||||||||||
11 | 2) Mendapatkan approval dok (point 1) | 17 Juli 2023 | Open | ||||||||||||||||||||||||||
12 | 3) Menyelesaikan alignment WBS dan BoQ, dan disampaikan kembali ke KPB | 12 Juli 2023 | Open | ||||||||||||||||||||||||||
13 | 4) Melengkapi referensi untuk masing2 item yang terdapat pada MTO | 12 Juli 2023 | Open | ||||||||||||||||||||||||||
14 | 5) Menyiapkan negosiasi komersial | 24 Juli 2023 | Open | ||||||||||||||||||||||||||
15 | 4 | CP-14 | Additional Fire Water Hydrant, Post Indicator Valve (PIV) and Hose Cabinet at Lawe-Lawe Terminal | 26076-JO-KPB-LT-01655 | 15-06-2021 | 30-05-23 | 26076-JO-KPB-LT- 02733 | 37,150,414,839 | ACCEPTABLE IN PRINCIPLE | 7 s/d 8 Juli 2023 | 1) Klarifikasi dan penjelasan Jastek | 8 Juli 2023 | Closed | ||||||||||||||||
16 | 2) Klarifikasi dan penjelasan kronologi | 12 Juli 2023 | Open | ||||||||||||||||||||||||||
17 | 3) Finalisasi aspek kontraktual | 12 Juli 2023 | Open | ||||||||||||||||||||||||||
18 | 5 | CP-24 | Additional On-Off Valve on Plant Air Header | 26076-JO-KPB-LT-02137 | 17-10-2022 | 20-06-23 | 26076-JO-KPB-LT-02814 | 1,040,841,213 | OWNER REVIEW | ||||||||||||||||||||
19 | 6 | CP-39 | Additional Deluge Valve and Pressure Reduction on By-Pass Line Deluge Valve Water Spray System | 26076-JO-KPB-LT-01680 | 03-08-21 | 11-03-23 | 26076-JO-KPB-LT- 02523 | 3,855,405,720 | OWNER REVIEW | ||||||||||||||||||||
20 | 7 | CP-41 | External Power Supply (DC Charger) for 24 kV MV Switchgear | 26076-JO-KPB-LT-01755 | 23-10-21 | 11,907,776,335 | ACCEPTABLE IN PRINCIPLE | 3 s/d 4 Juli 2023 | MOM NR- /KPI37700/2023-S0 | ||||||||||||||||||||
21 | 1) Menyampaikan surat keterangan rating DC Charger dari pihak manufacture | 6 Juli 2023 | Closed | ||||||||||||||||||||||||||
22 | 2) Finalisasi strategi pengadaan remaining cable di internal KPI-KPB | 14 Juli 2023 | Open | ||||||||||||||||||||||||||
23 | 3) Menyelesaikan alignment WBS dan BoQ, dan disampaikan kembali ke KPB | 14 Juli 2023 | Open | ||||||||||||||||||||||||||
24 | 4) Menyiapkan negosiasi komersial | 24 Juli 2023 | Open | ||||||||||||||||||||||||||
25 | 8 | CP-46 | Soil Improvement Fire Water Tank Foundation | 26076-JO-KPB-LT-02097 | 08-11-21 | 31,487,458,689 | ACCEPTABLE IN PRINCIPLE | 3 s/d 4 Juli 2023 | MOM NR- /KPI37700/2023-S0 | ||||||||||||||||||||
26 | 1) Menyelesaikan alignment WBS dan BoQ, dan disampaikan kembali ke KPB | 12 Juli 2023 | Open | su | |||||||||||||||||||||||||
27 | 2) Membuat & Menyampaikan BA penyelesaian Pek. Soil Improvement | 12 Juli 2023 | Open | ||||||||||||||||||||||||||
28 | 3) Menyiapkan negosiasi komersial | 24 Juli 2023 | Open | ||||||||||||||||||||||||||
29 | 9 | CP-58 | Modification Substation 101-SS-03 Building Size | 26076-JO-KPB-LT-01882 | 25-03-22 | 23-05-23 | 26076-JO-KPB-LT- 02779 | 41,505,956,690 | OWNER REVIEW | ||||||||||||||||||||
30 | 10 | CP-81 | Additional Material Quantity Due To Errors | 26076-JO-KPB-LT-02554 | 15-05-23 | 19,532,028,515 | OWNER REVIEW | ||||||||||||||||||||||
31 | 11 | CP-76 | Power & Control Cable for Onshore Facilities | 26076-JO-KPB-LT-02511 | 07-03-23 | 286,952,818,982 | OWNER REVIEW | 5 s/d 7 Juli 2023 | 1) Klarifikasi dan penjelasan Jastek | 6 Juli 2023 | Closed | ||||||||||||||||||
32 | 2) Klarifikasi dan penjelasan kronologi | 12 Juli 2023 | Open | ||||||||||||||||||||||||||
33 | 3) Penjelasan aspek kontraktual | 12 Juli 2023 | Open | ||||||||||||||||||||||||||
34 | 4) Submit dok (point 1 & 2) secara official ke KPB sebagai additional data. Setelah Jastek tersebut final, selanjutnya KPB akan membalas apabila ada komen | INFO | |||||||||||||||||||||||||||
35 | 5) Target 1 bulan closed dan mendapat jawaban dari sterko | INFO | |||||||||||||||||||||||||||
36 | NILAI TOTAL | 465,021,052,782 | |||||||||||||||||||||||||||
39 | 1 | CN-15 | Change Notification for Provision of Dike at Diesel Fuel Storage Tank (433-T-03) | 26076-JO-KPB-LT-00617 | 15-06-21 | 222,874,427 | |||||||||||||||||||||||
40 | 2 | CN-20 | Change Notification for Flowmeter Type Changes on Fire Water Pump Testing Line at Unit 433 Lawe-Lawe Terminal | 26076-JO-KPB-LT-00707 | 06-07-21 | Not Yet Estimate | |||||||||||||||||||||||
41 | 3 | CN-21 | Change Notification of Additional Pressure Transmitter | 26076-JO-KPB-LT-00632 | 16-06-21 | 163,726,805 | |||||||||||||||||||||||
42 | 4 | CN-22 | Change Notification of Additional Pressure Transmitter at Fire Water Network | 26076-JO-KPB-LT-00633 | 16-06-21 | 34,384,349 | |||||||||||||||||||||||
43 | 5 | CN-23 | Change Notification for the Changing in Control Valve 431-PV-030 Capacity | 26076-JO-KPB-LT-00634 | 16-06-21 | Not Yet Estimate | |||||||||||||||||||||||
44 | 6 | CN-26 | Change Notification of Additional Feature Connection for Pressure Instrumentation at Pump Suction and Discharge | 26076-JO-KPB-LT-00690 | 03-07-21 | 257,659,521 | |||||||||||||||||||||||
45 | 7 | CN-27 | Change Notification of Update Specification of Piping Materials for Bolt and Nut | 26076-JO-KPB-LT-00691 | 03-07-21 | 331,200,000 | |||||||||||||||||||||||
46 | 8 | CN-32 | Change Notification for Demineralized Water System from CS - SS and Flash Water Cooler Tube Passed | 26076-JO-KPB-LT-00726 | 13-07-21 | 6,097,976,789 | |||||||||||||||||||||||
47 | 9 | CN-33 | Change Notification of Additional Steam Line and Chemical Injection with Check Valve in Deaerator System | 26076-JO-KPB-LT-00727 | 13-07-21 | 47,653,178 | |||||||||||||||||||||||
48 | 10 | CN-37 | Change Notification of New Item Oil Pit in Transformers Area | 26076-JO-KPB-LT-00749 | 19-07-21 | 150,000,000 | |||||||||||||||||||||||
49 | 11 | CN-40 | Change Notification of FO Cable for Feeder Differential Protection from PLN Substation to Extend Substation | 26076-JO-KPB-LT-00919 | 31-08-21 | 5,312,103 | |||||||||||||||||||||||
50 | 12 | CN-47 | Change Notification for Redudancy Server for CCTV and ACS | 26076-JO-KPB-LT-01280 | 03-01-21 | Not Yet Estimate | |||||||||||||||||||||||
51 | 13 | CN-63 | Change Notification for Change Rating of AC UPS 220V | 26076-JO-KPB-LT- 01733 | 30-May-22 | 4,800,000,000 | |||||||||||||||||||||||
52 | 14 | CN-65 | Change Notification for Change in Law due to the Requirement under the Regulation of the Minister of Energy and Mineral Resources No. 32 year 2021 about Technical Inspection and Inspection of Safety of Installations and Equipment in Oil and Gas Business Activities | 26076-JO-KPB-LT-001831 | 30-06-22 | 10,515,000,000 | |||||||||||||||||||||||
53 | 15 | CN-67 | Change Proposal No. 67 for the Interim Extension of Time Milestone 1 | NOT YET | waktu | ||||||||||||||||||||||||
54 | 16 | CN-73 | Change Notification & Propose the Re-Negotiation on Contract Price Due to Increment Fuel and Asphalt Price | 26076-JO-KPB-LT- 02260 | 28-11-22 | 1,931,631,087 | |||||||||||||||||||||||
55 | 17 | CN-74 | Change Notification regarding Proposed Additional Vendor for Demineralized Package | 26076-JO-KPB-LT-02349 | 11-01-23 | waktu | |||||||||||||||||||||||
56 | 18 | CN-76 | Change Notification for Ductile Iron Valve | 26076-JO-KPB-LT-02499 | 07-03-23 | 3,060,000,000 | |||||||||||||||||||||||
57 | 19 | Integrated Control and Safety System (ICSS) | NOT YET | NOT YET | Not Yet Estimate | ||||||||||||||||||||||||
58 | 20 | CN-77 | Aerator Package System 432-A-01 Raw Water Treatment Plant | 26076-JO-KPB-LT- 02519 | 14-03-23 | 2,889,178,237 | |||||||||||||||||||||||
59 | 21 | CN-79 | Waste Water Treatment Plant | 26076-JO-KPB-LT- 02520 | 14-03-23 | 6,382,568,710 | |||||||||||||||||||||||
60 | 22 | CN-82 | LP Boiler Package | 26076-JO-KPB-LT- 02524 | 17-03-23 | 840,000,000 | |||||||||||||||||||||||
61 | 23 | CN-78 | Deep Well Pump 432-P-03 A/B/C/D/E | 26076-JO-KPB-LT- 02518 | 11-03-23 | 864,000,000 | |||||||||||||||||||||||
62 | 24 | Deaerator 431-DA-01 | NOT YET | NOT YET | Not Yet Estimate | ||||||||||||||||||||||||
63 | 25 | Instrument Air /Plant Air Package | NOT YET | NOT YET | Not Yet Estimate | ||||||||||||||||||||||||
64 | 26 | CN-80 | Change Notification of Additional Work Access Road & Paving for Operational on Penajam Station | 26076-JO-KPB-LT- 02521 | 14-03-23 | 365,034,195 | |||||||||||||||||||||||
65 | 27 | Elin Instlation Ms-2 | NOT YET | NOT YET | 10,566,926,486 | ||||||||||||||||||||||||
66 | 28 | CN-84 | Piping | 26076-JO-KPB-LT-02703 | 12-05-23 | 25,000,000,000 | |||||||||||||||||||||||
67 | 29 | CN-83 | Electrical Equipment and Changes Rating | 26076-JO-KPB-LT-02630 | 15-04-23 | 11,925,000,000 | |||||||||||||||||||||||
68 | 30 | Kenaikan Harga | 149,305,216,873 | ||||||||||||||||||||||||||
69 | NILAI TOTAL | 235,755,342,758 | |||||||||||||||||||||||||||
72 | 1 | Biaya Take Over Engineering | 65,072,875,851 | ||||||||||||||||||||||||||
73 | NILAI GRAND TOTAL | 765,849,271,391 | |||||||||||||||||||||||||||
74 | |||||||||||||||||||||||||||||
75 | Note : | ||||||||||||||||||||||||||||
76 | - | Change Notification ( CN ) berupa dokumen pemberitahuan/ notifikasi adanya change order | |||||||||||||||||||||||||||
77 | - | Change Proposal ( CP ) Berupa dokumen Proposal Change Order yang berisi evidence, BoQ, dokumen teknis dan commersial | |||||||||||||||||||||||||||
78 | |||||||||||||||||||||||||||||
79 | |||||||||||||||||||||||||||||
80 | |||||||||||||||||||||||||||||
81 | |||||||||||||||||||||||||||||
82 | |||||||||||||||||||||||||||||
83 | |||||||||||||||||||||||||||||
84 | |||||||||||||||||||||||||||||
85 | |||||||||||||||||||||||||||||
86 | |||||||||||||||||||||||||||||
87 | |||||||||||||||||||||||||||||
88 | |||||||||||||||||||||||||||||
89 | |||||||||||||||||||||||||||||
90 | |||||||||||||||||||||||||||||
91 | |||||||||||||||||||||||||||||
92 | |||||||||||||||||||||||||||||
93 | |||||||||||||||||||||||||||||
94 | |||||||||||||||||||||||||||||
95 | |||||||||||||||||||||||||||||
96 | |||||||||||||||||||||||||||||
97 | |||||||||||||||||||||||||||||
98 | |||||||||||||||||||||||||||||
99 | |||||||||||||||||||||||||||||
100 | |||||||||||||||||||||||||||||
101 | |||||||||||||||||||||||||||||
102 | |||||||||||||||||||||||||||||
103 | |||||||||||||||||||||||||||||
104 | |||||||||||||||||||||||||||||