1 | ID | Job Description | Duration | Start | Finish | % Progres | ||||||||||||||
2 | LISTRIK STG dan Batu Bara II | 7,03 days | 4/9/26 7:30 | 4/16/26 8:09 | ||||||||||||||||
3 | BOILER & STEAM SYSTEM | 7,03 days | 4/9/26 7:30 | 4/16/26 8:09 | ||||||||||||||||
4 | Start Work | 0 days | 4/9/26 7:30 | 4/9/26 7:30 | ||||||||||||||||
5 | F6P-2342WFAM : MOTOR FOR COAL FEEDER | Service di bengkel | 3,41 days | 4/10/26 7:30 | 4/13/26 17:18 | |||||||||||||||
6 | Pengamanan,siapkan alat kerja | 0,5 hrs | 4/10/26 7:30 | 4/10/26 8:00 | 100 | |||||||||||||||
7 | Minta safety permit dan safety tag | 0,25 hrs | 4/10/26 7:45 | 4/10/26 8:00 | 100 | |||||||||||||||
8 | Offkan breaker dan beri safety tag | 0,25 hrs | 4/10/26 8:00 | 4/10/26 8:15 | 100 | |||||||||||||||
9 | Buka/lepas kabel power motor | 1 hr | 4/10/26 8:15 | 4/10/26 9:15 | 100 | |||||||||||||||
10 | Buka baut pondasi motor & coupling | 1 hr | 4/10/26 9:15 | 4/10/26 10:15 | 100 | |||||||||||||||
11 | Turunkan motor dari pondasi | 0,5 hrs | 4/10/26 10:15 | 4/10/26 10:45 | 100 | |||||||||||||||
12 | Angkat motor ke bkl & beri name tag | 1 hr | 4/10/26 10:45 | 4/10/26 13:45 | 100 | |||||||||||||||
13 | Bongkar motor lepas cover dan rotor | 3 hrs | 4/10/26 13:45 | 4/10/26 16:45 | 100 | |||||||||||||||
14 | Servis stator/fernis dan dioven | 12 hrs | 4/10/26 16:45 | 4/11/26 19:45 | 100 | |||||||||||||||
15 | Servis dan balancing Rotor | 7 hrs | 4/11/26 9:45 | 4/11/26 19:45 | 100 | |||||||||||||||
16 | Pasang Bearing Baru | 2 hrs | 4/11/26 19:45 | 4/12/26 8:45 | 100 | |||||||||||||||
17 | Rakit kembali motor di bengkel | 3 hrs | 4/12/26 8:45 | 4/12/26 13:45 | 100 | |||||||||||||||
18 | Servis body motor dan cat motor | 2 hrs | 4/12/26 13:45 | 4/12/26 15:45 | 100 | |||||||||||||||
19 | Test motor ukur Amp & vibrasi motor | 0,5 hrs | 4/12/26 15:45 | 4/12/26 16:15 | 100 | |||||||||||||||
20 | Angkat motor ke lapangan/dipasang | 1 hr | 4/12/26 16:15 | 4/12/26 17:15 | 100 | |||||||||||||||
21 | Pasang baut pondasi motor | 1 hr | 4/12/26 17:15 | 4/13/26 8:15 | 100 | |||||||||||||||
22 | Pasang kabel power motor | 1 hr | 4/13/26 8:15 | 4/13/26 9:15 | 100 | |||||||||||||||
23 | Servis control lokal/LCS dan MCC | 1 hr | 4/13/26 9:15 | 4/13/26 10:15 | 100 | |||||||||||||||
24 | Dempul box terminal dan box LCS | 0,5 hrs | 4/13/26 10:15 | 4/13/26 10:45 | 100 | |||||||||||||||
25 | Onkan breaker dan lepas safety tag | 0,15 hrs | 4/13/26 10:45 | 4/13/26 10:54 | 100 | |||||||||||||||
26 | Test putaran motor | 0,25 hrs | 4/13/26 10:54 | 4/13/26 11:09 | 100 | |||||||||||||||
27 | Alignment dan Couple motor ke pompa/gearbox | 3 hrs | 4/13/26 11:09 | 4/13/26 16:09 | 100 | |||||||||||||||
28 | Test beban motor,ukur vib dan amp | 1 hr | 4/13/26 16:09 | 4/13/26 17:09 | 100 | |||||||||||||||
29 | Catat hasil servis di history card | 0,15 hrs | 4/13/26 17:09 | 4/13/26 17:18 | 100 | |||||||||||||||
30 | F6P-2342RMXA : MOTOR FOR COAL MILL DYNAMIC CLASSIFIER 2A | Service di bengkel | 2,05 days | 4/9/26 7:30 | 4/11/26 8:40 | |||||||||||||||
31 | Pengamanan,siapkan alat kerja | 0,5 hrs | 4/9/26 7:30 | 4/9/26 8:00 | 100 | |||||||||||||||
32 | Minta safety permit dan safety tag | 0,25 hrs | 4/9/26 7:45 | 4/9/26 8:00 | 100 | |||||||||||||||
33 | Offkan breaker dan beri safety tag | 0,25 hrs | 4/9/26 8:00 | 4/9/26 8:15 | 100 | |||||||||||||||
34 | Buka cover rumah-rumahan compressor | 0,5 hrs | 4/9/26 8:15 | 4/9/26 8:45 | 100 | |||||||||||||||
35 | Buka/lepas kabel power motor | 1 hr | 4/9/26 8:45 | 4/9/26 9:45 | 100 | |||||||||||||||
36 | Buka baut pondasi motor & coupling | 1 hr | 4/9/26 9:45 | 4/9/26 10:45 | 100 | |||||||||||||||
37 | Angkat motor ke bkl & beri nametag | 1 hr | 4/9/26 10:45 | 4/9/26 13:45 | 100 | |||||||||||||||
38 | Bongkar motor lepas cover dan rotor | 2 hrs | 4/9/26 13:45 | 4/9/26 15:45 | 100 | |||||||||||||||
39 | Servis stator/varnish dan dioven | 10 hrs | 4/9/26 15:45 | 4/10/26 4:15 | 100 | |||||||||||||||
40 | Servis dan balancing Rotor | 7 hrs | 4/9/26 19:45 | 4/10/26 4:15 | 100 | |||||||||||||||
41 | Ganti bearing | 2 hrs | 4/10/26 4:15 | 4/10/26 6:15 | 100 | |||||||||||||||
42 | Rakit kembali motor di bengkel | 2 hrs | 4/10/26 6:15 | 4/10/26 8:16 | 100 | |||||||||||||||
43 | Service body motor dan cat motor | 1,5 hrs | 4/10/26 8:16 | 4/10/26 9:46 | 100 | |||||||||||||||
44 | Test motor ukur Amp & vibrasi motor | 0,5 hrs | 4/10/26 9:46 | 4/10/26 10:16 | 100 | |||||||||||||||
45 | Angkat motor ke lapangan/dipasang | 1 hr | 4/10/26 10:16 | 4/10/26 11:16 | 100 | |||||||||||||||
46 | Pasang baut pondasi motor | 0,5 hrs | 4/10/26 11:16 | 4/10/26 13:46 | 100 | |||||||||||||||
47 | Pasang kabel power motor | 1 hr | 4/10/26 13:46 | 4/10/26 14:46 | 100 | |||||||||||||||
48 | Tutup kembali cover rumah-rumahan compressor | 1 hr | 4/10/26 14:46 | 4/10/26 15:46 | 100 | |||||||||||||||
49 | Servis control lokal/LCS dan MCC | 1 hr | 4/10/26 15:46 | 4/10/26 16:46 | 100 | |||||||||||||||
50 | Dempul box terminal dan box LCS | 0,5 hrs | 4/10/26 16:46 | 4/10/26 17:16 | 100 | |||||||||||||||
51 | Onkan breaker dan lepas safety tag | 0,5 hrs | 4/10/26 17:16 | 4/11/26 7:46 | 100 | |||||||||||||||
52 | Test putaran dan ukur ampere | 0,25 hrs | 4/11/26 7:46 | 4/11/26 8:01 | 100 | |||||||||||||||
53 | Test beban motor,ukur vib dan amp | 0,5 hrs | 4/11/26 8:01 | 4/11/26 8:31 | 100 | |||||||||||||||
54 | Catat hasil servis di history card | 0,15 hrs | 4/11/26 8:31 | 4/11/26 8:40 | 100 | |||||||||||||||
55 | F6P-2342RMXB : MOTOR FOR COAL MILL DYNAMIC CLASSIFIER 2B | Service di tempat | 2,26 days | 4/9/26 7:30 | 4/11/26 13:40 | |||||||||||||||
56 | Pengamanan,siapkan alat kerja | 0,5 hrs | 4/9/26 7:30 | 4/9/26 8:00 | 100 | |||||||||||||||
57 | Minta safety permit dan safety tag | 0,25 hrs | 4/9/26 7:45 | 4/9/26 8:00 | 100 | |||||||||||||||
58 | Offkan breaker dan beri safety tag | 0,25 hrs | 4/9/26 8:00 | 4/9/26 8:15 | 100 | |||||||||||||||
59 | Buka cover rumah-rumahan compressor | 0,5 hrs | 4/9/26 8:15 | 4/9/26 8:45 | 100 | |||||||||||||||
60 | Buka/lepas kabel power motor | 1 hr | 4/9/26 8:45 | 4/9/26 9:45 | 100 | |||||||||||||||
61 | Buka baut pondasi motor & coupling | 1 hr | 4/9/26 9:45 | 4/9/26 10:45 | 100 | |||||||||||||||
62 | Angkat motor ke bkl & beri nametag | 1 hr | 4/9/26 10:45 | 4/9/26 13:45 | 100 | |||||||||||||||
63 | Bongkar motor lepas cover dan rotor | 2 hrs | 4/9/26 13:45 | 4/9/26 15:45 | 100 | |||||||||||||||
64 | Servis stator/varnish dan dioven | 10 hrs | 4/9/26 15:45 | 4/10/26 4:15 | 100 | |||||||||||||||
65 | Servis dan balancing Rotor | 7 hrs | 4/9/26 19:45 | 4/10/26 4:15 | 100 | |||||||||||||||
66 | Ganti bearing | 2 hrs | 4/10/26 4:15 | 4/10/26 6:15 | 100 | |||||||||||||||
67 | Rakit kembali motor di bengkel | 2 hrs | 4/10/26 6:15 | 4/10/26 8:16 | 100 | |||||||||||||||
68 | Service body motor dan cat motor | 1,5 hrs | 4/10/26 8:16 | 4/10/26 9:46 | 100 | |||||||||||||||
69 | Test motor ukur Amp & vibrasi motor | 0,5 hrs | 4/10/26 9:46 | 4/10/26 10:16 | 100 | |||||||||||||||
70 | Angkat motor ke lapangan/dipasang | 1 hr | 4/10/26 10:16 | 4/10/26 11:16 | 100 | |||||||||||||||
71 | Pasang baut pondasi motor | 0,5 hrs | 4/10/26 11:16 | 4/10/26 13:46 | 100 | |||||||||||||||
72 | Pasang kabel power motor | 1 hr | 4/10/26 13:46 | 4/10/26 14:46 | 100 | |||||||||||||||
73 | Tutup kembali cover rumah-rumahan compressor | 1 hr | 4/10/26 14:46 | 4/10/26 15:46 | 100 | |||||||||||||||
74 | Servis control lokal/LCS dan MCC | 1 hr | 4/10/26 15:46 | 4/10/26 16:46 | 100 | |||||||||||||||
75 | Dempul box terminal dan box LCS | 0,5 hrs | 4/10/26 16:46 | 4/10/26 17:16 | 100 | |||||||||||||||
76 | Onkan breaker dan lepas safety tag | 0,5 hrs | 4/10/26 17:16 | 4/11/26 7:46 | 100 | |||||||||||||||
77 | Test putaran dan ukur ampere | 0,25 hrs | 4/11/26 7:46 | 4/11/26 8:01 | 100 | |||||||||||||||
78 | Alignment dan pasang baut pondasi | 2 hrs | 4/11/26 8:01 | 4/11/26 10:01 | 100 | |||||||||||||||
79 | Couple motor ke pompa/gearbox | 1 hr | 4/11/26 10:01 | 4/11/26 11:01 | 100 | |||||||||||||||
80 | Test beban motor,ukur vib dan amp | 0,5 hrs | 4/11/26 11:01 | 4/11/26 13:31 | 100 | |||||||||||||||
81 | Catat hasil servis di history card | 0,15 hrs | 4/11/26 13:31 | 4/11/26 13:40 | 100 | |||||||||||||||
82 | F6P-2343RMAM :MOTOR FOR COAL MILL 2A | service di tempat Motor CM 2A | 0,08 days | 4/9/26 7:30 | 4/9/26 9:30 | |||||||||||||||
83 | Pengamanan,siapkan alat kerja | 0,25 hrs | 4/9/26 7:30 | 4/9/26 7:45 | 100 | |||||||||||||||
84 | Siapkan safety permit dan safety tag | 0,25 hrs | 4/9/26 7:30 | 4/9/26 7:45 | 100 | |||||||||||||||
85 | Offkan breaker di MCC dan beri safetytag | 0,15 hrs | 4/9/26 7:45 | 4/9/26 7:54 | 100 | |||||||||||||||
86 | Cek dan service motor Di tempat | 1,5 hrs | 4/9/26 7:54 | 4/9/26 9:24 | 100 | |||||||||||||||
87 | Catat hasil servis di history card | 0,1 hrs | 4/9/26 9:24 | 4/9/26 9:30 | 100 | |||||||||||||||
88 | F6P-2343RMBM : MOTOR FOR COAL MILL 2B | service di tempat Motor CM 2B | 0,08 days | 4/9/26 9:30 | 4/9/26 11:30 | |||||||||||||||
89 | Pengamanan,siapkan alat kerja | 0,25 hrs | 4/9/26 9:30 | 4/9/26 9:45 | 100 | |||||||||||||||
90 | Siapkan safety permit dan safety tag | 0,25 hrs | 4/9/26 9:30 | 4/9/26 9:45 | 100 | |||||||||||||||
91 | Offkan breaker di MCC dan beri safetytag | 0,15 hrs | 4/9/26 9:45 | 4/9/26 9:54 | 100 | |||||||||||||||
92 | Cek dan service motor Di tempat | 1,5 hrs | 4/9/26 9:54 | 4/9/26 11:24 | 100 | |||||||||||||||
93 | Catat hasil servis di history card | 0,1 hrs | 4/9/26 11:24 | 4/9/26 11:30 | 100 | |||||||||||||||
94 | F6P-2401GBM : MOTOR FOR FORCED DRAFT FAN 2 | cek, service & ganti pelumas/oil Fdfan | 0,15 days | 4/9/26 13:30 | 4/9/26 17:06 | |||||||||||||||
95 | Pengamanan,siapkan alat kerja | 0,25 hrs | 4/9/26 13:30 | 4/9/26 13:45 | 100 | |||||||||||||||
96 | Siapkan safety permit dan safety tag | 0,25 hrs | 4/9/26 13:45 | 4/9/26 14:00 | 100 | |||||||||||||||
97 | Offkan breaker di MCC dan beri safetytag | 0,15 hrs | 4/9/26 13:51 | 4/9/26 14:00 | 100 | |||||||||||||||
98 | Cek dan service motor Di tempat | 3 hrs | 4/9/26 14:00 | 4/9/26 17:00 | 100 | |||||||||||||||
99 | Catat hasil servis di history card | 0,1 hrs | 4/9/26 17:00 | 4/9/26 17:06 | 100 | |||||||||||||||
100 | F6P-2411GBM : MOTOR FOR PRIMARY AIR FAN 2 | cek, service ganti oil PAF di tempat | 0,73 days | 4/9/26 17:06 | 4/10/26 10:36 |