A | B | C | D | E | F | G | H | I | J | K | L | M | N | O | P | Q | R | S | T | U | V | W | X | Y | Z | |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1 | Province of Albay | |||||||||||||||||||||||||
2 | Municipality of Camalig | |||||||||||||||||||||||||
3 | ||||||||||||||||||||||||||
4 | REPORT ON THE UTILIZATION OF LOCAL DISASTER RISK REDUCTION AND MANAGEMENT FUND | |||||||||||||||||||||||||
5 | For the period of December 31, 2022 | |||||||||||||||||||||||||
6 | ||||||||||||||||||||||||||
7 | ||||||||||||||||||||||||||
8 | Particulars | LDRRMF | NDRRMF (OCD) | From Other LGUs | From Other Sources | Total | ||||||||||||||||||||
9 | Quick Response Fund (QRF) 30% | Mitigation Fund (70%) | ||||||||||||||||||||||||
10 | A. Sources of Funds | - | ||||||||||||||||||||||||
11 | A. 1 Current Appropriations | - | ||||||||||||||||||||||||
12 | Disaster Risk Reduction Management Program | - | ||||||||||||||||||||||||
13 | Other Purposes - Relief and Recovery QRF - MOOE | - | ||||||||||||||||||||||||
14 | 1-Procurement and distribution of prioritized basic needs, dissemnination of warning advisories and real time reports, activation of incident command system, RDANA teams, activation of evacuation system, implementation of alternative livelihood, provision of basic health services and wash materials/supplies, emergency supplies, office supplies, provide psychological first aid to disaster/emergency-effected persons | 1,400,000.00 | 1,400,000.00 | |||||||||||||||||||||||
15 | 2-Provision of welfare goods for affected families | 3,016,901.26 | 3,016,901.26 | |||||||||||||||||||||||
16 | 3-Provision of clearing of road access | 250,000.00 | 250,000.00 | |||||||||||||||||||||||
17 | Prevention and Mitigation | - | ||||||||||||||||||||||||
18 | 1-Formulation and updating of DRRMO component plans | 200,000.00 | 200,000.00 | |||||||||||||||||||||||
19 | 2-Maintenance and upgrading of early warning system | - | ||||||||||||||||||||||||
20 | MOOE | 500,000.00 | 500,000.00 | |||||||||||||||||||||||
21 | Capital Outlay | 300,000.00 | 300,000.00 | |||||||||||||||||||||||
22 | 3-Assistance to Search, Rescue and Retieval team, MDRRMC Members, MDRRMO Personnel, RDANA team and incident management team | 100,000.00 | 100,000.00 | |||||||||||||||||||||||
23 | 4-Insurance for equipment and other local government resources at risk to hazards | - | - | |||||||||||||||||||||||
24 | 5-Provision of rescue equipment and supplies for rescue and emergency management | - | ||||||||||||||||||||||||
25 | MOOE | 400,000.00 | 400,000.00 | |||||||||||||||||||||||
26 | Capital Outlay | 300,000.00 | 300,000.00 | |||||||||||||||||||||||
27 | 6-Conduct of typoon mitigation activities | 300,000.00 | 300,000.00 | |||||||||||||||||||||||
28 | 7-Conduct of Pre-Disaster Risk Assessment (PDRA) at all levels for preparedness for reponse | 150,000.00 | 150,000.00 | |||||||||||||||||||||||
29 | Preparedness | |||||||||||||||||||||||||
30 | 8-Capacity Development program for disaster preparedness and response | 700,000.00 | 700,000.00 | |||||||||||||||||||||||
31 | 9-Support to MDRRMC and Incident Management Operations | 200,000.00 | 200,000.00 | |||||||||||||||||||||||
32 | 10-Establishement of Emergency Operation Center and 24/7 Municipal Rescue and Emergency Transport Services | - | ||||||||||||||||||||||||
33 | MOOE | 1,221,000.00 | 1,221,000.00 | |||||||||||||||||||||||
34 | Capital Outlay | 100,000.00 | 100,000.00 | |||||||||||||||||||||||
35 | 11-Conduct of emergency drills and simulations | 50,000.00 | 50,000.00 | |||||||||||||||||||||||
36 | 12-Attendance and participation to various DRRM-CCAM trainings and seminars via various platforms | 50,000.00 | 50,000.00 | |||||||||||||||||||||||
37 | 13-Conduct of DRRM sectoral training and development | 250,000.00 | 250,000.00 | |||||||||||||||||||||||
38 | 14-Conduct of Information, Education and Communication (IEC) campaign and build capacity of communities on resilient building practices | 320,000.00 | 320,000.00 | |||||||||||||||||||||||
39 | 15-Stockpiling of welfare goods | 3,539,436.29 | 3,539,436.29 | |||||||||||||||||||||||
40 | Rehabilitation and Recovery | |||||||||||||||||||||||||
41 | 16-Conduct of post damage assessment and needs analysis by development and updating of a standard/harminized guidelines and procedures including sectoral assessments for easy consolidation and analysis of the communities immediate needs | 100,000.00 | 100,000.00 | |||||||||||||||||||||||
42 | 17-Rehabilitation of calamity affected sectors | 600,000.00 | 600,000.00 | |||||||||||||||||||||||
43 | 18-Support to pre-emptive health care services, management of diseases and other hazards | 800,000.00 | 800,000.00 | |||||||||||||||||||||||
44 | 19-Financial Assistance to disaster victims and assistance for the management of dead and missing persons | 300,000.00 | 300,000.00 | |||||||||||||||||||||||
45 | DRRM Activities and Compliance to laws and regulations | |||||||||||||||||||||||||
46 | 20-Support to the National Disaster Resilience Month Activities under EO- No. 29 dated June 28, 2017 | 200,000.00 | 200,000.00 | |||||||||||||||||||||||
47 | 21-Support to fire prevention and management activities | 59,000.00 | 59,000.00 | |||||||||||||||||||||||
48 | 22-Support to BDRRMC instiutionalization through conduct of capacity building on hazard, vulnerability, Exposure assessment and mapping | 150,000.00 | 150,000.00 | |||||||||||||||||||||||
49 | ||||||||||||||||||||||||||
50 | Total Current Appropriations | 4,666,901.26 | 10,889,436.29 | - | 15,556,337.55 | |||||||||||||||||||||
51 | A. 2 Continuing Appropriation - Capital Outlay | - | - | - | ||||||||||||||||||||||
52 | A. 3 Expenses obligated but not yet paid - Previous Year'MOOE | - | - | - | ||||||||||||||||||||||
53 | A. 4 Previous Years Appropriation Transferred to the Special Trust Fund | - | ||||||||||||||||||||||||
54 | 2021 Previous Year's Appropriations transferred to Special Trust Fund (details will be refleced after copy of LDRRMFIP is received) | |||||||||||||||||||||||||
55 | 1. Procurement of rescue supplies and equipment for use in the 24/7 emergency management services | 180,000.00 | 180,000.00 | |||||||||||||||||||||||
56 | 2-Procurement of rescue supplies for use in the 24/7 covid response and emergency management services | 250,000.00 | 250,000.00 | |||||||||||||||||||||||
57 | 3-Welfare goods for calamity affected sectors and population | 1,200,000.00 | 1,200,000.00 | |||||||||||||||||||||||
58 | 4-Procurement of Covid-19 testing kits | 500,000.00 | 500,000.00 | |||||||||||||||||||||||
59 | Disaster Preparedness, Prevention, Mitigation and Early Recovery Services | |||||||||||||||||||||||||
60 | 1. Procurement of multi-purpose rescue and evacuation vehicle | 1,800,000.00 | 1,800,000.00 | |||||||||||||||||||||||
61 | 2. Conduct of technical training/rescue and evacuation vehicle operations/evacuation drills conducted | 51,467.30 | 51,467.30 | |||||||||||||||||||||||
62 | Total Previous Years Appropriation Transferred to Special Trust Fund | 3,981,467.30 | 3,981,467.30 | |||||||||||||||||||||||
63 | A. 5 Transfers / Grants with separate SLs | - | ||||||||||||||||||||||||
64 | Transfers/Grants | - | - | - | ||||||||||||||||||||||
65 | Total Funds Available | 4,666,901.26 | 14,870,903.59 | - | - | - | 19,537,804.85 | |||||||||||||||||||
66 | ||||||||||||||||||||||||||
67 | B. Utilization | - | ||||||||||||||||||||||||
68 | A. 1 Current Appropriations | |||||||||||||||||||||||||
69 | 1-Procurement and distribution of prioritized basic needs, dissemnination of warning advisories and real time reports, activation of incident command system, RDANA teams, activation of evacuation system, implementation of alternative livelihood, provision of basic health services and wash materials/supplies, emergency supplies, office supplies, provide psychological first aid to disaster/emergency-effected persons | |||||||||||||||||||||||||
70 | A/P#100 | 44,550.00 | 44,550.00 | |||||||||||||||||||||||
71 | 100-2212-2989 | 171,300.00 | 171,300.00 | |||||||||||||||||||||||
72 | AP#2 | 97,136.92 | 97,136.92 | |||||||||||||||||||||||
73 | AP#101 | 44,550.00 | 44,550.00 | |||||||||||||||||||||||
74 | AP#151 | 342,000.00 | 342,000.00 | |||||||||||||||||||||||
75 | 2-Provision of welfare goods for affected families | |||||||||||||||||||||||||
76 | AP# | 3,012,464.99 | 3,012,464.99 | |||||||||||||||||||||||
77 | Prevention and Mitigation | |||||||||||||||||||||||||
78 | 1-Formulation and updating of DRRMO component plans | |||||||||||||||||||||||||
79 | AP#136 | 3,450.00 | 3,450.00 | |||||||||||||||||||||||
80 | AP#134 | 2,400.00 | 2,400.00 | |||||||||||||||||||||||
81 | AP#132 | 2,700.00 | 2,700.00 | |||||||||||||||||||||||
82 | AP#130 | 5,850.00 | 5,850.00 | |||||||||||||||||||||||
83 | AP#209 | 3,600.00 | 3,600.00 | |||||||||||||||||||||||
84 | 2-Maintenance and upgrading of early warning system | |||||||||||||||||||||||||
85 | 100-2212-2858 | 146,000.00 | 146,000.00 | |||||||||||||||||||||||
86 | 100-2212-2890 | 44,550.00 | 44,550.00 | |||||||||||||||||||||||
87 | 5-Provision of rescue equipment and supplies for rescue and emergency management | |||||||||||||||||||||||||
88 | 100-2212-2981 | 44,500.00 | 44,500.00 | |||||||||||||||||||||||
89 | AP#198 | 71,630.00 | 71,630.00 | |||||||||||||||||||||||
90 | 7-Conduct of Pre-Disaster Risk Assessment (PDRA) at all levels for preparedness for reponse | |||||||||||||||||||||||||
91 | AP#133 | 5,550.00 | 5,550.00 | |||||||||||||||||||||||
92 | AP#131 | 1,500.00 | 1,500.00 | |||||||||||||||||||||||
93 | AP#129 | 2,100.00 | 2,100.00 | |||||||||||||||||||||||
94 | AP#128 | 5,850.00 | 5,850.00 | |||||||||||||||||||||||
95 | 8-Capacity Development program for disaster preparedness and response | |||||||||||||||||||||||||
96 | 100-2212-2283 | 121,875.00 | 121,875.00 | |||||||||||||||||||||||
97 | 100-2212-2885 | 36,000.00 | 36,000.00 | |||||||||||||||||||||||
98 | 100-2212-2891 | 40,500.00 | 40,500.00 | |||||||||||||||||||||||
99 | 100-2212-2976 | 8,500.00 | 8,500.00 | |||||||||||||||||||||||
100 | AP#91 | 105,300.00 | 105,300.00 |