2017 TCP Master List
New in Dec. 2017: ITS-000-T(9)--25-00
481311Counts =132733321816
2
StatusTCP ID TCP ID PINTCP ID KEYBrief Name/LocationEstimated IWZ CostsProject Est. CostPINAccounting Proj #IWZ Billing Project NumberCountyRouteConstruction ActivityLetting DateWeekly ReportsPlans AvailablePre-Con Meeting DateAnticipated StartTraffic Impacts Start DateActual Construction StartLate StartEnd DateProject Working Days / DurationProject ContactProject ADEProject InspectorTIM PlanTIM Consultant & NotesMitigation StrategyCTRE Monitoring LevelStaked DateDeploy DateIntegrated DateAPS Active DateEstimated IWZ Equipment Removal Date Notes District Meeting NotesPre-Construction Notes
3
1B161H17NE 54th Ave. Over I-35 0.5 Mile N. Of I-80 Jct.$2,500,00013770354160IM-035-4(160)87--13-77Polk35Bridge Replacement-Steel Girder11/17/15YesIP4/4/16140Jesse Tibodeau
Tony Gustafson
Got rid of TBR and Shift , no impacts , Night Time Closures
4
Active1J161J161J I-35/80 at 100th St in Des Moines$6,500$601,00011770803199NHS- 080-3(199)128--11-77
old NHS-080-3(201)128--11-77
old NHS- 080-3(198)128--11-77
Polk35/80100th Street bridge in Urbandale over I-35/80. Bridge replacement in 20161/18/2017YesIP2/15/20162/15/201611/23/2017110Jesse Tibodeau
Tony Gustafson
IWZ - Queue Detection; 2 Portable DMS, 1 to take the place of the former EB permanent side-mount DMS.Sensor2/15/20172/15/2017Bridge work started February 2016; Ramp work in 2017; Maintaining 12 ft lanes. No speed reduction. Intermittent night work and intermittent lane closures. Continues to 2017 and connects to Wrighter corner project
Currently using SSR PDMS for project info - Use Existing ITS for QD (199) letting of 12/15/2015
the traffic control will basically be identical to the NW Beaver Drive over 35/80 project (except for a different off site detour for the night time interstate closures). 100th street closing in February 2016. Previous project was let on 12/15/15 and divided into (198) and (207) which were for bridge and approaches - steel girder and RCB culvert replacement-single box (Culvert Extensions new I-80 Interchange).
5
Complete1Q
161A17Bear Creek 3.3 mi S of Co Rd E18 $87,246.18$433,0000M850351505MBIN-035-1(505)120--0M-85Story35Deck Joint Repair2/21/2017Yes3/31/20174/9/174/9/174/16/20175/12/1742Mark Dunn
Tony Gustafson
Clayton BurkeYesIWZ - Queue Detection, CCTV MonitoringSensor3/30/173/31/174/3/174/3/2017April and may
Traffic down 1 lane in each direction
Sun night through Thursday morning
Bridge repairs
Lane reduction in both directions, work Sunday nights through Friday Morning (Thursday Incentive)
Would like two cameras at bridge (radio)m Queue Detection both NB and SB - 2 PDMS
Add Speed Feedback Trailers; 1 NB, 1 SB prior to merge point
Add another Camera at the north merge point
6
Complete1T161TI-35 in Story County$50,000$601,00003850354173done IM-NHS-035-4(173)109--03-85
(NOT IMX-35-4(173)109--02-85)
Story35DONE: grading for I-35 South of Ames
COMPLETE - 1V is next Phase
Tony Gustafson
IWZ - TIM PDMSSensorE-57 Bridge Replacement for Permanent CCTV/Sensor being torn out - replace with Temp
7
Active1U (includes 1T)171B17I-35 & US 30 Interchange In Ames $138,402.00$22,997,14413850354182IM-035-4(182)112--13-85Story35PCC Pavement - Grade and New
Bridge New-Steel Girder
Traffic Signs
Lighting
RCB Culvert Replacement - Twin Box
9/20/2016Yes4/3/175/8/174/3/2017240Jenny Hoskins
Tony Gustafson
YesIWZ - Queue Detection (Maybe?)Sensor3/30/173/31/173/31/17Traffic impacts April – night work with lane closures for shoulder strengthening
May 8th – August : Close SB to WB ramp And the Dayton off ramp
Overnight interstate and 30 full closures later in the year

Traffic control stages 1-3 year 1, stages 4-6 year 2
arrange for one speed trailer in each direction on I-35 in advance of the work areas for IM-035-4(182)112--13-85 (for SB) and IMN-035-4(190)98--0E-77 (for NB). Per JT
Detour prior to closure - maybe temp signal at US-30 EB, TIM plan being developed by Jared & Gary
8
Active 1V171C17I-35 SB over South Skunk River 2.6 Miles South of US 30$40,867.20$1,000,00002850354188
IMX-035-4(188)110--02-85
IM-NHS-035-4(208)109 --03-85
IMX-035-4(174)109--02-85
Story35Bridge Replacement-PPCB.
SB Lane closures overnight while removing E57 bridge.
1/20/2016Yes2/18/17Feb 201712/20/2017120
Tony Gustafson
IWZ - Queue Detection & CCTV Monitoring3/8/20173/20/20173/20/20173/30/17Knocking down E57 overhead bridge over 35; Paving the new SB lanes.
Overnight lane closures for shoulder strengthening
2 lanes both direction, during the day.
Lane shifts SB only 2 lane shifts for a month or so total
Camera relocated ahead of time – mid February would be the earliest the bridge would come down.
Permanent Camera to be relocated and replaced w/ Trailer
Queue Detection SB, 2 Sensors 1 PDMS
Raising Embankment - may not be able to be on bridge
8PM Lane Closures between Ames and DSM - NB Direction
9
Complete1W171D17IA 210 Over I-35 $4,62239852103036BRFN-210-3(36)--39-85
(not BRFN-065-4(140)--39-77)
Story210Bridge Deck Overlay11/15/16Yes06/01/176/5/174/3/174/3/20176/5/201710/31/201730
Tony Gustafson
IWZ - Ramp Sensor3/21/201711/01/2017Bridge deck overlay; 210 down to one lane; 210 over the interstate- will not impact the mainline (35)

Automated Temp signals will be used with TRB over the bridge.
May have some queueing onto the ramps during evening rush (add sensor to NB exit).
10
1X171E.171.6 mi N of Co Rd F22 to 3.5 mi N of IA 210 (NB / SB) $4,988,0000E770354190IMN-035-4(190)98--0E-77Polk35HMA Resurfacing1/18/2017Yes4/25/20175/1/176/5/2017120
Tony Gustafson
CTRE monitor with permanent sensorsSB mm 98 to 105.8
NB 102.5 105.8
Nighttime resurfacing; Includes all 4 ramps at IA20
arrange for one speed trailer in each direction on I-35 in advance of the work areas for IM-035-4(182)112--13-85 (for SB) and IMN-035-4(190)98--0E-77 (for NB). Per JT
Nighttime Closures
11
1Z171G17UP RR 1.1 mi N of NE I-80/35/I-235 Interchange (SB) $472,0000M770351503MBIN-035-1(503)88--0M-77Polk35Bridge Approach Repair1/18/17Yes4/20/20175/1/20174/30/20176/5/20176/15/201740Danielle Mulholland, RCE, 515-986-2851
Tony Gustafson
Mike Pagel
515-689-7490
Monitor onlyMaintaining 3 lanes but narrowing to 10'
Replacing the bridge trusses
Close the SB entrance from Corporate Woods for about a month
~2 month entire project
-2 message Boards added on Corporate Woods (EB & WB)
-Double Lane Closures from 11:00pm-5:00am
-Single Lane Closures & Lane Shifts taking place
- No import on material during daytime
-Traffic Control : Iowa Plains
12
Complete1Y171F17In Ankeny from E of Peachtree Dr to E of I-35 $24,456.60$4,012,0003H771601013NHSX-160-1(13)--3H-77Polk160PCC Pavement Widening12/20/2016Yes2/27/20183/16/20175/1/201710/01/2017120
Tony Gustafson
IWZ 3/8/173/16/173/16/173/29/1711/01/2017Widening on 160 through the ramp terminals.
13
Complete1AA171I17Delaware Ave. Over I-80/35, 0.5 Mile W. Of I-235 Near NEMM$40,759$10,482,71413770354161IM-035-4(161)87--13-77Polk35Bridge Replacement-Steel Girder8/16/16Yes6/12/179/19/2016170
Tony Gustafson
IWZ - Queue Detection6/5/2017Bridge coming down in July; Lane Shifts and Night Closures; Will be similar to 54 bridge project in 2016.
–Lane shifts for pier work and nighttime closures.
Permanent camera relocated, Queue Detection using permanent ITS
THRU Traffic on I-235, Morningstar DMS needs to be removed. IM-035-4(161)87--13-77 started last fall. The overnight interstate closures will start in mid to late June
14
Complete1AB171K17 IA 141 From IA 44 to Just N. of I-35/80$29,160$7,726,5803H771417042NHSX-141-7(42)--3H-77
NHSX-141-7(47)--3H-77
NHSX-141-7(48)--3H-77
NHSX-141-7(49)--3H-77
Polk141PCC Pavement - Grade and New RCB Culvert Extension - Single Box, Traffic Signs, Traffic Signals
10/18/16Yes04/06/20175/1/20175/15/201710/2/2017100

Danielle Mulholland, RCE, 515-986-2851

Tony Gustafson
Christy McClain, Lead Inspector, 515-250-6731
Paul Prentice, Inspector, 515-238-5429
YesJared STIM Plan and DMS for Diversion Routes5/5/20175/8/20175/9/2017Closing a lane overnight, no cross overs
Signalized so no Queue detection
No IWZ for this project
15
Active1AC171L17NW Morningstar Dr. 1.7 Miles W of IA 415$24,138.00$3,551,0000E770804056IMN-080-4(56)134--0E-77Polk80Bridge Replacement-PPCB1/18/17Yes02/23/20174/3/20174/3/201711/16/2017120Danielle Mulholland
Tony Gustafson
Sean Passick 515-250-6715IWZ - CCTV3/8/20173/20/173/30/17Maintaining 3 Lanes & Using Detours
Permanent CCTV and DMS will need to be removed (DMS removed 4/4/17)
Will replace with Temp CCTV
Check into lane shifts for PDMS and CCTV PLacementStarting work first on SB Mark Anthony : Working Manger Remove the sign to Grimes Maintenance CCTV removed before March 27
16
1AD171M17US 65/IA 330/IA 117 Intersection $7,828,0002R500654143
NHSN-065-4(143)--2R-50
Jasper65Grading
Bridge New _PPCB
12/20/16Yes4/2/20174/2/2017130
Tony Gustafson
New interchange; Looking for haul routes
North of Traffic Signals

Lane closures in both directions over RR
Primary concern in 2017 is truck haul route crossings.
Next interchange north will be where haul entrance point is/
No impacts to Intersection Conflict Warning System in 2017 - likely in 2018
17
1AE171N17141 IA 17 Interchange (WB)
141 IA 17 Interchange (EB)
34187, 34188BRFN-141-7(44)--39-77
BRFN-141-7(45)--39-77
Polk141Bridge Deck Overlay3/21/17Yes70
Tony Gustafson
no IWZDeck overlay one lane in each direction during the day.
Not a lot of traffic but it is in an areas that is a transition from rural to interstate.
18
1AF171O17I-35 from Story City to Ellsworth8850355105IHSIPX-035-5(105)125--08-85Story – Hamilton35Guardrail 7/19/2016Yes3/1/201740
Tony Gustafson
Primary condern in 2017 is truck haul route crossings.
Next interchange north will be where haul entrance poit is/
No impacts to Intersection Conflict Warning System in 2017 - likely in 2018
19
not TCP1AG171P18Co. Rd. E18 To W. Jct. Ia. 1753H640145075NHSX-014-5(75)--3H-64Marshall14PCC Pavement Widening/PCC Resurfacing
Tony Gustafson
low traffic – road will be closed for construction in 2017 or 2018.
20
Future year1AH171Q20Bridge over Des Moines River 1.6 Miles E. of IA 28 I-35/80 Des Moines River Bridge0E770353189OLD: IMN-035-3(189)83--0E-77Polk35/80Bridge Rehabilitation - Joint Repair
Tony Gustafson
IWZ - Queue Detection2020 ProjectNOT in 2017. Delayed until later redesign
21
1AI171R17I-80 Over W. 148th St S, 1 Mile E. of S-270M500801507MBIN-080-1(507)150--0M-50Jasper80Abutment Repair4/18/2017Yes5/24/201730Jeff Devries
Tony Gustafson
Monitor OnlyNight Work / Under Bridge Work. Plans just released for review 2/10/2017. The precon for MBIN-080-1(507)150--0M-50 is May 22. I think it will drop off the IWZ list, but we will see after the precon.Starting May 24th. Lane/Shoulder Closure for work on barrier rails will last a few hours. If deck work is required they will let us know then lane closures will be night time closure for a few days.
22
Complete1AJCo Rd P59 Interchange
to 0.5 mi W of Co Rd P73 (EB/WB)
$17,5613H940203172NHSX-020-3(172)--3H-94WebsterUS 20PCC Pavement - Replace3/30/174/10/201708/31/2017143
Tony Gustafson
Kay Powell 515-370-1971Speed Feedback Trailers3/21/20174/10/20173/30/179/6/2017Would like Speed Feedback trailers in each direction on US-20.  EB was paved last year and WB will be paved this year.  Contractor is Jefferson (WB Speed Feedback was moved east from staked location still within 55 mph speedzone.)
23
Complete1AKUS 30 just east of Grand Junction$44,01038370303043BRF-030-3(43)--38-37Greene30Bridge Work4/17/2017140Jenny Hoskins
Tony Gustafson
YesTIM PDMS04/10/201704/10/2017Heavy truck traffic anticipated as 85 wind turbines are being constructed in 2017.  Contractor anticipates roughly 100 trucks/day moving dirt for roads to turbines.  With US-30 closed, all of these trucks will be using the detour route.  Need approximately 5 TIM PDMS - to be staked by Jared and Gary.
24
Complete1ALHwy 141 @ 121st St.$4,26692771417054TSF-141-7(54)--92-77Polk141Data Collection9/6/201730
Tony Gustafson
06/28/2017The AADT at this location in 2015 was 15,200 w/ 6% trucks. Construction year is expected in 2018 or early 2019. Due to the growth anticipated traffic growth, we feel this location justified placing a counter for 1 month this summer. This data collection will also help understand traffic turning movements WB to NB. This movement will be impacted during construction and mitigation may be justified during peak hours (according to the DRAFT concept).I do not think we need to stake this location, as long as Street Smart can place the sensor with these requirements:
-On Iowa 141, just east of the 121st Street Intersection.
-Collecting data for all 6 lanes of Iowa 141 (WB right-turn lane, WB thru, WB thru, WB left-turn lane, EB thru, EB thru)
-Close enough to 121st Street so that westbound traffic turning north or south will be fully in their turn lanes when they pass the sensor.
-Face the Sensor perpendicular to Iowa 141 (not parallel to 121st).
-Make sure the sensor is NOT within the sight triangles for a northbound or southbound vehicle sitting behind either of the stop bars on 121st, and looking at approaching traffic on Iowa 141.
25
Active1AM17I-35 over 1st Street in Ankeny (Bridge Replace)$19,116IM-NHS-035-4(140)92—03-77
IM-NHS-035-4(193)-93—03-77
IM-NHS-035-4(194)94—03-77
IM-NHS-035-4(218)93—03-77
NHS-035-4(221)93—11-77

Polk35Bridge Replacement7/18/2017Yes8/11/178/20/2017224Ben Hucker
Tony Gustafson
08/21/201708/21/2017
26
Stakes
27
Complete2E162E
Williston Ave/W 18th St to N of W 6th St (NB/SB)$42,018.752R072187232NHSN-218-7(232)--2R-07Black Hawk218Resurfacing11/15/2016Yes4/1/20174/1/201711/8/201795Ron LoecherDavid LittleIWZ3/6/20173/9/20173/10/20173/10/2017night work some day time work but they will maintain two lanes of traffic for this. Permanent devices should be adequate. duration: all summer. Daytime bridge work – start early in project month and a half of work – only replacing the S approach on NB bridge. 63 project is close so there may be additional issues from this project. 218 NB off ramp to NB 63 is biggest concern for back ups
bridge approach closures are 24 hours a day
closure at Jefferson Street on 63 NB first city street intersection past 218
28
2F17Ia. 3 At Jct. I‐350E350356124IMN‐035‐6(124)165‐‐0E‐35Franklin 35Bridge Deck Overlay10/18/2016Yes4/1/201790Roy GelhausDavid Little
29
Complete2G17IA 9 Trout Creek bridge in Decorah, 2 mi. E of US 52$84,46939960098037BRFN‐009‐8(37)‐‐39‐96Winneshiek 9Bridge Deck Overlay12/20/2016Yes3/1/20173/1/20174/1/201710/5/2017218Ron LoecherDavid LittleSignal Timing, IWZ3/8/20173/10/20173/15/20173/15/201710/3/2017Decorah should be working on the signal timing.
CCTV can be deployed as well in this area to keep an eye on it- so we can help define the problem and then find a solution. Or send a traffic tech
out to do daily counts. Lane closures will be in place for most of the summer. DMS could help warn people of backups.  Queue detection and cameras.  Use late merge if queues are long enough?
Driveway in this area will become a right in right out at Medical clinic on the north will also be an issue. Temp lane separator to keep people from making left turns.
East Edge of Decara - Signalized intersection east of bridge has lots of left-turn movement.
Lane reductions at intersection - Issues anticipated
Decora working on signal timing (SRF can assist)
Possible deployment of CCTV to monitor, DMS to Warn
Queue detection possibility? Late merge possibility?
Temporary Lane Separator to prevent left turns
Work will start on stage 2 instead of stage 1. Stage 2 switches traffic to a two-lane two-way traffic pattern in the westbound lanes.
30
Active2H17Hwy 63 in Waterloo just north of 218$10,152.003H070636078NHXS-063-6(78)—3H-07 &(075)Black Hawk63Reconstructing one-way pairs; SB closed in 2017; NB closed in 2018.12/20/20163/13/20172/21/20174/3/201711/21/17150Ron LoecherDavid LittleIWZ3/6/20173/9/20173/10/20173/10/20172017 - Closing SB lanes - Traffic H2H in NB Lanes
2018 - Closing NB lanes - Traffic H2H in SB Lanes
North of (78) completely closed & detoured - backups expected
Add presets to WLTV26 and 218 @ 1st St to Zoom in on Franklin
Add permanent camera on franklin
Jefferson Street to Franklin Street H2H plus ramp down to 1 lane
Next year could be full detour of US63
31
2I171 mi N of IA 9 to the MN State Line0E980358050IMN‐035‐8(50)205‐‐0E‐98Worth35NB & SB Microsurfacing; all lanes, both directions7/1/2016Yes5/1/20175/1/201775Roy GelhausDavid LittleCTRE INRIX monitoringINRIXShoulders done in 2016, Microsurfacing in 2017
No Mainline work last year
Daytime Lane Closures - Up to 8 miles/day
No Weekend Work 30-60 Days
32
2J17I‐35 From Hamilton Co. Line N. to Minnesota State Line0E990356122MN‐035‐6(122)150‐‐0E‐99Wright 35PCC Patching5/1/2017Mid June 20176/15/2017Roy GelhausDavid LittleMM 186 to 205, 205 to State Line
County Road over 35, not on mainline
33
Completed2K17Microsurfacing 3.0 mi S of B43 to 1.0 mi N of Iowa 9$7,487
16-17-035-010
0E170357071IMN-035-7(71)186--0E-17
(not county 99)
Cerro Gordo35Future Data Collection7/18/20174/1/20174/1/201770Roy GelhausDavid LittleData Collection3/8/20173/14/20173/15/2017n/aWould like more data between clear lake and north of hwy 3. Have data from month of September, but would like to have data for April through November.
Could possibly start this fall
34
2L17I-35 Resurfacing, 0.7 mi S of B20 north to 1.1 mi S of Iowa 913-17-035-01025170357073ITS-035-7(73)197--25-17
IMX-035-7(70)197--02-17
Cerro Gordo35Originally "Resurfacing from mm 197- 202 (3 mi N of B20)"7/18/2017Fall 20178/24/17Roy GelhausDavid LittleData CollectionI-35 Resurfacing 2018 - I-35 Reconstruction from MM 197-202 (3 miles north of B-20) letting September or October. Night work only unless there is bridge work involved in this project. ATR just north of hwy 9. No Additional Sensors Requested.
35
2MI-380 in Waterloo at Cedar River Bridge0M073802509MBIN-380-2(509)71--0M-07Black Hawk380Rip Rap along Cedar River accessing via I-3804/18/20176/1/2017Ron LoecherDavid LittleI-380 in Waterloo Cedar River bridge on east side of bridge. Night Work. Nb and SB traffic.
Possibility for Truck Entering System?
36
2NSB US 218 in Waterloo, from US 63, N to Green Hill Rd (from last year)2R072187234NHSN-218-7(234)--2R-07Black Hawk218Joint Patching7/1/20163/1/20179/1/2017Ron LoecherDavid LittleGreenhill road south to US 63 - Night Work SB only down to one lane of traffic
37
2ONB US 218 in Waterloo from US63 to Green Hill Rd2R072187236NHSN-218-7(236)--2R-07Black Hawk218Joint PatchingAug or Nov 20172018Ron LoecherDavid LittleOpposite above project - 2018
38
Complete2PIA-58 and Viking Road Grade Separation - IA-58 Under Viking Rd$3,9153H07581092NHSX-58-1(92)--3H-07Black Hawk58Interchange Construction (Grade Separation)12/201720182018Ron LoecherDavid Little3/6/20173/9/20173/10/20173/10/2017District to check with City on availability of traffic data from signal system.  If not, deploy sensors for data collection - 2018 Project
Collect data till January 1st 2018.
IA-58 Will be sunk under viking rd
Check with City to see if signals track counts
39
40
Active3B163B163B I-29 Sioux City$48,43803970297049IM-NHS-029-7(49)149--03-97Woodbury29Unknown Pavement - Grade and Replace12/15/20153/21/20163/21/2016Mid-March 3rd Monday in March impacting traffic2 yr projects100Dean Herbst
Shane Tymkowicz
Rollin.Nemitz@dot.iowa.gov
Office (712) 239-1367
Cell (712) 539-1295
Tri-StateQueue Detection3/16/20163/21/20163/22/20163/23/20163 year project, 3rd year, continue doing queue detection this year.  South end of the project is now further to
the north, had better success this year than the previous year.

Work will start in March or as soon as weather allows they will begin. 
Traffic configuration they have will be in place until July 1st,
NB exit 147B at Dace to close around March 20, 2017. Next changes will be when Stage 3A & 3B start in July 2017: NB exit at Wesley will be closed; detour will exit earlier, but some traffic will miss detour and proceed to Hamilton. So. Dakota will be working on I-29 bridge decks across the Sioux River at the Iowa border. SB I-29 has lane closures now but will not change over the course of the summer.
41
Complete3E17Dry Creek 3.4 mi N of Co Rd C60 (SBL)$29,75439750752087BRFN‐075‐2(87)‐‐39‐75Plymouth 75Bridge Deck Overlay4/x/2017Yes7/1/201710/31/201760
Shane Tymkowicz
Camera & SB Queue Detection7/3/201717000 ADT one lane at a time historically get queues. Mostly peak hours. Will only be 3 month long, no construction start date at this time. Mid- april would be the early start late start august. SB only, divided median in this area.
42
3F17From E. Of Moville E to Minnesota Ave. (EBL) 3H970201118NHSX-020-1(118)--3H-97Woodbury20Grading12/20/2016Yes20
Shane Tymkowicz
Monitor OnlyInrix4/10/2017Do not expect that they will need any IWZ devices in this area, they have been detouring 20 for the last few years and have had no issues. Monitor Only.
43
Complete 3G17Merrill and Le Mars and Sioux city$95,1352R750752092NHSN-075-2(92)—2R-75Plymouth75PCC Pavement - grade and replace2/21/2017Yes04/19/201710/31/2017170Dean Herbst
Shane Tymkowicz
Rollin.Nemitz@dot.iowa.gov
Office (712) 239-1367
Cell (712) 539-1295
Queue Detection4/10/20174/17/20174/19/2017Feb letting, peak hours will experience issues. Will have cross overs, multiyear project. Merrill to co rd C38.wanted to give you a heads up that the project is under a Value Engineering proposal and the southbound lane will be constructed first. Originally the northbound lane was staged to be completed first, but that has been reversed. Southbound lane first. Thanks
44
Complete 3H17US 75 from the Woodbury County Line to South of West Grover St in Hinton $7,533NHSX-75-2(95)--3H-75 NB 2018
NHSX-75-2(96)--3H-75 SB 2020
Plymouth75Future Data Collection
PCC Pavement Widening/PCC Resurfacing
5/30/20179/22/2017100
Shane Tymkowicz
9/25/2017(95) & (96) Plymouth county NB & SB data collection
45
Active3II-29 SB exit at Singing Hills in Sioux City$23,868OE430295235IMN-029-5(235)72-OE-43Woodbury29SB Exit Ramp widening and Pork plant opening.7/1/2017Nonone6/15/176/15/20179/15/1790Roxanne Seward
Shane Tymkowicz
Ramp Queue Detection09/15/2017Tony Lazarowicz called Tim S on 6/7/17 and asked for SB ramp queue detection to be installed as soon as convenient. The ramp is expecting increased traffic when a new port plant opens in July or August, and the City also will be letting a project in July to widen the SB ramp to lengthen the SB right-turn lane. The ramp queue detection system and count sensor will be helpful before, during and after the widening and plant opening.Tony will provide a project number; Roxanne Seward, Todd Cogdill and Dean Herbst will stake the three locations.Sensor on Exit Ramp; PDMS on SB I-29, after exits to US 20; PDMS on ramp from EB US 20 to SB I-29.
46
Complete 3JUS 60 North of Ashton, Osceola County$10,00039720604091BRFN-60-4(91)--39-72Osceola60SB brige is being reconstructed, one half at a time. initial stage has single lane SB traffic shifted right--has resulted in several crashes. Cameras should only be needed for first stage.2017Nopast08/25/201711/3/1730Roxanne Seward
Shane Tymkowicz
Martin JennessTwo cameras to observe crash causesnone8/25/20178/25/20178/25/201711/6/20178/24/17 Roxanne told Tim that they have had SB trucks run off the road and aren't sure why.
47
48
Active4.1154.1.154.1 Council Bluffs Interstate$186,176FY16-0E780293155/ FY17-0E780293158IM-035-2(354)56--13-91Pottawattamie29/80New Interchange9/16/2014Contact HDR4/6/175/1/17Ongoing through Winter9/4/2017130Tara KramerWes MayberryHDRQueue Detection, Truck DetectionHighVariesVariesVariesVariesProject schedule for the 28th Street Sewer project (I-29 in Council Bluffs near 25th Street interchange Exit 55) - 2017
49
4O17Basswood Rd. Over I-29, 2.6 Miles S. Of lA. 920M780294506MBIN-029-4(506)45--0M-78Pottawattamie29Bridge Painting1/18/2017Yes3/1/20173/1/20177/17/201760Wes MayberryMonitor OnlyWill maintain 2 lanes, queuing not expected other than Friday 2-6pm.
50
Complete4P17From The Co. Rd. L34(Beebeetown) Interchange E to I-80 (EBL) $82,05302786802161IMX-680-2(161)20--02-78Pottawattamie680HMA Surfacing/Cold-in-Place Recycling 2/21/2017Yes4/19/20173/1/20175/15/20175/1/20174/30/201712/1/2017120Tara KramerWes MayberryMike Adler
michael.adler@hdrinc.com
402-305-8706
should be integrated with CBIS (and improved from last summer).Queue Detection + Cameras4/19/20174/27/201705/03/201712/11/2017Did WB direction last year would have been nice to have IWZ. April/May start. Depends on how soon it warms up. All year till fall. Queue detection. De-brief on last year could be helpful (HDR will organize). Cross overs, were in place till late fall. Weekly Meeting Notes-Traffic Control : Iowa Plains
- Project will Start from Site 3 on May 1st
- Shift to Site 2 and Site 1 on Mid-May
-Site 2 will have Head-to-Head Traffic
-Site 1,3 will be Lane Closures
- Project Manager : Hussein Khalil (hussein.khalil@hdrinc.com)
51
4Q17I-80 bridge repairs over US 6/169 at DeSoto Interchange0E250803218IMN-080-3(218)110—0E-25Dallas80Bridge Repair to EB&WB bridges over US 169 that was hit in 2016.4/18/2017Yes4/19/2017Wes MayberryMonitor Only24 hour lane closures – full closure for curing. Lane closure on 169 will affect ramp traffic if we have closures below during peak times traffic could back up quite a bit.
Scheduled for April letting, going to be short term, but it will affect traffic, less than 2 weeks hopefully. Cannot be moved to weekend work. Looks like we may have had data from previous summers-
169 is a diversion route so we should make sure these are coordinated efforts.
52
Completed4R17I-80 Bridge Widening at Raccoon River$22,599IMN-080-1(413)50--0E-15Dallas80Future Data Collection, just east of DeSoto201903/1/2017100Wes MayberryData CollectionFuture Data Collection: Put sensors out for: i-80 Raccoon River Bridge widening bridges in the area, would like some, 2 sets of bridges just west of van meter interchange at 213. Raccoon River branches where they cross I-80. Looking at a 2019 letting. Project numbers are now in PCC database.We had a sensor deployed just east and west of here in the past. We need to see how long that was deployed. Add a sensor for much of the summer if needed.
53
4S17E‐W Connector, I‐29/I‐80 Local
on to WB I‐80 (Ramp
E) over I‐29 & Ramp A
I‐29/80 In Council Bluffs At N‐E Connector I‐29 to I‐80
Express Over I‐80/Ramp
03780801392IM-NHS-080-1(392)0--03-78
IM‐029‐3(82)52‐‐13‐78
IM‐029‐3(83)52‐‐13‐78
Pottawattamie 29Bridge New‐Steel Girder11/15/2016YesWes MayberryHDR Project? Queue DetectionTied projects (82), (83), Missouri River Bridge to Nebraska? Using lane rental specifically for crossovers that we expect to have to mitigate with queue detection or diversion. SSR contract issues for Missouri or Nebraska? Should be fine as long as we coordinate with the other states.
54
4T17I-80 from Pottawattamie Co. Line E. to I-350E150801413IMN-080-1(413)50--0E-15Cass80PCC Patching4/18/2017Wes MayberryMonitor OnlyPCC patching project, but we should monitor cass county (413) time restrictions closer to the city it was night work only- so we did not have too many issue last year. They did not hear of too many problems, but it was October. IF this happens in July, we might want to do something—usually okay if they have time restrictions.
55
4U17I‐80 from Missouri River E. to Cass Co. Line0E780801422IMN‐080‐1(422)0--0E‐78Pottawattamie 80PCC Patching3/21/20175/1/2017Greg MoweryWes MayberryMonitor OnlyHDR would like to be consistent with the time restrictions for those contractors. As it affects tara’s work. (165) is a similar situation. Monitor Only
56
4V17I-680 from Missouri River E. to I-80 0E786801165IMN-680-1(165)0--0E-78Pottawattamie680PCC Patching3/21/2017Yes5/1/20175/1/2017Greg MoweryWes MayberryMonitor OnlyHDR would like to be consistent with the time restrictions for those contractors. As it affects tara’s work. (165) is a similar situation. Monitor OnlyOnly 2 sensors , more data need to be calculated
57
4WResurfacing I-80 Ramps at Exits 57, 64, 70IMN-080-1(463)52--0E-15

IMN-080-1(470)57--0E-15
Cass80Resurfacing & Reconstruction of Ramps along I-806/20163/29/2017Scott NixonWes MayberryMonitor OnlyIMN-080-1(463)52—0E-15 is a mill/patch/HMA resurfacing of ramps at Co Rd M-56, and Ia 173 interchanges on
I-80.  M-56 was done fall 2016 and will finish IA 173 spring 2017.  IMN-080-1(470)57-0E-15 is a
reconstruction of ramps at 3 interchanges on I-80, those being Exit 57, Exit
64, and Exit 70.  The West ramps were done fall 2016 at exit 64 and we
will do the East ramps this year.  The plans do not allow work on all 3
simultaneously.  Once Exit 64 is done, we will close ramps at Exit 57 and Exit 70
58
Complete4X28th Street Sewer project (I-29 in
Council Bluffs near 25th Street interchange Exit 55)
$25,9080E780293198IMN-029-3(198)55--0E-7829Sewer5/1/201709/18/2017140Nick Johnson
Nick.Johnson@hdrinc.com
Wes Mayberry
Brian Higginbotham
bhigginbotham@hgmonline.com
Queue Detection04/25/20174/28/201705/04/0201the 28th Street Sewer project (I-29 in Council Bluffs near 25th Street interchange Exit
55).  The schedule is showing a May 1 start date including lane closures
(when we will want the queue detection equipment deployed).
Brian Higginbotham with HGM is the lead inspector for this job. We will need to work with him to identify preferred
locations for our IWZ equipment and to get updates on the schedule.  bhigginbotham@hgmonline.com.
Schedule
59
60
Complete5A165a165A US 34 West of Fairfield
Over Big Cedar Creek 1.5 Miles W. Of Co. Rd. V-63(EBL)
$15,98038510348156BRF-034-8(156)--38-51Jefferson34Bridge Replacement-PPCB12/15/2015Yes3/8/2016IP4/4/20163/10/2017120A. Jared Klein, D5 Traffic Ops Engineer, jared.klein@dot.iowa.gov, 641-472-1771, 319-270-3820. Lauren GiarmoMark Van DykeKent AndersonNo plan, if lane had to be closed, could go head to head on WB lanes4/8/2016HMA overlay, two down to one lane EB, on a curve,No crossovers, just single lane. The plan is to complete all 4 traffic stages this year before the snow starts (2016)
61
Complete5B165B165B I-35 in Warren County
From Clanton Creek Approx. 2 Miles S of IA 92 N through IA 92 Interchange (NBL) From Clanton Creek Approx. 2 Miles S. Of IA. 92 N. Through The IA. 92 Interchange(SBL)
Over Middle River 0.4 Mile S. Of Ia. 92 (SBL)
$188,61403910352354IM‐NHS‐035‐2(378)54‐‐03‐91 (2017)Warren35
PCC Pavement - Grade and Replace Bridge Replacement-PPCB
8/18/2015Plans (354, 379, 380)Plans (378)2/13/20173/23/2017 (Confirmed via CCTV)9/28/2017227Liz Finarty, IA DOT- Chariton RCE, lizfinarty@iowadot.us 641-774-5056, 641-777-2871Mark Van DykeChuck Culbertson, IA DOT- Chariton RCE, chuck.culbertson@iowadot.us, 641-774-5056, 641-774-6739YesQueue Detection3/8/20173/15/20173/15/20179/27/2017Charge all devices to (378) including TIM. Lane Shifts NB & SB, Full Camera coverage requested, Queue detection at both ends. Traffic on NBL, working on SBL. Head to head traffic on I-35 all summer. (2016)
62
Complete5G175G175G US 61 in Lee Co, Cameras for wind blades$7,00039290612089BRFN-061-2(89)—39-29
LeeUS 61 in Lee County, Cameras to view movements of wind turbine bladesN/aIPMark Van Dyke1/17/20171/17/2017District 5, MVE, Permit Center, TMC, T & S today discussing movement of the
large wind blades down in Lee County. There is going to be a large number
blades moving from the Siemen plant to a storage area three miles south of
their plant. From the plant to the storage site is a right turn onto US 61 then
a right turn onto 280th. The concern of the District is the return
trip from the storage site back to the plant. The semis are not being required
to shorten up so they will be long crossing US 61 to go back north and then
again a left into the plant.

63
Complete5H175C17I-35 Interchange at G76 near New Virginia$59,390.55$6,512,00014910352423BRFIMX‐035‐2(423)44‐‐14‐91Warren35Bridge Replacement-PPCB12/20/2016Plans & Pre-Con MM2/22/20174/3/201710/2/2017131Liz Finarty, IA DOT- Chariton RCE, lizfinarty@iowadot.us 641-774-5056, 641-777-2871Mark Van DykeRusty Stansbery, 641-774-5056, 641-777-42983/8/20173/14/20173/15/20173/15/201712/5/2017Over Interstate. Night closures only on I-35.Will have more details closer to pre-con. Will plan for IWZ, no work on 35, one of the incident routes, ramp closures: NB off ramp SB on ramp coming from the north. 130 working days. (Full season).
64
Complete5J175E.17Ia. 28 Intersection In Martensdale$40,497$1,620,0002R910925056NHSN‐092‐5(56)‐‐2R‐91 Warren92PCC Pavement - Grade and Replace5/16/2017Yes06/19/201712/1/201790Liz Finarty, IA DOT- Chariton RCE, lizfinarty@iowadot.us 641-774-5056, 641-777-2871
Mark Van DykeThayer, Nate <NATE.THAYER@iowadot.us>

Poush, Vincent <Vincent.Poush@iowadot.us>
12/5/2017Will need to relocate the TIM cameraLetting date has changed to May. Will start after July 4th. No preliminary plans available now, will send in a month or so. Staging for this intersection will be complicated. This is on a main TIM route, so there is concern there. 569 to 5 re-route the detour or take them down 34? It is a long detour, we want to monitor to see if people are sneaking by. Need to check with D1 to make sure there is no conflict in Indianola 69 & D4 for 69 and 80. Add some additional signage/DMS to let drivers know where to go. Cameras are needed. Diversion route, blue route will no longer work, purple route should still work as primary, orange no longer works.+
65
Active5K175F17From Approx. 2 Miles S. of IA 92 N. to Muscatine Co. Line$430,573$20,739,0003L580613059HSIPX‐061‐3(59)‐‐3L‐58 Louisa 61PCC Pavement - Grade and Replace7/19/2016Yes4/1/20179/28/2018545Giarmo, Lauren <LAUREN.GIARMO@iowadot.us>Mark Van DykeYesTIM plan; Cameras for monitoring during Stages 2 & 3; PDMS with possible Queue Detection on IA 92.3/8/20173/28/173/29/17Paving to expand from 2 lanes to 4 lane expressway, including 2 new interchangesCarry project over from last year, already active.Will have TIM. Was not able to start full construction (paving) last fall. 
Will start ASAP in spring. Krol paving (contractor), Pre-con already happened.   A lot of the work initially will be off the roadway, will affect traffic more heavily once they are ready to switch over to new lanes and construct interconnects. Assume there will be issues at the school. TIM plan will require IWZ devices. 

Camera? Yes - At the 92 interchange, during some of the staging queue detection and PDMS for some advanced warning if people get confused when using the new ramps. Fairly high truck traffic, should have a four way stop condition to deal with this will work operationally.   


Traffic impacts in stages 2-4; Stage 2 includes daytime flagging at south crossover. ** TIM Plan already complete, please make sure all IWZ devices are placed with TIM devices in mind.
66
Complete5L175H17E. Ia. 2 Intersection In Leon$20,250$516,0002J270691042 STPN‐069‐1(42)‐‐2J‐27 Decatur 69PCC Pavement - Grade and Replace3/21/2017Yes5/31/20175/31/20178/15/201760Liz Finarty, IA DOT- Chariton RCE, lizfinarty@iowadot.us 641-774-5056, 641-777-2871Mark Van Dyke5/25/20175/31/20176/2/20178/8/2017Critical closure open July 19 , Remaining work done in AugustDecatur County – incorporate intersection in Leon, monitor only. (42) add some cameras
67
Complete5M175I17Ia. 22 Intersection In Kalona$10,058$1,625,0002R920014048NHSN‐001‐4(48)‐‐2R‐92 Washington1PCC Pavement - Grade and Replace1/18/2017Yes4/10/20174/17/201711/15/2017130Mark Van DykeCamera for monitoring4/26/2017Complicated staging may be worth having a camera deployed so they can monitor
68
Complete5N175J17Ia. 5 Intersection In Albia$7,459$2,344,0002R680346089NHSN‐034‐6(89)‐‐2R‐68 Monroe 34PCC Pavement - Grade and Replace1/18/2017Yes4/10/174/18/174/1/177/10/201775Mark Van DykeCamera for monitoring4/10/20174/11/20174/11/20178/8/2017Complicated staging may be worth having a camera deployed so they can monitor
69
5O175K17Missouri State Line to Co Rd J14 (Various Locations)$2,676,0000E270351172IMN‐035‐1(172)0‐‐0E‐27Decatur35HMA Resurfacing with Milling2/21/2017Yes115Mark Van DykeTied with 5QMonitor only: paving shoulders Decatur county with shoulder closures
70
5P175L17White Breast Creek 1.6 mi E of E Jct US 65$1,540,00038590346079BRF‐034‐6(79)‐‐38‐59Lucas34Bridge Replacement-PPCB1/18/20173/13/2017Mark Van DykeNothing planned, but possible monitoring cameraSRF to review plans. They mentioned as a possible TCP.
71
5Q175M17From Missouri State Line N. to W. I-35/80/235 Interchange$650,0000E270351144 IMN‐035‐1(144)0‐‐0E‐27Decatur35PCC Patching2/21/2017Mark Van DykeTied with 5OPCC patching – intermittent closures. Monitor.
72
5R175N17Mississippi River in Burlington$42,433$800,00039290349217BRFN‐034‐9(217)‐‐39‐29Des Moines34Bridge Repair1/18/2017Yes
late june/early july
30Mark Van DykeBurlington Bridge repair. 30 working days, closing a lane in each direction. Border bridge- there may be a need for devices. May have a need for TIM as well. Jared Smith will be working on border bridge TIM plans, but they are lower priority now.
73
5S17I-35 in Clark & Warren Counties, median repair0E200351173IMN-035-1(173)24--0E-20Clark/Warren35Median drain repairIPMark Van DykeMedian repair, Clark & Warren County (173) 4 mile lane closures each direction, TBR at locations of actually doing the work.  3 or 4 locations where they are working within the 4 mile closures, might be tricky to set up the deployment as the work zone moves. Had a backup over the Thanksgiving Day holiday. Perhaps add some sensors so they could detour traffic if needed.  Carry over from last year and will be in place for at least the first half of the 2017 season.  The plans are available, but they are not sure how the contractor will perform the operations. Road Safe is the traffic control subcontractor.  Maybe put a few devices at just a few key intersections.
74
75
6I16US 20 & Old Highway Rd/Menards intersection
US 20 Interchange with SW Arterial
$120,6793H310321038NHSX-032-1(38)--3H-31
also NHSX-032-1(37)--3H-31
Dubuque32US 20 & Old Highway Rd/Menards intersection
US 20 Interchange with SW Arterial
7/19/20166/1/2017; 7/19 Paving; Sept Bridge Work2018240Benjamin Hucker
 benjamin.hucker@dot.iowa.gov
Office: 563-927-2397
Cell: 563-929-6903

Hugh Holak
   hugh.holak@dot.iowa.gov
Office: 563-927-2397
Cell: 563-920-9830
Ken YannaJohn Willenbring
Office: 563-927-2397
Cell: 563-920-9832

Douglas Hefel
douglas.hefel@dot.iowa.gov
2016: Should not affect traffic 2016 if they let. June/July planned letting, ROW issues currently. - Along 20 – Queue detection on Eastbound but none required on Westbound. Catfish Creek & NW Arterial covered so no devices needed. SB sidemount to warn of any traffic impact. - Dubuque has city camera and their own Operations Center. Possible temp signal at Seippel Road. Traffic plans and Detour are not final.

2017: Dubuque (37) Menards frontage road project, closing traffic and rerouting (started in 2016). Problems on 20 with full turn lanes. Will be effecting traffic for 2017. Plenty of cameras, but inbound message boards EB 20 by conningham, outbound by century drive and s of ashbury road. Problem is turning left from eb 20 to NB 32
Turing lane fills up and holds traffic
Up on 32 the city lengthen the turn lane, but the turn lanes are backing up.
The arterials work well if people are in the correct lane.
Queue detection on EB US 20 is required when construction impacts traffic - mostly need system leading into stoplight. WB traffic is part of signalized corridor (no Queue Detection). City is coordinating and monitoring signals. City is willing to share camera viewing privileges with Iowa DOT and need to be  integrated into TransSuite.
IWZ’s on NHSX-032-1(38)—3H-31 is not anticipated. For NHSX-032-1(37)—3H-31, we do not expect to impact mainline US 20 traffic until this fall, although the majority of the traffic impacts will occur next season (2018) any needed lane closures will take place between 9:00PM and 6:00AM, with two lanes of traffic in both directions maintained throughout the project outside of those hours.
76
Completed6J176A17
SB I-380 over W-60 and R.R. 7.4 Miles N. of I-80
SB I-380 over Iowa River 7.9 Miles N. of I-80
$31,4040E523806287IMN-380-6(287)7--0E-52
IMN-380-6(289)8--0E-52
Johnson380Bridge Deck Overlay11/15/2016Plans & Pre-Con MM3/7/20174/3/174/3/174/3/174/3/20177/15/201785Doug McDonald, District Construction Engineer
319 350-2818
Ken YannaHR Green Inc.
John Lampint (HR Green)
319-270-3096
3/23/173/29/173/30/173/30/178/12/20172 lanes open during the day, and take the lanes at night.
Narrow lanes 11 ft. traffic split into the outsides with the work in the middle

(298) sister project. ** Same as last year. Narrow shoulders like last year. 10 ft. lanes during the split. Allowing for a 12 foot opening.
* Queue detection. Use camera in place where available. SB this year (NB last year). A couple extra boards last board
is Wilson ave in Cedar Rapids. Traffic control contract does not have any portable DMS – so we will provide them as
part of this contract.
77
Complete6K176B17In the City Of Cedar Rapids Over 15th St. and 16th St. 2.5 Miles N. Of US 30 (NBL)$24,219.000E573806290IMN-380-6(290)19--0E-57Linn380Bridge Deck Overlay11/15/2016Yes3/23/175/8/175/8/20175/8/1710/22/2017100John Vu for now 
This will be a consultant inspector
Ken YannaHR Green Inc.
John Lampint (HR Green)
319-270-3096
YESSet up Queue Detection
Sensor Re-calibration when Lane/Stage changes
3/7/20173/13/20173/13/20173/17/2017Iowa DOT working with City of Cedar Rapids for signal timing at Wilson - Discussion of closing ramps at Wilson (NB on Ramp)
May need a static "Be Prepared to Stop" on SB Diagonal On Ramp
Night Work - Still could be busy
(290) moved to January letting. Contractor unknown, 3 lane portion in Cedar Rapids, unique as they will maintain 3 lanes.
Of traffic in one direction and 1 lane in the other. Some camera in the area and some DMS. Large bridge so April may start and will run most of the summer.   ** first time using this traffic configuration in Iowa.  D6 will send plans.

Pavement Work on Weekends
Night Time Closures
TBR to be installed by Advanced Traffic Control
Jasper Construction : Project Manager
HR Green: Consultant (Inspection)
Late Start May 8 ,100 Working Days
78
6L176C17Mississippi River in Bettendorf
I-74 Approaches to Arch Bridge Over Mississippi River
I-74 Mississippi River Bridges Between Bettendorf, IA and Moline,IL
WB I-74 And U.S. 67 Ramps B and D In Bettendorf
0E820741254IMN-074-1(254)5--0E-82
BRFIM-074-1(197)5--05-82
BRFIM-074-1(198)5--05-82
BRFIM-074-1(199)5--05-82
Scott74Bridge Rehabilitation01/18/2017Yes4/3/174/18/1707/03/1790Mark BrandlKen YannaCosts shared with Illinois DOT.
Will utilize existing ITS - Check on Permanent APS Logic
Night work. No additional IWZ needed. Monitor only. WB bridge work must be done by July 17.
(197) , (198), (199) will not affect roadway
until 3 years from now.  New bridge construction.
Monitoring before during and after Iteris helping with this.
79
6N176E.17Mt Vernon/Lisbon Bypass from W of Wilcox Rd to IA 1 (120) to Spring Creek (188) to E of Charles Ave (189)NHSX-030-7(120)--3H-57
NHSX-030-7(188)--3H-57
NHSX-030-7(189)-3H-57
Linn30Grading2/1/2017Yes4/3/20179/27/201820Mark BrandlKen YannaMonitor(120), (188), (189) construction not on the mainline. Paving next year may affect traffic. They will affect Ia. 1 just south of 30. 2 lanes of traffic at all times. November of 2017 is when bridge over one will start.   Likely a "Monitor Only" project
80
Complete6Q176H17In The City Of Davenport Over I-80 (EBL)$62,7750E820741231IMN-074-1(231)0--0E-82Scott74Reconstruction - Bridge Deck Replacement12/20/2016Yes4/27/20175/8/20176/5/178/7/201750Mark BrandlKen YannaBart Hofeldt 563-349-4578IWZ- Queue Detection4/27/20175/3/20175/4/20175/5/20178/7/2017Add Queue Detection for EB 80, prior to 61, and to SB 61 prior to 80 to help guide traffic and detour trafficScott county 74, detour will increase traffic at 51 interchange and I-74 in EB lane. At rush hour we can expect delay.  
Davenport. Plans are out, let 12/20 late start first part of June, but it could happen earlier. May 1st early start.
Will need to shift I-80 traffic onto shoulders for bridge work.
81
6R176J17I-380 From I-80 N to US 218 in Waterloo0E523806282IMN-380-6(282)0--0E-52Johnson, Linn, Black Hawk +380PCC Patching03/21/20174/12/175/1/20174/24/1712/20/2017John VuKen YannaMonitorHMA project in Scott County will be night work, one lane closed for most of the summer.  They may be a potential for crashes in there.  Monitor with permanent Sensors, cameras - John Vu will provide daily/weekly updates for work progress, as available
82
6SOn I-80 WB only from 1.1 mile East of Y-40 (MP
285.5) to Z-30, (MP 302.8), including various overhead bridges
0282808282IMX-80-8(282)285--02-82Scott80Asphalt Overlays3/14/20174/2/20174/3/1712/21/2017115Mark BrandlKen YannaMonitorMcCarthy Improvements are handling the Project (Contractor)
Advanced Traffic Control will be responsible for Traffic Control
April 10 - Close of Bridge and Division
Also doing shoulder overlays up to the bridge work from 2016 (just west of Mississippi River)
83
6TIA 38 Bridge deck over I-80 at Atalissa/X46 interchange (Exit 265)$5,8050E16807106IMN-80-7(106)265--0E-16Cedar80Bridge Deck Overlay5/1/176/5/1740Mark BrandlKen YannaMonitorPlace CCTV at Bridge for Inspection, No other IWZ needed.
84
Complete6UUS 52/61 in Dubuque$5,95677310526508MB-052-6(508)46--77-31Dubuque52Bridge Repair7/20184/24/20176/2/201740Willy SorensonKen YannaData Collection - Temporary Sensorsensors4/24/20174/28/20176/5/2017Sensor deployment for data collectionsThe project this is for is PIN 16-31-052-050, MB-052-6(508)46--77-31, Dubuque Co. Designs 518, 618, 718, 818, with a July 2018 letting
85
6VI-80 Patching in Iowa, Johnson & Cedar counties Spring and Fall IMN-080-6(321)205--0E-48
IMN-080-6(322)240--0E-52
IMN-080-7(104)254--0E-16
Iowa Johnson Cedar80PCC Patching4/4/20174/6/2017May 8th
October 2nd
15
10
John VuKen YannaLowell Martin
319-560-4189
Monitor only: Inrix & permanent sensorsInrix & sensorsLate Start Spring Patching : May 8,2017 (15 Working Days)
Approximate Start Date for Fall Patching: October 2,2017 (10 Working Days)
Pre-con MM Cedar Falls Construction
86
Active6WI-80 & I-380 Systems Interchange & Forevergreen Interchange$25k FY18; $515k FY19
02-52-080-010
25520806427ITS-080-6(427)239--25-52 (FY18) ITS-080-6(428)239--25-52 (FY19)Johnson80Systems interchange reconstruction & new interchange at ForevergreenKen YannaBrian Stelken 563-920-9816
John Lamping 319-270-3096
IWZ- Camera Radio
87
9
88
0Staked
89
0DeployedCost Centers
90
10ActiveInterstates601000
91
26CompleteState/ US hwy611000
92
1Future year
93
94
IWZ+TIMComplete
95
IWZComplete
96
TIMComplete
97
NO ITSComplete
98