A | B | C | D | E | F | |
---|---|---|---|---|---|---|
1 | Park/Facility | Project | Funding Source | Project Amount | Current Status | Notes |
2 | Brooks Park | Curbing/Edging | CDBG | Soliciting quotes | A public meeting date & time are being considered and will be announced. | |
3 | City Wide Low-to-Moderate Income Areas | Tree Stump Removal/Tree Planting | CDBG | $530,00 | Underway | This work is continuing. The first phase of $280K is complete; the second phase of $250K of stump removal and tree planting is underway, fall 2022 |
4 | Thomas Brooks Park | Pomp's Wall Restoration | CPA | $300,000 | Restructuring Project Phasing | Dead trees and invasive species marked for removal. The project has come to Procurement; the office has restructured the project into three subprojects. The first subproject to go out to bid will be an archeological dig. |
5 | Capen Park | Basketball Court Resurfacing | To be determined | $25,000 | Exploring funding options | Not eligible for CPA funds, reviewing other funding sources |
6 | Capen Park | Renovation of Water Feature | CPA; PDS budget | $81,900 | Funding Secured | Awarded CPA funds, reviewing proposal from landscape architect consultant. Will solicit quotes for the construction work during spring, with intent to complete work summer/fall 2023 |
7 | Capen Park, Cummings Park, Tufts Park | Sandboxes and resurfacing | CPA | Underway | Woodchip resurfacing complete. Remaining work is to install sandboxes. | |
8 | Carr Park | Implementing Carr Park Vision Plan (Phase 1) | Land & Water Conservation Fund; ARPA; Potentially CPA and other | $2.5M | Phase 1 funded & in design/permitting | The City has seccured a Federal Land & Water Grant for $1M and has approved $1.2M in ARPA funds; design includes 4 pickleball courts, funded with CPA. Working on permitting and furthering construction documents. Intend to start construction in late June 2023. |
9 | Carr Park | Implementing Carr Park Vision Plan (Future phases) | $5M | Phase 2 has tenatitve funding | Securing funding for Phase 2 work, which includes the playgrounds and basketball courts | |
10 | Clippership Connector | Clippership Connector | DCR | Underway | DCR expects to begin construction in FY 2023. They are working on a legal easement before project can go out to bid. | |
11 | Condon Shell | Restrooms | Underway | The City, Farmers Market, and Paddle Boston split costs for seasonal portapotties from April - October 2022. It is intended that the same strategy be done for the upcoming 2023 season. | ||
12 | Dugger Park | Park Access (Guardrail and pathway to West Medford Community Center) | ARPA (state earmark); Economic Bond Bill earmark | $350,000 | In conversation with DCR | City, community, and state representatives have met repeatedly with DCR on site and have confirmed State interest in completing this work: installation of a pathway from WMCC to Mystic River Road, crosswalk, and removal of part of the guardrail for park access. DCR to set up project group meeting in the new year with DPW and Parks staff. |
13 | Gillis Park | Gillis Park Accessibility Renovation | CDBG; PARC; ARPA; possible CPA | $1.2M | Final Design | Contracted for bid documents; funding secured for construction summer 2023 |
14 | Hickey Park | Basketball and Tennis Courts Reconstruction | CPA; ARPA | $187,000 | Securing remaining funding | Awarded CPA funds. Bids came in higher than allocated funds, working to secure remaining funding. Expected to be completed in October 2023. |
15 | Hickey Park | Canopy seating area | CPA, other | $5,000 | Underway | Canopy installed 2020, picnic table and concrete pad pending. Working to install concrete pad. |
16 | Hormel Stadium | Street Hockey Reconstruction | CPA | $238,000 | Funding secured | Awarded CPA funds. Project went out to bid but did not receive bids and must be put back out to bid. |
17 | Hormel Stadium Facility and Riverbend Park | Riverbend Park Labyrinth | CPA | $214,800 | Substantially complete fall 2022; | Substantially complete, signage and poetry installations being completed winter 2022-2023 |
18 | LoConte Ice Rink | ADA Improvements (bathrooms) | CDBG/To Be Determined | Developing contract with DCR | Drafting budget for skate guard; funding available for ADA renovations | |
19 | Logan Park | Nature Play Area Improvements | CDBG | $153,000 | Preparing bid documents | Pathways paving was completed in July 2022 and grass seeded in September. Secured Medford Arts Council grant for funding to convert tree needing to be removed into a sculpture. Conceptual design is finalized, working to advance construction documents. |
20 | MacDonald Park | Park Improvements: New Playground; Labyrinth; Butterfly Garden; Complete Pathway | DCR | Anticipated to be funded in FY2022 | The final design and permitting are still being worked on (Chapter 91 license in particular). Anticipate work to be finished in summer 2023 | |
21 | Memorial Park | Concession Stand Renovation | CPA | $15,000 | Funding secured | Awarded CPA funds, contract was finalized. Previous stand removed. Early Spring anticipated completion. |
22 | Memorial Park | Baseball Dugouts | DCR | Contracted and funded | DCR is working on putting in ramps to the new dugouts. DCR and City are in conversation about an agreement between the State and the City. | |
23 | Morrison Park | Morrison Park Tot Lot | CDBG | $407,140 | Contracted; construction spring 2023 | Addition of improvements geared toward pre-school age kids. ADA re-surfacing of the existing play space is included in the scope/work. Adding sandbox, toddler play elements, safety improvements, visit https://www.linktr.ee/MorrisonPark for more information. |
24 | Park Trees | Tree planting | CPA | $84,000 | Underway | Completed: Morrison- 23 new trees; Playstead- 23 new trees; Hickey- 12; Barry- 16; Honor Roll Park- 3 new trees, LoConte/Hormel- 5 new trees. This fall new trees were installed at Dugger, Playstead, Hormel/LoConte. Trees to be installed at Wrights Pond and possibly Capen Park in Spring 2023 (the next seasonably appropriate time for planting). |
25 | Route 28 Underpass | Route 28 Underpass | Massachusetts Gaming Commission; MassDOT | Design | The State will manage and pay for construction of project. A coalition of representatives from Medford, MassDOT, DCR, and Nitsch are managing the progress. It is anticipated this will be bid out for construction in winter 2024, for spring 2025 construction. | |
26 | Riverside Plaza | Shading and seating | Linkage | Reviewing scope | Working with landscape architect firm on developing a conceptual design to incorporate shade and seating options at the plaza. There is interest in exploring more permanent shading options that are safe during wind, preferably permanent, functional, and look nice with the area. Cost estimates came in high, reviewing scope. | |
27 | Tufts Pool | Replace Pool Deck | ARPA and CPA | $610,000 | Underway | Deck work is complete. Piping for water mushroom is complete and the remaining mushroom work will be finished in the Spring 2023. |
28 | Water Mushroom at Wading Pool | |||||
29 | Tufts Pool | Heating and Weatherization | Linkage; Other | $80,000 | On hold | Need to consider other funding sources. Not eligible for Green Communities funds. |
30 | Wellington Greenway | Wellington Greenway Phase 4 | Gaming Commission | $1,200,000+ | Needs additional funding; Fully designed | Gathering construction funding. On hold until funding secured |
31 | Wright's Pond | Water Aeration System | CPA | Funding secured | Consulting with contractor; may shift to using Earmark funds to free up CPA $ for other projects | |
32 | New Project Proposals | |||||
33 | City-wide Athletic Needs Assessment | Considering the hire of a consultant for a system wide needs assessment | Paused | |||
34 | Covid Memorial Grove Design | To be determined | $28,000 | Secured CPA funding | Awarded CPA funding. | |
35 | Dugger Park | Tennis/Lacrosse Backboard; Commemorative Signage | $8,000 | Secured CPA funding | Awarded CPA funding. | |
36 | Dog Off Leash Hours/Satellite Parks | Off-leash Dog Hours Public Input Gathering | n/a | Collecting community input | Closed community survey to collect information from the public on options for a pilot for off-leash hours or satellite dog parks on 12/15/22. Next step is to discuss findings with the public, community groups, and city staff. | |
37 | Gillis Park | Picnic and outdoor fitness areas | $97,000 | Secured CPA funding | This work will be included in the full accessibility renovation work, which has an anticipated construction start date in July 2023 | |
38 | LoConte Ice Rink | Rink Improvements | New proposal/In discussion | Discussing funding options (not CPA eligible). | ||
39 | Tufts Park | Basketball Court Resurfacing | $300,000 | Applying for funds | Applied for CPA funds | |
40 | Wright's Pond | Additional Mural | Early Discussion | Early Discussion | ||
41 | Wright's Pond | Additional updates | $350,00 | State Earmark | Will solicit community input via survey and/or public meeting in the spring to understand public's interest in additional upgrades to Wright's Pond Facility; considering lighting, electrical upgrades, staffing for events off-season | |
42 | ||||||
43 | ||||||
44 | ||||||
45 | ||||||
46 | ||||||
47 | ||||||
48 | ||||||
49 | ||||||
50 | ||||||
51 | ||||||
52 | ||||||
53 | ||||||
54 | ||||||
55 | ||||||
56 | ||||||
57 | ||||||
58 | ||||||
59 | ||||||
60 | ||||||
61 | ||||||
62 | ||||||
63 | ||||||
64 | ||||||
65 | ||||||
66 | ||||||
67 | ||||||
68 | ||||||
69 | ||||||
70 | ||||||
71 | ||||||
72 | ||||||
73 | ||||||
74 | ||||||
75 | ||||||
76 | ||||||
77 | ||||||
78 | ||||||
79 | ||||||
80 | ||||||
81 | ||||||
82 | ||||||
83 | ||||||
84 | ||||||
85 | ||||||
86 | ||||||
87 | ||||||
88 | ||||||
89 | ||||||
90 | ||||||
91 | ||||||
92 | ||||||
93 | ||||||
94 | ||||||
95 | ||||||
96 | ||||||
97 | ||||||
98 | ||||||
99 | ||||||
100 |