A | B | C | D | E | F | G | H | I | J | K | L | M | N | O | P | Q | R | S | T | U | V | W | X | Y | Z | |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1 | February | |||||||||||||||||||||||||
2 | ID | Item | 10/02/2013 | 11/02/2013 | 12/02/2013 | 13/02/2013 | 14/02/2013 | 15/02/2013 | 16/02/2013 | 17/02/2013 | 18/02/2013 | 19/02/2013 | 20/02/2013 | 21/02/2013 | 22/02/2013 | 23/02/2013 | 24/02/2013 | 25/02/2013 | 26/02/2013 | 27/02/2013 | 28/02/2013 | Predecessors | Comments (qwazix) | Comments (warfare) | Comments (DocScrutinizer) | Comments (other) |
3 | IPHH | Total costs: <300 for hw-upgrade, 100..300 shipping 0/mo | ||||||||||||||||||||||||
4 | ||||||||||||||||||||||||||
5 | HFA | HiFo Approval | ||||||||||||||||||||||||
6 | CS | Contracts signing | HFA | |||||||||||||||||||||||
7 | SS | Server shipment | HFA | I'm putting 3 in case it takes longer | Should take around 2 working days | shipping costs TBD on Monday, should be <300 | ||||||||||||||||||||
8 | SPS | Server physical set up | SS | |||||||||||||||||||||||
9 | SSW | Server sw setup | SPS | |||||||||||||||||||||||
10 | DT | Data transfer | SSW | DNS transfer/switching? | ||||||||||||||||||||||
11 | TD | Testing deployment | DT | will 2 days for integration and test suffice? | ||||||||||||||||||||||
12 | See comments here ==> | re: warfare's comment ---> I agree, and even if they will not provide for another year, we can go to Hetzner (solution 2) anytime within 15 working days (See below) | I think, IPHH is the cheapest and safest for a year. If they won't continue, they will let us know well in advance and this buys us lots of time, to get our infrastructure straightened out. | I second warfare's comment <-- Ading the remark that nothing beats having a sysop with direct access to the servers. HW-upgrade as specified by Falk/warfare - a few HDD to beef up servers to 4TB and some for backup | ||||||||||||||||||||||
13 | Hetzner | Total costs: 400€ setup. <300/mo | ||||||||||||||||||||||||
14 | ||||||||||||||||||||||||||
15 | HFA | HiFo Approval | ||||||||||||||||||||||||
16 | SOP | Servers order & payment | HFA | |||||||||||||||||||||||
17 | HZ | Server setup by Hetzner | SOP | Does Hetzner provide servers immediately? | Sometimes takes up to 24 hours, if they need paperwork | two days definitely are enough. Usually 24h max | ||||||||||||||||||||
18 | SSW | Server software setup | HZ | |||||||||||||||||||||||
19 | DT | Data transfer | SSW | |||||||||||||||||||||||
20 | TD | Testing deployment | DT | |||||||||||||||||||||||
21 | ||||||||||||||||||||||||||
22 | Osuosl | Total costs: setup >>600€(CoLo shipping), ???/mo | ||||||||||||||||||||||||
23 | ||||||||||||||||||||||||||
24 | HFA | HiFo Approval | Moving maemo out of EU and to US legislative might be incompatible to usage terms of maemo. US has weaker privacy protection and possibly higher risk for patent trolls | |||||||||||||||||||||||
25 | LEG | legal check | HFA | |||||||||||||||||||||||
26 | CS | Contracts signing | LEG | |||||||||||||||||||||||
27 | SPS | Server physical set up | LEG | I didn't even consider shipping | shipping UPS: 48h:1300€, 7d:630€ | |||||||||||||||||||||
28 | SSW | Server sw setup | SPS | the iron to the US | ||||||||||||||||||||||
29 | DT | Data transfer | SSW | This timeline is for getting | ||||||||||||||||||||||
30 | TD | Testing deployment | DT | rootservers or VM's | ||||||||||||||||||||||
31 | ||||||||||||||||||||||||||
32 | Legend | General Comments | ||||||||||||||||||||||||
33 | ||||||||||||||||||||||||||
34 | Depending on us to speed up | I find this timeline too packed, and it is easy to lose a day or two for some reason (somebody sick, shipping delays or other unpredictable things) so while there is some slack in HiFo's approval, quick approval is of paramount importance as it is better to have the slack at the end rather than eat it all from the beginning. | ||||||||||||||||||||||||
35 | Not depending on us | |||||||||||||||||||||||||
36 | Critical end date | |||||||||||||||||||||||||
37 | Slack/Uncertainty | |||||||||||||||||||||||||
38 | ||||||||||||||||||||||||||
39 | ||||||||||||||||||||||||||
40 | ||||||||||||||||||||||||||
41 | ||||||||||||||||||||||||||
42 | ||||||||||||||||||||||||||
43 | ||||||||||||||||||||||||||
44 | ||||||||||||||||||||||||||
45 | ||||||||||||||||||||||||||
46 |