Measure N Bond Projects Update
2
September-2025
3
Project Name Status Estimated Start Estimated Finish Construction Completion % Project DescriptionLink to Digital Media
4
5
6
District Wide Clock Speaker/Speaker UpgradeConstruction Fall 2024Winter 202570%New public address system at all sites with digital clocks, and speakers, in classrooms, common areas and exteriors of buildings.
7
8
District Office (Redevelopment Agency Funded)Project CompletionWinter 2023COMPLETE100%Funded by Redevelopment Agency.District Office Media
9
10
Baseball Field Rennovations: Madison ES & Monroe ESProject CompletionFall 2024COMPLETE100%Rennovations to exisitng baseball fields with new infield dirt and sod outfields.
11
12
Solar Project Phase IProject CompletionFall 2023COMPLETE100%District wide solar installations and upgrades.Solar Array Locations
13
14
San Leandro High School New GymProject CompletionFall 2022COMPLETE100%Construction of a new 55,000 sqft gynamsium, 3000 seats, multiple full competition courts, dance room, weight room, locker rooms, exercise room and team rooms. San Leandro High School New Gym
15
16
Adult Education New PortablesProject CompletionSummer 2024COMPLETE100%Installation of two new portable buildings for office space. Adult Education New Portables Media
17
18
Lincoln High School New CampusProject CompletionFall 2022COMPLETE100%Construction is 100% completeLincoln High School New Campus Media
19
20
SLHS Shade Structure ProjectProject CompletionSummer 2023COMPLETE100%Construction is 100% completeSLHS Shade Structure Project Media
21
22
McKinley Elementary School Drop-Off and Entryway ImprovementsProject CompletionSummer 2023COMPLETE100%Construction is 100% completeMcKinley Drop-Off and Entryway Improvements Media
23
24
Bancroft Middle School Courtyard Improvements Project CompletionSummer 2023COMPLETE100%Construction is 100% completeBancroft Courtyard Improvements
25
26
Madison TK Portables Project CompletionMay2023COMPLETE100%Construction is 100% completeMadison TK Portables Media
27
28
Bancroft Middle School Site, Entry and Field ImprovementsProject CompletionSpring 2022COMPLETE100%Construction is 100% completeBancroft Site Improvements Project
29
30
John Muir Middle School Shade StructureProject CompletionJanuary 2023COMPLETE100%Construction is 100% completeJohn Muir Middle School Modular Shade Structure
31
32
McKinley Elementary School Campus ImprovementsProject CompletionSummer 2021COMPLETE100%Construction is 100% completeMcKinley Elementary School Interior Improvements
33
34
Garfield Elementary School Shade StructureProject CompletionSummer 2022COMPLETE100%Construction is 100% completeGarfield Elementary School Shade Structure
35
36
Madison Elementary School Shade StructureProject CompletionSummer 2022COMPLETE100%Construction is 100% completeMadison Elementary School Shade Structure
37
38
Monroe Elementary School Shade StructureProject CompletionSummer 2022COMPLETE100%Construction is 100% completeMonroe Elementary School Shade Structure
39
40
Roosevelt Elementary School Shade Structure and Basketball CourtsProject CompletionSummer 2022COMPLETE100%Construction is 100% completeRoosevelt Elementary School Shade Structure
41
42
Washington Elementary School Shade Structure and Basketball CourtsProject CompletionSummer 2022COMPLETE100%Construction is 100% completeWashington Elementary School Shade Structure
43
44
Halkin Elementary School Shade StructureProject CompletionSummer 2022COMPLETE100%Construction is 100% completeHalkin Elementary School Shade Structure
45
46
Roosevelt Elementary School Site and Entry ImprovementsProject CompletionSummer 2021COMPLETE100%Construction is 100% complete.Roosevelt Site and Entry Improvements Concepts
47
48
Bancroft Middle School Modular ClassroomsProject CompletionFebruary 2022COMPLETE100%Construction is 100% complete.Bancroft Modular Building Media
49
50
San Leandro High School Courtyard ImprovementsProject CompletionSummer 2022COMPLETE100%Construction is 100% complete.SLHS Courtyard Improvements Conceptual
51
52
McKinley Shade Structure/CourtyardProject CompletionSummer 2022COMPLETE100%Construction is 100% complete.McKinley Elementary School Shade Structure
53
54
John Muir Middle School Modular ClassroomsProject CompletionApril 2022COMPLETE100%Construction is 100% complete.John Muir Middle School Modular Classrooms
55
56
Multi-Site Marquee InstallationProject CompletionSpring 2022COMPLETE100%Construction is 100% complete.Multi-site Marquee Signage
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
80
81
82
83
84
85
86
87
88
89
90
91
92
93
94
95
96
97
98
99
100