OUTSTANDING WORK FOR ECS Date: 13/10/22
3
4
No.Build. & FloorRooms NameCategoryTradeInstallationSite Progress StatusMaterial RequiredTarget Completion
Date
Target Completion
Date (Modified)
Remark
5
6
1OCC/ L3SER 2CAT-B (D2)ECSPressure test and PU insulationIn-Progess03-10-2222-10-22after CHWP installation
7
2CAT-B (D2)ECSSecondary Drain panPendingSecondary drain pan04-10-2225-10-22
8
3CAT-B (D2)ECSCDP workPending06-10-2227-10-22after CHWP installation
9
10
1OCC/ L3SER 3CAT-B (D2)ECSPU insulationIn-Progess01-10-2201-10-22
11
2CAT-B (D2)ECSSecondary Drain panPendingSecondary drain pan03-10-2203-10-22
12
3CAT-B (D2)ECSCDP workPending05-10-2215-10-22
13
14
1OCC/ L3SER 4CAT-B (D2)ECSPU insulationPending01-10-2201-10-22after CHWP installation
15
2CAT-B (D2)ECSSecondary Drain panPendingSecondary drain pan03-10-2203-10-22
16
3CAT-B (D2)ECSCDP workPending05-10-2217-10-22
17
18
1OCC/ L3CE/ISCS 2CAT-B (D2)ECSPU insulationPending04-10-2215-10-22
19
2CAT-B (D2)ECSSecondary Drain panPendingSecondary drain pan05-10-2216-10-22
20
3CAT-B (D2)ECSCDP workPending07-10-2220-10-22after CHWP installation
21
22
1OCC/ L3CE/ISCS 3CAT-B (D2)ECSChilled water piping workIn-Progess12-10-2215-10-22
23
2CAT-B (D2)ECSPressure test and PU insulationPending13-10-2202-11-22after CHWP installation
24
3CAT-B (D2)ECSSecondary Drain panPendingSecondary drain pan15-10-2203-11-22
25
4CAT-B (D2)ECSCDP workPending17-10-2207-11-22after CHWP installation
26
27
1OCC/ L3CE/ISCS 4CAT-B (D2)ECSChilled water piping workIn-Progess12-10-2216-10-22
28
2CAT-B (D2)ECSPressure test and PU insulationPending13-10-2204-11-22after CHWP installation
29
3CAT-B (D2)ECSSecondary Drain panPendingSecondary drain pan15-10-2205-11-22
30
4CAT-B (D2)ECSCDP workPending17-10-2210-11-22after CHWP installation
31
32
1OCC/ L3TTCR 2CAT-B (D2)ECSPressure test and PU insulationPending05-10-2222-10-22after CHWP installation
33
2CAT-B (D2)ECSSecondary Drain panPendingSecondary drain pan06-10-2225-10-22
34
3CAT-B (D2)ECSCDP workPending08-10-2228-10-22after CHWP installation
35
36
1OCC/ L3TTCR 1CAT-B (D2)ECSChilled water piping workIn-Progess05-10-2212-10-22
37
2CAT-B (D2)ECSPressure test and PU insulationPending07-10-2225-10-22after CHWP installation
38
3CAT-B (D2)ECSSecondary Drain panPendingSecondary drain pan08-10-2226-10-22
39
4CAT-B (D2)ECSCDP workPending10-10-2230-10-22after CHWP installation
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
80
81
82
83
84
85
86
87
88
89
90
91
92
93
94
95
96
97
98
99
100