Name of Work:CONSTRUCTION OF ACADAMIC BLOCK COLLEGE BUILDING
2
GENERAL ABSTRACT OF ESTIMATE
3
Sl.NoSub Head Amount in RS.
4
5
1 Earth Work 170,435
6
2 Concrete Work 448,247
7
3 Reinforced Concrete Work 8,154,913
8
4 Brick Work 2,191,682
9
5 Marble Work 369,940
10
6 Wood Work 297,261
11
7 Steel Work 387,490
12
8 Flooring 885,627
13
9 Roofing 548,427
14
10 Finishing 1,476,966
15
11 Miscellaneous Building 979,567
16
12 Sanitary Installation 32,988
17
13 Water Supply 188,710
18
14 Drainage 216,315
19
15 Pile Work 3,553,368
20
16 External Service connection @ 5% 995,097
21
17 Internal Electrical Installations @ 12.5% 2,487,742
22
18 Quality Contorl Charges @ 1% 199,019
23
19 Fire fighting 300,000
24
20 Site development wise pathway, approach road, separate borewell 2,630,000
25
21 Tender Advertisement Charges 100,000
26
22 Consultancy charges 150,000
27
23 Contingencies @ 3% 596,891
28
24 VAT @ 0.7% 139,314
29
GRAND TOTAL 27,500,000
30
( Rupees Two Crores Seventy Five Lakhs only )
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
80
81
82
83
84
85
86
87
88
89
90
91
92
93
94
95
96
97
98
99
100