ABCDEFGHIJKMNORSTUVWXYZAAABACADAE
1
2
MONITORING PEMBAHASAN CO PADA PROYEK EPCC LAWE-LAWE FACILITIES RDMP RU-V BALIKPAPAN
3
4
NoCP/CNDiscripsi CONo. SuratTgl
Kirim
Tgl Pengajuan Ulang No. Surat Revisi Terakhir NilaiStatusRangkuman Hasil Pembahasan
5
TglTindak LanjutTargetRemark
6
A.Klaim ke Owner
7
1CP-66Klaim atas Change in Law selama pandemi COVID-1926076-JO-KPB-LT-0196316-09-2020 1,515,323,416 REJECTED
8
2CP-02Klaim atas kompensasi biaya pembelian pipa 20 inch karena OWNER menginstruksikan pembelian dari lokal26076-JO-KPB-LT-0045504/17/2021 18,647,778,861 OWNER REVIEW
Pembahasan Jastek
9
3CP-07Klaim atas CP untuk Early Work Area 526076-JO-KPB-LT-0035103-03-2021 11,425,249,522 ACCEPTABLE
IN PRINCIPLE
3 s/d 4 Juli 2023MOM NR- /KPI37700/2023-S0
10
1) Submit ulang revisi DED kepada Engineering KPB untuk mendapat aproval
5 Juli 2023Close
11
2) Mendapatkan approval dok (point 1)
17 Juli 2023Open
12
3) Menyelesaikan alignment WBS dan BoQ, dan disampaikan kembali ke KPB
12 Juli 2023Open
13
4) Melengkapi referensi untuk masing2 item yang terdapat pada MTO
12 Juli 2023Open
14
5) Menyiapkan negosiasi komersial
24 Juli 2023Open
15
4CP-14Additional Fire Water Hydrant, Post Indicator Valve (PIV) and Hose Cabinet
at Lawe-Lawe Terminal
26076-JO-KPB-LT-0165515-06-202130-05-23 26076-JO-KPB-LT- 02733 37,150,414,839 ACCEPTABLE
IN PRINCIPLE
7 s/d 8 Juli 20231) Klarifikasi dan penjelasan Jastek
8 Juli 2023Closed
16
2) Klarifikasi dan penjelasan kronologi
12 Juli 2023Open
17
3) Finalisasi aspek kontraktual
12 Juli 2023Open
18
5CP-24Additional On-Off Valve on Plant Air Header26076-JO-KPB-LT-0213717-10-202220-06-23 26076-JO-KPB-LT-02814 1,040,841,213 OWNER REVIEW
19
6CP-39Additional Deluge Valve and Pressure Reduction on By-Pass Line Deluge Valve Water Spray System26076-JO-KPB-LT-0168003-08-2111-03-23 26076-JO-KPB-LT- 02523 3,855,405,720 OWNER REVIEW
20
7CP-41External Power Supply (DC Charger) for 24 kV MV Switchgear26076-JO-KPB-LT-0175523-10-21 11,907,776,335 ACCEPTABLE
IN PRINCIPLE
3 s/d 4 Juli 2023MOM NR- /KPI37700/2023-S0
21
1) Menyampaikan surat keterangan rating DC Charger dari pihak manufacture
6 Juli 2023Closed
22
2) Finalisasi strategi pengadaan remaining cable di internal KPI-KPB
14 Juli 2023Open
23
3) Menyelesaikan alignment WBS dan BoQ, dan disampaikan kembali ke KPB
14 Juli 2023Open
24
4) Menyiapkan negosiasi komersial
24 Juli 2023Open
25
8CP-46Soil Improvement Fire Water Tank Foundation26076-JO-KPB-LT-0209708-11-21 31,487,458,689 ACCEPTABLE
IN PRINCIPLE
3 s/d 4 Juli 2023MOM NR- /KPI37700/2023-S0
26
1) Menyelesaikan alignment WBS dan BoQ, dan disampaikan kembali ke KPB
12 Juli 2023Opensu
27
2) Membuat & Menyampaikan BA penyelesaian Pek. Soil Improvement
12 Juli 2023Open
28
3) Menyiapkan negosiasi komersial
24 Juli 2023Open
29
9CP-58Modification Substation 101-SS-03 Building Size26076-JO-KPB-LT-0188225-03-2223-05-23 26076-JO-KPB-LT- 02779 41,505,956,690 OWNER REVIEW
30
10CP-81Additional Material Quantity Due To Errors26076-JO-KPB-LT-0255415-05-23 19,532,028,515 OWNER REVIEW
31
11CP-76Power & Control Cable for Onshore Facilities26076-JO-KPB-LT-0251107-03-23 286,952,818,982 OWNER REVIEW5 s/d 7 Juli 20231) Klarifikasi dan penjelasan Jastek
6 Juli 2023Closed
32
2) Klarifikasi dan penjelasan kronologi
12 Juli 2023Open
33
3) Penjelasan aspek kontraktual
12 Juli 2023Open
34
4) Submit dok (point 1 & 2) secara official ke KPB sebagai additional data.
Setelah Jastek tersebut final, selanjutnya KPB akan membalas apabila ada komen
INFO
35
5) Target 1 bulan closed dan mendapat jawaban dari sterko
INFO
36
NILAI TOTAL
465,021,052,782
39
1CN-15Change Notification for Provision of Dike at Diesel Fuel Storage Tank (433-T-03)26076-JO-KPB-LT-0061715-06-21 222,874,427
40
2CN-20Change Notification for Flowmeter Type Changes on Fire Water Pump Testing Line at Unit 433 Lawe-Lawe Terminal26076-JO-KPB-LT-0070706-07-21Not Yet Estimate
41
3CN-21Change Notification of Additional Pressure Transmitter26076-JO-KPB-LT-0063216-06-21 163,726,805
42
4CN-22Change Notification of Additional Pressure Transmitter at Fire Water Network26076-JO-KPB-LT-0063316-06-21 34,384,349
43
5CN-23Change Notification for the Changing in Control Valve 431-PV-030 Capacity26076-JO-KPB-LT-0063416-06-21Not Yet Estimate
44
6CN-26Change Notification of Additional Feature Connection for Pressure Instrumentation at Pump Suction and Discharge26076-JO-KPB-LT-0069003-07-21 257,659,521
45
7CN-27Change Notification of Update Specification of Piping Materials for Bolt and Nut26076-JO-KPB-LT-0069103-07-21 331,200,000
46
8CN-32Change Notification for Demineralized Water System from CS - SS and Flash Water Cooler Tube Passed26076-JO-KPB-LT-0072613-07-21 6,097,976,789
47
9CN-33Change Notification of Additional Steam Line and Chemical Injection with Check Valve in Deaerator System26076-JO-KPB-LT-0072713-07-21 47,653,178
48
10CN-37Change Notification of New Item Oil Pit in Transformers Area26076-JO-KPB-LT-0074919-07-21 150,000,000
49
11CN-40Change Notification of FO Cable for Feeder Differential Protection from PLN Substation to Extend Substation26076-JO-KPB-LT-0091931-08-21 5,312,103
50
12CN-47Change Notification for Redudancy Server for CCTV and ACS26076-JO-KPB-LT-0128003-01-21Not Yet Estimate
51
13CN-63Change Notification for Change Rating of AC UPS 220V26076-JO-KPB-LT- 0173330-May-22 4,800,000,000
52
14CN-65Change Notification for Change in Law due to the Requirement under the Regulation of the Minister of Energy and Mineral Resources No. 32 year 2021 about Technical Inspection and Inspection of Safety of Installations and Equipment in Oil and Gas Business Activities26076-JO-KPB-LT-00183130-06-22 10,515,000,000
53
15CN-67Change Proposal No. 67 for the Interim Extension of Time Milestone 1NOT YET waktu
54
16CN-73Change Notification & Propose the Re-Negotiation on Contract Price Due to Increment Fuel and Asphalt Price26076-JO-KPB-LT- 0226028-11-22 1,931,631,087
55
17CN-74Change Notification regarding Proposed Additional Vendor for Demineralized Package26076-JO-KPB-LT-02349 11-01-23 waktu
56
18
CN-76
Change Notification for Ductile Iron Valve26076-JO-KPB-LT-0249907-03-23 3,060,000,000
57
19Integrated Control and Safety System (ICSS)NOT YETNOT YETNot Yet Estimate
58
20CN-77Aerator Package System 432-A-01
Raw Water Treatment Plant
26076-JO-KPB-LT- 0251914-03-23 2,889,178,237
59
21CN-79Waste Water Treatment Plant26076-JO-KPB-LT- 0252014-03-23 6,382,568,710
60
22CN-82LP Boiler Package26076-JO-KPB-LT- 0252417-03-23 840,000,000
61
23CN-78Deep Well Pump 432-P-03 A/B/C/D/E26076-JO-KPB-LT- 0251811-03-23 864,000,000
62
24Deaerator 431-DA-01NOT YETNOT YETNot Yet Estimate
63
25Instrument Air /Plant Air PackageNOT YETNOT YETNot Yet Estimate
64
26CN-80Change Notification of Additional Work Access Road & Paving for Operational on Penajam Station26076-JO-KPB-LT- 0252114-03-23 365,034,195
65
27Elin Instlation Ms-2NOT YETNOT YET 10,566,926,486
66
28CN-84Piping26076-JO-KPB-LT-0270312-05-23 25,000,000,000
67
29CN-83Electrical Equipment and Changes Rating26076-JO-KPB-LT-0263015-04-23 11,925,000,000
68
30Kenaikan Harga 149,305,216,873
69
NILAI TOTAL
235,755,342,758
72
1Biaya Take Over Engineering 65,072,875,851
73
NILAI GRAND TOTAL 765,849,271,391
74
75
Note :
76
-
Change Notification ( CN ) berupa dokumen pemberitahuan/ notifikasi adanya change order
77
-
Change Proposal ( CP ) Berupa dokumen Proposal Change Order yang berisi evidence, BoQ, dokumen teknis dan commersial
78
79
80
81
82
83
84
85
86
87
88
89
90
91
92
93
94
95
96
97
98
99
100
101
102
103
104