ABCDEFGHIJKLMNOPQRSTUVWXYZ
1
MZ
2
3
ReferenceCalculationOutput
4
5
6
Catchment Area57.8ha
7
8
Design Protection Level
9
Design protection level5yr ARI
10
Checking100yr ARI
11
12
13
Inflow Hydrographs
14
Chapter 2The design discharges estimation adopted using Rational Hydrograph Method
15
16
Equation 2.4Chapter 2The computed average runoff coefficient0.65
17
18
Chapter 2The time of concentration for the catchment at the outlet point, tc48min
19
20
The hydrographs for the longer duration than the time of concentration are also considered because for the sizing of the pumps and storage the total volume of runoff is also an important design parameter to be considered
21
22
Chapter 2The rainfall intensity adopted is from the Revised Hydrological Procedure no.1 (2010) for Station 3015001 (Puchong Drop, K Lumpur)
23
24
The computed peak discharges and inflow hydrograph using Rational Hydrograph MethodTable 19.B1
25
26
27
Estimate Storage Volume and Stage-Storage Relationship
28
Total available storage from elevation 16.5 mRL to 19.5mRL (provide 0.5 m freeboard with platform level at 20.0 mRL) is about. Figure 19.B2
29
Required storage, Vs2832m3
30
31
32
The Stage-Storage for the pump sump storage and channel storageTable 19.B2
33
Figure 19.B3
34
35
36
37
Estimate Pumping Rate and Number of Pumps
38
Section 2.3.2Runoff volume for 48 min rainstorm, based on Figure 19.B4Figure 19.B4
39
Vt (1/2 x 96 min x 9.08 m3/s)26163.74992m3
40
41
Qp (Vt/48 min x 60)9.08463539m3/s
42
43
Equation 19.A1Delta Q2.98885008
44
45
Estimated required pumping rate (Qp - DeltaQ)6.09578531m3/s
46
Figure 19.B4
47
From this analysis, provides3 x 2 m3/s submersible axial pumps
48
49
50
Estimate the Total Dynamic Head
51
Assuming that the lowest and highest levels the pumps need to pump are 16.5 mRL and 19.5 mRL respectively and the weir level need to pump over is 21.5 mRL as given in Figure 19.B3, hence the maximum and minimum static heads are as follows:
52
Higher level that needs to be pumped21.5m
53
Highest level of storage19.5m
54
Lowest level of storage16.5m
55
Hs (max) = 21.5 - 16.55m
56
Hs (min) = 21.5 - 19.52m
57
58
It is assumed that the diameter of the column pipe, D is 1 m and for 2 m3/s discharge the velocity head is:
59
Assumed D1m
60
Assumed Q2m3/s
61
Velocity (v) = Q/A2.546479089m/s
62
hv = v^2/2g0.3305074288m
63
64
The friction head is approximated using the Hazen-William equation. It is assumed that the column pipe is 4 m length and for steel pipe, the friction factor C is 100:
65
Assumed length of column pipe4m
66
Steel friction factor, C100
67
hf = 6.83.v^1.85.L/(C^1.85.D^1.165)0.03072344466m
68
69
With all the above, the maximum and minimum Total Dynamic Head can be computed as follows:
70
TDH (max) = 5m + 0.33m + 0.03m5.361230873m
71
TDH (min) = 2m + 0.33m + 0.03m2.361230873m
72
73
74
Selection of Pump Performance Curve
75
With the pumping rate and TDH requirements, the pump performance curve can be selected and the pump chosen that suits the requirementsFigure 19.B5
76
77
Pump Start - Stop Levels and Stage - Pump Discharge Relationship
78
The design start - stop levels for the pumpTable 19.B3
79
80
From the start - stop lebels of the pumps, pump performance curve and TDH, the stage - pump discharge reationship
81
1. Water level rising in the pump sump storageTable 19.B4
82
2. Water level dropping in the pump sup storageTable 19.B5
83
84
The stage-pump discharge relationship plotFigure 19.B6
85
86
87
Routing of Pump Sump Storage
88
With the Stage - Storage and Stage - Discharge Relationships, routing procedure similar to pond routing as elobarated in Chapter 2 is engaged to determine the water level in the pump sump storage. The only difference is that as mentioned earlier, there are two different Stage - Pump Discharge Relationships for the water lebel rising and dropping conditions due to te different start - stop levels of the pumps
89
90
The routing procedure to obtain the pump discharge and water level in the pump sump storage for the 5-year ARI 48 min inflow hydrograph and the maximum water level in the pump sump storage (lower than the design 19.50 mRL)Table 19.B6
91
Highest Water Level19.31m
92
Water Level at 48 min18.84m
93
94
The routing is plotted:
95
1. 5 year ARIFigure 19.B7
96
97
98
99
Discussion
100
From the pump routing analysis, the pumps provided are sufficient to meet the 5-year ARI flood protection criterion for Kampung Pasir Baru. The checks done on 100-year ARI review that the flood level is 0.7 m above the platform level of 20 mRL and the maximum inundation period is about 50 min. It can be deduced from the analysis that it is sufficient to design for the pump station to cater for 5 to 10-year ARI protection where even during 100-yar ARI rainstorm, the flooding will not be severe. With this, the capital cost can be optimised.