DESCRIPTIONQUANTITYUNITUNIT COSTTOTAL COST
5
6
MaterialLaborTotal
7
BUILDING SHELL WORKS
8
1
MOBILIZATION
9
MOBILIZATION/ DEMOBILIZATION(BUNK HOUSE + TEMPORARY ELECTRICITY )
1LOT40,000.0040,000.0040,000.00
10
11
SUBTOTAL (MOBILIZATION)40,000.00
12
2
STAKEOUT
13
2X2X10' COCO50PCS 100.00 60.00160.008,000.00
14
NYLON STRING2ROLL 150.00 90.00240.00480.00
15
4" CWN3KLS.70.0042.00112.00336.00
16
2 1/2" CWN3KLS. 70.00 42.00112.00336.00
17
18
SUBTOTAL (STAKEOUT)9,152.00
19
3
COLUMN FOOTING 25.8 153
20
SOIL EXCAVATION155CU.M.2,200.002,200.00341,000.00
21
PORTLAND CEMENT310BAGS 250.00 150.00400.00124,000.00
22
WASHED SAND13CU.M. 1,850.00 1,110.002,960.0038,480.00
23
G1" WASHED GRAVEL26CU.M. 1,850.00 1,110.002,960.0076,960.00
24
20MM DIA. DSB X 6M GR. 60149LTHS. 780.00 468.001,248.00185,952.00
25
16MM DIA. DSB X 6M GR.4013LTHS. 455.00 273.00728.009,464.00
26
# 16 G.I. TIE WIRE1ROLL 1,980.00 1,188.003,168.003,168.00
27
SUBTOTAL (COLUMN FOOTING)779,024.00
28
29
4
COLUMN 42.5
30
PORTLAND CEMENT510BAGS250.00150.00400.00204,000.00
31
WASHED SAND22CU.M. 1,850.00 1,110.002,960.0065,120.00
32
3/4 WASHED GRAVEL44CU.M.1,850.001,110.002,960.00130,240.00
33
20MM DIA. DSB X 6M GR.60215LTHS.780.00468.001,248.00268,320.00
34
20MM DIA. DSB X 7.5M GR.60
151LTHS.975.00585.001,560.00235,560.00
35
16MM DIA. DSB X 6M GR.4050LTHS.455.00273.00728.0036,400.00
36
10MM DIA. DSB X 6M GR.331150LTHS. 148.00 88.80236.80272,320.00
37
# 16 G.I. TIE WIRE12ROLLS1,980.001,188.003,168.0038,016.00
38
2X3X10' COCO SCAFFOLDS600LTHS. 150.00 90.00240.00144,000.00
39
2X2X8' COCO FORMS560LTHS. 80.00 48.00128.0071,680.00
40
1/2 " PHENOLIC BOARD45SHTS.1760.001,056.002,816.00126,720.00
41
4" CWN40KLS.70.0042.00112.004,480.00
42
2 1/2" CWN40KLS. 70.00 42.00112.004,480.00
43
SUBTOTAL (GROUND FLOOR COLUMN)1,601,336.00
44
5
SLAB ON FILL 22.3
45
PORTLAND CEMENT267BAGS 250.00 150.00400.00106,800.00
46
WASHED SAND11CU.M. 1,850.00 1,110.002,960.0032,560.00
47
3/4 WASHED GRAVEL22CU.M.1,850.001,110.002,960.0065,120.00
48
10MM DIA. DSB X 6M186LTHS. 148.00 88.80236.8044,044.80
49
#16 G.I. TIE WIRE8KLS.100.0060.00160.001,280.00
50
51
SUBTOTAL (SLAB ON FILL)249,804.80
52
6
TIE BEAM & STRAP BEAM 16.65
53
PORTLAND CEMENT205BAGS 250.00 150.00400.0082,000.00
54
WASHED SAND9CU.M. 1,850.00 1,110.002,960.0026,640.00
55
3/4 WASHED GRAVEL18CU.M.1,850.001,110.002,960.0053,280.00
56
16MM DIA. DSB X 6M GR. 40255LHTS.455.00273.00728.00185,640.00
57
10MM DIA. DSB X 6M 300LHTS. 148.00 88.80236.8071,040.00
58
# 16 G.I. TIE WIRE4ROLLS1980.001,188.003,168.0012,672.00
59
2X2X10' COCO SCAFFOLDS60LTHS. 150.00 90.00240.0014,400.00
60
2X2X8' COCO FORMS80LHTS. 80.00 48.00128.0010,240.00
61
3/8" ORDINARY PLYWOOD25SHTS. 550.00 330.00880.0022,000.00
62
4" CWN10KLS.70.0042.00112.001,120.00
63
2 1/2" CWN10KLS 70.00 42.00112.001,120.00
64
1 1/2" CWN5KLS.70.0042.00112.00560.00
65
66
SUBTOTAL (TIE BEAM)480,712.00
67
7
FLOOR BEAM 27
68
PORTLAND CEMENT342BAGS 250.00 150.00400.00136,800.00
69
WASHED SAND15CU.M. 1,850.00 1,110.002,960.0044,400.00
70
3/4 WASHED GRAVEL30CU.M.1,850.001,110.002,960.0088,800.00
71
16MM DIA. DSB X 6M GR.60600LTHS. 465.00 279.00744.00446,400.00
72
10MM DIA. DSB X 6M 850LTHS. 148.00 88.80236.80201,280.00
73
# 16 G.I. TIE WIRE14ROLLS1980.001,188.003,168.0044,352.00
74
2X3X10' COCO SCAFFOLDS350LTHS. 150.00 90.00240.0084,000.00
75
2X2X8' COCO FORMS460LTHS. 70.00 42.00112.0051,520.00
76
1/2" PHENOLIC BOARD68SHTS. 1,760.00 1,056.002,816.00191,488.00
77
4" CWN20KLS.65.0039.00104.002,080.00
78
3" CWN20KLS. 65.00 39.00104.002,080.00
79
2 1/2" CWN20KLS.65.0039.00104.002,080.00
80
1" CWN20KLS.65.0039.00104.002,080.00
81
SUBTOTAL ( BEAM)1,297,360.00
82
8
CONCRETE CANOPY AND MOULDINGS
83
CONCRETE CANOPY AND MOULDINGS
25LN M 1,000.00 600.001,600.0040,000.00
84
85
SUBTOTAL (CONCRETE CANOPY AND MOULDINGS)40,000.00
86
9
WALL FOOTINGS, CHB WALLS, PLASTERING & WATERPROOFING
87
SOIL EXCAVATION12CU.M.2,200.002,200.0026,400.00
88
POZZOLAN CEMENT510BAGS 200.00 120.00320.00163,200.00
89
PORTLAND CEMENT720BAGS 250.00 150.00400.00288,000.00
90
WASHED SAND59CU.M. 1,800.00 1,080.002,880.00169,920.00
91
3/4 WASHED GRAVEL6CU.M.1,800.001,080.002,880.0017,280.00
92
FINE SAND (FOR PLASTERING)
33CU.M.1,800.001,080.002,880.0095,040.00
93
10MM DIA. DSB X 6M 630LTHS. 148.00 88.80236.80149,184.00
94
#16 G.I. TIE WIRE2ROLLS1980.001,188.003,168.006,336.00
95
4" CHB5,980PCS. 20.00 12.0032.00191,360.00
96
6" CHB5,450PCS. 30.00 18.0048.00261,600.00
97
SAPAL RTU17PAILS 5,100.00 3,060.008,160.00138,720.00
98
CLEVER SIL,EPOCOAT MB,LEAK PLUG
36PAILS5,940.003,564.009,504.00342,144.00
99
100
SUBTOTAL (WALL FOOTING, CHB WALLS AND PLASTERING)1,849,184.00