1 | DATE | DOCUMENT | SYSTEM | |
2 | 12/17/1987 | Water well and pump record for 354 Pinewood | EG | |
3 | 9/12/1988 | Well logs for MW-30i and MW-30d | Unit E | |
4 | 12/20/1991 | 373 Pinewood (deep) well log | EG | |
5 | 10/26/1992 | Consent Judgment between GSI and MDNR | General | |
6 | 10/30/1992 | GSI submittal of Report of LB-1 Aquifer Performance Test | EG | |
7 | 10/30/1992 | GSI submittal of Treatment System Specification Document | EG | |
8 | 10/30/1992 | MDNR information - Recent well test results, GSI consent judgment requirements, schedule of required submittals and responses | General | |
9 | 11/25/1992 | GSI submittal on Core Area "Evaluation of Groundwater Reinjection Alternative - Pilot Testing of UV/Oxidation Systems" | Core | |
10 | 12/23/1992 | MDNR response to GSI specification sheet for Evergreen System Treatment Equipment | EG | |
11 | 12/28/1992 | GSI submittal for remedial investigation work plan, system design and schedule for the Western System | Little Lake | |
12 | 1/22/1993 | Work plan for Evergreen System, Applications for groundwater reinjection permits for Evergreen and Core Systems | Core | |
13 | 1/22/1993 | Work plan for Evergreen System, Applications for groundwater reinjection permits for Evergreen and Core Systems | EG | |
14 | 2/15/1993 | Letter from Attorney General's office regarding National Pollutant Discharge Elimination System (NPDES) Act 245 appeal of Scio Township residents on permit issued to GSI | NPDES | |
15 | 2/16/1993 | CDM review of Western System Work Plan | Little Lake | |
16 | 2/22/1993 | MDNR response to 12-28-92 GSI submittal on Western System | Little Lake | |
17 | 2/23/1993 | First GSI quarterly report, 10/26/92 to 2/23/93 | QtrRpt | |
18 | 2/23/1993 | GSI "Report on Development of a Groundwater Flow Model for the Core Area" (excluding Appendix A, MODFLOW output, containing 7,921 data points from which report was generated) | Core | |
19 | 2/23/1993 | GSI submittal of Core System Work Plan | Core | |
20 | 3/2/1993 | CDM review of Evergreen System Work Plan | EG | |
21 | 3/9/1993 | GSI revisions of Western System submittal | Little Lake | |
22 | 3/22/1993 | GSI submittal of "Marshy Area System Work Plan" | Marshy | |
23 | 3/24/1993 | MDNR response to GSI Core & Evergreen System groundwater reinjection permits | Core | |
24 | 3/24/1993 | MDNR response to GSI Core & Evergreen System groundwater reinjection permits | EG | |
25 | 3/25/1993 | MDNR response to GSI 1/25/93 submittal on Evergreen system | EG | |
26 | 3/29/1993 | CDM review of Core System Work Plan | Core | |
27 | 3/31/1993 | GSI proposed work plan for groundwater monitoring on Honey Creek | NPDES | |
28 | 4/8/1993 | MDNR response to GSI Western System revision | Little Lake | |
29 | 4/16/1993 | GSI revisions of Evergreen System submittal | EG | |
30 | 4/20/1993 | MDNR response to Core System submittal | Core | |
31 | 4/26/1993 | GSI submittal of Spray Irrigation Field work plan | Spray | |
32 | 4/28/1993 | CDM review of Marshy Area System Work Plan | Marshy | |
33 | 4/28/1993 | MDNR memo on Honey Creek 95% exceedance flows | NPDES | |
34 | 5/12/1993 | GSI response to 4/20/93 MDNR comments on Core System Work Plan | Core | |
35 | 5/20/1993 | MDNR response to Evergreen work plan revisions | EG | |
36 | 5/20/1993 | MDNR response to Marshy Area work plan | Marshy | |
37 | 5/24/1993 | GSI submittal of "Soils System Plan" | Soils | |
38 | 5/27/1993 | Maps showing existing monitoring wells and estimated spread of dioxane groundwater contamination | General | |
39 | 5/28/1993 | CDM review of Spray Irrigation Field RI Work Plan | Spray | |
40 | 5/28/1993 | MDNR request for performance monitoring plan for Evergreen Groundwater Discharge | EG | |
41 | 6/10/1993 | GSI response to MDNR rejection of Marshy Area System Work Plan | Marshy | |
42 | 6/14/1993 | CDM comments on GSI Honey Creek Monitoring Plan | NPDES | |
43 | 6/15/1993 | MDNR review of proposed work plan to determine groundwater/surface water interaction on Honey Creek | NPDES | |
44 | 6/17/1993 | GSI submittal of Evergreen System Monitoring Plan | EG | |
45 | 6/17/1993 | Letter from S. Holodnick to R. Olsen | General | |
46 | 6/22/1993 | GSI submittal of Evergreen System Performance Monitoring Plan for groundwater discharge | EG | |
47 | 6/22/1993 | GSI submittal of Western Plume System Aquifer Evaluation | Little Lake | |
48 | 6/22/1993 | MDNR response to Spray Irrigation Field Work Plan | Spray | |
49 | 6/23/1993 | GSI submittal of Spray Irrigation Field Soil Flushing System Work Plan | Spray | |
50 | 6/30/1993 | CDM review of Soil Remediation Plan | Soils | |
51 | 6/30/1993 | Second GSI Quarterly Report, 3/1/93 to 5/31/93 | QtrRpt | |
52 | 7/13/1993 | GSI clarification of Spray Irrigation Field Work Plan | Spray | |
53 | 7/14/1993 | G. R. Kunkle and Associates review of Gelman work plan for study of Honey Creek | NPDES | |
54 | 7/22/1993 | MDNR request for performance monitoring plan for proposed Core Area System Groundwater Discharge | Core | |
55 | 7/22/1993 | MDNR response to Work Plan for Soils System | Soils | |
56 | 7/27/1993 | CDM review of Evergreen System Monitoring Plan | EG | |
57 | 7/28/1993 | CDM review of Spray Irrigation Field Soil Flushing System | Spray | |
58 | 8/3/1993 | GSI submittal of Proposed Study and Interim Discharge to Honey Creek and Honey Creek Tributary | NPDES | |
59 | 8/3/1993 | MDNR clarification of 7/22/93 letter requesting performance monitoring plan | Core | |
60 | 8/5/1993 | GSI Progress Update for Core System Work Plan | Core | |
61 | 8/6/1993 | MDNR response to Evergreen System Monitoring Plan | EG | |
62 | 8/6/1993 | MDNR response to Evergreen System Performance Monitoring Plan for Groundwater Discharge | EG | |
63 | 8/6/1993 | MDNR response to Spray Irrigation Field Soil Flushing System Work Plan | Spray | |
64 | 8/11/1993 | GSI reply to 7/22/93 MDNR response to Soils System Plan | Soils | |
65 | 8/19/1993 | GSI reply to 7/22/93 MDNR response to Core Area Exemption | Core | |
66 | 9/1/1993 | CDM review of GSI 8/1/93 revised Honey Creek proposal | NPDES | |
67 | 9/1/1993 | CDM review of Kunkle's 7/14/93 comments on original Honey Creek proposal | NPDES | |
68 | 9/7/1993 | GSI reply to 8/6/93 MDNR response to Evergreen Monitoring Plan | EG | |
69 | 9/8/1993 | GSI reply to 8/6/93 MDNR response to Evergreen Performance Monitoring Plan | EG | |
70 | 9/8/1993 | Kunkle's review of GSI 8/1/93 revised Honey Creek proposal | NPDES | |
71 | 9/13/1993 | GSI third quarterly report, 6/1/93 to 8/31/93 | QtrRpt | |
72 | 9/21/1993 | MDNR response to GSI revision of Marshy Area Work Plan | Marshy | |
73 | 9/22/1993 | GSI submittal of revisions to Spray Irrigation Field Soil Flushing Work Plan | Spray | |
74 | 10/4/1993 | Bore hole log for IW-1 (also related to Evergreen System) | Unit E | |
75 | 10/4/1993 | Letter from A. Gatta to City of Ann Arbor | General | |
76 | 10/4/1993 | MDNR response to 8/3/93 GSI submittal of revised Honey Creek work plan | NPDES | |
77 | 10/11/1993 | Letter from J. Fahrner to L. Lipinski | General | |
78 | 10/12/1993 | MDNR response to 9/8/93 GSI submittal on Evergreen System Performance Monitoring Plan for Groundwater Discharge | EG | |
79 | 10/18/1993 | Notice of public hearing on NPDES Permit #MI-0008453 | NPDES | |
80 | 10/25/1993 | GSI submittal of "Proposed Work Plan for Groundwater Monitoring Along the Honey Creek/Honey Creek Tributary" | NPDES | |
81 | 10/25/1993 | GSI submittal of Evergreen System performance monitoring plan and exemption notification for groundwater discharge | EG | |
82 | 10/26/1993 | Letter from C. Gelman to MDNR on Evergreen monitor wells | EG | |
83 | 10/26/1993 | MDAG memo of GSI installment payment for past costs | General | |
84 | 10/28/1993 | Letter from S. Garris to MDNR on discharge to Honey Creek | NPDES | |
85 | 10/29/1993 | Letter and motion to adjourn or reschedule contested case hearing on NPDES permit for discharge to Honey Creek | NPDES | |
86 | 11/5/1993 | MDNR response to C. Gelman letter of 10/26/93 | EG | |
87 | 11/8/1993 | MDNR response to S. Garris letter of 10/28/93 | NPDES | |
88 | 11/16/1993 | GSI revision to Evergreen System Performance Monitoring Plan for Groundwater Discharge | EG | |
89 | 11/17/1993 | Resolution by Washtenaw Co. Board of Commissioners on discharge to Honey Creek | NPDES | |
90 | 11/19/1993 | Memo from ERD to WMD on Evergreen System Performance Monitoring Plan for Groundwater Discharge | EG | |
91 | 12/2/1993 | MDNR response to Paula Globerson letter of 10/8/93 (attached) | General | |
92 | 12/8/1993 | MDNR response to 10/25/93 GSI revision of proposal to discharge to Honey Creek | NPDES | |
93 | 12/8/1993 | MDNR response to 11/16/93 GSI revision to Evergreen System Performance Monitoring Plan for Groundwater Discharge | EG | |
94 | 12/13/1993 | GSI submittal of Soils System schedule and sample results | Soils | |
95 | 12/13/1993 | MDNR response to GSI submittal of Groundwater Discharge Permit Exemption notification for Evergreen System | EG | |
96 | 12/15/1993 | GSI fourth quarterly report, 9/1/93 to 11/30/93 | QtrRpt | |
97 | 12/15/1993 | GSI submittal of Marshy Area System Work Plan Update | Marshy | |
98 | 12/20/1993 | GSI letter to Ann Arbor with data on Dolph Park discharge | Core | |
99 | 12/20/1993 | GSI submittal of Western System monitoring results | Little Lake | |
100 | 12/20/1993 | Letter from Alan Wasserman on change in GSI Project Manager | General |