Water Supply Network Activities PID Weekly Work Plan
 Share
The version of the browser you are using is no longer supported. Please upgrade to a supported browser.Dismiss

View only
 
 
ABCDEFGHIJKLMN
1
Project Implementation Directorate/KUKL
2
Kathmandu Valley Water Supply Improvement Project
3
Anamnagar, Kathmandu
4
Weekly Program
5
From 2076/10/05 to 2076/10/11 (Jan 19-Jan 25)
6
S.NContract NoWorkunitTargeted Quantity of WorkLocationRemark
7
SundayMondayTuesdayWed.dayThursdayFridaySaturdayTotal
8
1Bulk Distribution System(BDS ) 1 and SRTLaying of 1200mm Hume pipe worksm101020Basbari
9
Valve chamber%1515151560Basbari
10
Piling works continuedNos2226Bansbari
11
2Bulk Distribution System(BDS) 2 and SRTBoundary wall at Khumaltar SRT continuedm555520Khumaltar
12
Repairing works in Pipe lineNos112Koteswor and Tinkune
13
Construction of Guard and pump house continued%22228Panipokhari
14
3Bulk Distribution System(BDS ) 3 and SRTSite Development works at SRT Balaju continued%3333315Balaju SRT
15
4Bulk Distribution System(BDS ) 4 and SRTEarth work excavation in foundation of SRTcu.m101010101050Katunje
16
Valve Chamber construction continued%5050Tigeni50 percent of construction works
17
Pressure test continuedm300300600Kirtipur and Ghalate
18
5Distribution Network Improvement (DNI) 1Panipokhari Leakage RepairNos112Panipokhari, Maharajgung
19
110mm pipe laying worksm2525252520120Teku and lagan
20
75mm Pipelaying worksm20202060Jamal
21
Air valve chamber constructionNos112Panipokhari and Narahiti Durbar
22
Valve chamber constructionNos11Mahalaxmisthan, Ringroad
23
Interconnection of pipe linesNos11Mahalaxmisthan, Ringroad
24
6Distribution Network Improvement (DNI) 2Construction of Valve chamber (Butterfly)%555555535Gwarkhu
25
Short Run Test of pipe linem500400900UN park and Pulchok
26
Household meter connectionNos22222212Anamnagar
27
Flushingm2000200020002000Khumaltar to GwarkhuThree days in Same section
28
7Distribution Network Improvement (DNI) 3Short Run Test of pipe line continuedm100100100100400Khusibu Road
29
8Distribution Network Improvement (DNI) 4 (7A)HDPE Pipe (75mm to 110mm) laying workm404080Kuleswor
30
m303030304040200Sanepa, Dhobighat
31
m404080Ombahal, Patan
32
Short run pressure test in Pipe linesm20025080150680Khusibu, Sanepa, Chune Bhairab, Balkumai
33
Road Reinstatementm508080808080450Khusibu Rope way Sadak, Sanepa, Madan nagarSub base/Base course
34
Valve chamber construction 4 Nos continued%1055525Sanepa,Khusibu Nayabzar,Likmarg Kalanki,Kuleshwor awas area
35
Flat stone reinstatementm2020202080Chaysal
36
9Integration and DisintregationPressure test in pipe linem240240240SunakhothiSame section
37
Distribution networks KUKL/DNI/9A, KapanEarth work Excavation in foundation for OHT continuedcu.m1010101010101070Kapan Overhead Tank
38
11Municipal Road ReinstatementSurya bikram Margm5050Old BanesworBase Course
39
Shree Binayak Margm100100100300BanesworBase Course
40
Kusum Margm100160260BanesworBase Course
41
Manidol Magm100100100100100500ManidolBase course
42
* SRT: Service Reservoir Tank