NUMBERTASK TITLETASK OWNERSTART DATEDUE DATEDURATIONSTATUSREASONS
9
10
1Mold design, 3D formwork design & electronic component finalize
11
1.1Desk 3D formwork finalizeProduct Manager-Qiu2/1/232/28/2327Done/
12
1.2Electronic components finalizeProduct Manager-Qiu2/1/232/28/2327Done/
13
1.3Mold designProduct Manager-Qiu2/1/232/28/2327Done/
14
2Mold Manufacturing, CNC, finishing, mold trial, and production T0, T1, and T2
15
2.1Mold ManufacturingProduct Manager-Qiu2/20/234/15/2355Done/
16
2.2*Mold Modify (Follow Production Process)Product Manager-Qiu4/15/234/20/235Done/
17
2.3T0 sample (mold tooling)Product Manager-Qiu4/25/236/20/2355DoneT0 and T1:
Supplier Integration:
We have encountered challenges in managing multiple mold suppliers, which led us to reevaluate our plan. As a result, we have integrated two reliable mold suppliers who can ensure quality control throughout the process.
Product Design Efforts: We have invested considerable time in changing and optimizing our products. For instance, we have replaced the fanless power supply design, eliminating power-related noise and enhancing the user experience.
18
2.4T0 sample assembly, use testProduct Manager-Qiu6/21/237/14/2323Done
19
2.5Structure adjustment, appearance adjustment, mold adjustment, supplier replacementProduct Manager-Qiu7/15/2310/10/2385DoneFollowing the results from the T0 stage sample tests, we identified several areas for improvement. We have refined the product's overall architecture, which necessitated some changes in its appearance. Additionally, we made adjustments to the structural mold. To further enhance product quality, we have also switched to a new manufacturer.
20
2.6T1 sample (mold tooling)Product Manager-Qiu10/11/2311/12/2331Done
21
2.7T2 sample (mold tooling)Product Manager-Qiu11/13/2312/13/2330Done/
22
2.8OTA (Over-The-Air)Product Manager-Qiu1/1/241/31/2430Done
23
2.9T3 sample (mold tooling)Product Manager-Tang2/1/243/29/2430Done
24
3Product trial production and mass productionTrial Production and Mass Production:
Material Supplier: Anticipating challenges due to the multitude of material suppliers, any delay in logistics could potentially result in a product delay as a whole. The shortage of certain electronic components, such as the main controller and MCU, in the market has prompted us to adjust our production timeline. We can only order these components for trial production after the conclusion of T2. Similarly, mass production is contingent upon the completion of trial production and material availability.
Extended Timeframe: Initially, our suppliers underestimated the complexity of our products, which has resulted in an extension of the estimated time for production. We acknowledge this oversight and are taking steps to address it.
25
3.1Trial production&products are further optimized according to mass production needsProduct Manager-Tang4/1/244/20/2419Working on it
26
3.2Start purchasing materials for mass productionProduct Manager-Tang4/20/245/1/2410Not yet
27
3.3Mass productionProduct Manager-Tang5/1/245/31/2430Not yet/
28
3.4ShippingProduct Manager-Tang6/1/246/30/2430Not yet
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
80
81
82
83
84
85
86
87
88
89
90
91
92
93
94
95
96
97
98
99
100