FDP Form 7 - 20% Development Fund Utilization
3
4
UTILIZATION OF THE 20% OF THE NATIONAL TAX ALLOTMENT
5
6
REGION:
REGION V - BICOL REGION
CALENDAR YEAR:2023
7
PROVINCE:CAMARINES SURQUARTER:2
8
CITY/MUNICIPALITY:BUHI
9
10
Program or ProjectLocationTotal CostDate StartedTarget Completion DateProject StatusNo. of Extensions, if anyRemarks
11
% of CompletionTotal Cost Incurred to Date
12
SOCIAL DEVELOPMENT
13
2016 & 2017 Fund:
14
Improvement of Pamuntugan ParkSan Buenaventura, Buhi, Camarines Sur 1,384,284.55 01-Dec-2227-Jan-23100% 1,383,778.10 -100% Completed
15
16
17
18
2017 & 2018 Fund:
19
Enhancement of Local Eco-Tourism Development ProjectMagindara, Salvacion, Buhi, Camarines Sur 5,500,000.00 17-Mar-2205-Jan-23100% 5,497,000.00 -100% Completed
20
21
22
23
2018 Fund:
24
Site Development of Rural Health Unit Building (Phase II)Infront of Office on Agricultural Services (OAS), San Buena, Buhi, Camarines Sur 1,000,000.00 13-Jan-20-70% 694,487.51 -Suspended due to lot boundary negotiation; The remaining work is 18.93 LM. Concrete Fence & Steel.
25
26
27
28
29
30
2019 Fund:
31
Repair / Rehab. Of Water SystemTambo - Burocbusoc, Buhi, Camarines Sur 828,082.00 --- 563,826.00 -Suspended
32
33
34
Construction of Public ToiletPublic Terminal, San Buenaventura, Buhi, Camarines Sur 1,056,660.00 20-Mar-2330-Jun-23100% 770,946.00 -100% Completed
35
36
37
38
Page 1 of 4 Pages
39
FDP Form 7 - 20% Development Fund Utilization
40
41
UTILIZATION OF THE 20% OF THE NATIONAL TAX ALLOTMENT
42
43
REGION:
REGION V - BICOL REGION
CALENDAR YEAR:2023
44
PROVINCE:CAMARINES SURQUARTER:2
45
CITY/MUNICIPALITY:BUHI
46
47
Program or ProjectLocationDate StartedTarget Completion DateProject StatusNo. of Extensions, if anyRemarks
48
% of CompletionTotal Cost Incurred to Date
49
Construction of Public ToiletInfront of Rizal Park, San Buenaventura, Buhi, Camarines Sur 765,530.00 20-Mar-2323-Jun-23100% 541,213.80 -100% Completed
50
51
52
53
54
2020 Fund:
55
Installation of Level 2 Potable Water Supply SystemTambo - Burocbusoc, Buhi, Camarines Sur 150,000.00 --- 114,680.00 - Suspended
56
57
58
59
Repair / Rehab. of Igbac Water SystemIgbac, Buhi, Camarines Sur 900,000.00 08-Mar-22-- 798,643.60 - Suspended
60
61
62
63
2022 Fund:
64
Construction of Multi - Purpose Technical Building (Phase II)Old Municipio Building, Sta. Elena, Buhi, Camarines Sur 3,000,000.00 --- 449,638.76 -On-going
65
66
67
68
Rehabilitation of Damaged Roofing and Roof FramingBuhi Public Market, Sta. Elena, Buhi, Camarines Sur 2,000,000.00 --- 299,807.85 -On-going
69
70
71
72
2023 Fund:
73
Installation of Streetlights Along Provincial RoadSalvacion to Burocbusoc, Buhi, Camarines Sur 5,000,000.00 --- 2,113,163.52 -On-going
74
75
76
Page 2 of 4 Pages
77
FDP Form 7 - 20% Development Fund Utilization
78
79
UTILIZATION OF THE 20% OF THE NATIONAL TAX ALLOTMENT
80
81
REGION:
REGION V - BICOL REGION
CALENDAR YEAR:2023
82
PROVINCE:CAMARINES SURQUARTER:2
83
CITY/MUNICIPALITY:BUHI
84
85
Program or ProjectLocationDate StartedTarget Completion DateProject StatusNo. of Extensions, if anyRemarks
86
% of CompletionTotal Cost Incurred to Date
87
Rehabilitation of Evacuation CenterSan Buenaventura, Buhi, Camarines Sur 2,000,000.00 --- - -On-going
88
89
90
91
ECONOMIC DEVELOPMENT
92
2022 Fund:
93
Reblocking of San Isidro (Portion of Crossing) Farm to Market RoadSan Isidro, Buhi, Camarines Sur 1,000,000.00 05-Oct-2224-Jan-23100% 999,359.50 -100% Completed
94
95
96
Concreting of San Vicente (Sitio Lantad) Farm to Market RoadSitio Lantad, San Vicente, Buhi, Camarines Sur 1,000,000.00 24-Nov-2203-Feb-23100% 999,359.50 -100% Completed
97
98
99
Concreting of Sagrada (Tawagan) Farm to Market RoadSagrada, Buhi, Camarines Sur 1,000,000.00 --- 149,903.93 -On-going
100