ABCDEFGHIJKLMNOPQRSTUVWXYZ
1
Preliminary Economic Analysis of Railbelt RPS, Scenario 3
2
By: Alan Mitchell, Analysis North, alan@analysisnorth.com, 907-310-9124
3
4
This model calculates very preliminary Costs and Benefits of Implementing Scenario 3 relative to the Base Case
5
Scenario described in the Renewable Portfolio Standard Assessment for Alaska's Railbelt, authored by the National
6
Renewable Energy Laboratory (NREL).
7
8
This is a back-of-the-envelope analysis; a thorough estimate of costs and benefits is needed.
9
The model simplistically assumes that all of the investments to implment Scenario 3 are made in 2035,
10
and fuel savings are calculated and accrued from that point forward. All dollars are 2020 inflation-adjusted dollars.
11
12
** If you make a Copy and Edit this Model, please indicate who you are and what changes were made.
13
14
Summary Slides are available Here
15
16
Blue values are inputs,
17
Purple values are inputs to this model but come unaltered from the NREL Study.
18
Black values are calculated by this model.
19
20
Changes in Generation Capacity between Base Case and Scenario 3
21
22
From Table 4 of the NREL RPS Study
23
24
Final Portfolio Capacity (MW)
25
TechnologyBase CaseScenario 3Change
26
Wind45847802
27
Solar1456455
28
Hydro (Storage)18624862
29
Hydro (run-of-river)25250
30
Geothermal0.40.40
31
Biomass05050
32
Landfill Gas770
33
Tidal000
34
Battery Storage1631630
35
Fossil thermal2,0481,911-137
36
Total2,4753,7071,232MW
37
38
39
Estimate Capital Costs for Changes in Generation Capacity to Implement Scenario 3
40
Use the change in generation capacity from above along with per unit capital cost estimates to estimate
41
total capital cost required to implement Scenario 3.
42
43
TechnologyGeneration Change, MWUnit Generation Capital Cost
$ / kW (2020 $)
Additional Generation Capital Cost
$ million (2020 $)
Notes on Unit Generation Cost Estimates
44
Wind802$2,912$2,3351.94 times the US Average for 100-200 MW plants built in 2019-2020 (from the 2021 Land-based Wind Market Report). 1.94 is the ratio of the Eva Creek cost / kW to the national average at the time it was built. Conservative because larger RPS Project should be less. Also, coastal projects should be less.
45
Solar455$1,750$796Upper range of the cost estimate for a proposed HEA 20 MW project, as stated in this article: https://www.kbbi.org/2021-10-21/proposed-solar-farm-ippsolar
46
Hydro (Storage)62$1,484$92This is the cost of just adding another 63 MW Turbine to the Bradley Powerhouse. Rough estimate from Bryan Carey, AEA.
47
Hydro (run-of-river)0
48
Geothermal0
49
Biomass50$4,462$2231.94 (use Wind Capital Adjustment) times the EPA Average estimate here: https://www.epa.gov/sites/default/files/2015-07/documents/biomass_combined_heat_and_power_catalog_of_technologies_7._representative_biomass_chp_system_cost_and_performance_profiles.pdf
50
Landfill Gas0
51
Tidal0
52
Battery Storage0
53
Fossil thermal-137$1,510-$207From Railbelt IRP Study, Black and Veatch, Table 10-13, GE LM6000 Turbine: http://www.susitna-watanahydro.org/wp-content/uploads/2012/05/Black_Veatch_2010_AlaskaRIRPFinalReport.pdf, adjusted to 2020 $.
54
Total$3,240million
55
56
Conclusion:
Incremental capital costs to implement Scenario 3 are approximately $ 3.2 billion (2020 $)
57
58
59
Estimate Change in Annual Fuel and Operating Costs of Scenario 3 vs. the Base Case
60
Positive values in this Section are Cost Savings, negative value are cost increases.
61
62
Fuel Savings
63
Fuel Savings shown in the NREL RPS Report are for the year 2040. This model assumes a one-time investment in the year 2035, so adjust
64
first year fuel savings back to that year.
65
66
Low Fuel Savings Estimate in 2040:
$426million / year
67
High Fuel Savings Estimate in 2040:
$506million / year
68
Average:$466million / year
69
70
Scale this back to 2035 using ratio of blended fuel prices from those two years
71
2040 Blended Fuel Price:$16.6/ MMBTUfrom RPS Report
72
2035 Blended Fuel Price:$14.7/ MMBTUfrom RPS Report
73
Ratio of 2035 to 2040:0.886
74
75
2035 Fuel Savings:$413million / year
76
77
Operating & Maintenance Cost Impacts
78
Positive values are O&M Savings, negative are O&M Cost Increases
79
The per kW operating costs inputed below are applied to the additional capacity requirements calculated in the first section above.
80
81
CategoryOperating Cost
$ / kW / year
Savings
$ million / year
(2020 $)
Notes
82
Wind Operating Cost$49 $ (39)1.94 times average O&M for US plants with 2020 data. From Land-Based Wind Market Report, 2021 Edition, US DOE.
83
Solar Operating Cost$23 $ (11)1.46 times the value in this document, Slide 21: https://eta-publications.lbl.gov/sites/default/files/utility_scale_solar_2021_edition_slides.pdf . The 1.46 multiplier is consistent with Capital Cost estimate for solar.
84
Hydro (Storage) Operating Cost
$30 $ (2)Estimated as 2% of capital cost / year.
85
Biomass Operating Cost$245 $ (12)1.94 times the value in this table: https://www.eia.gov/outlooks/aeo/assumptions/pdf/table_8.2.pdf
86
Reduced Fossil Fixed Operating Cost
$78 $ 11 From Railbelt IRP Study, Black and Veatch, Table 10-13, GE LM6000 Turbine: http://www.susitna-watanahydro.org/wp-content/uploads/2012/05/Black_Veatch_2010_AlaskaRIRPFinalReport.pdf, adjusted to 2020 $.
87
Reduced Fossil Variable Operating Cost
$ 15 From Railbelt IRP Study, Black and Veatch, Table 10-13, GE LM6000 Turbine: http://www.susitna-watanahydro.org/wp-content/uploads/2012/05/Black_Veatch_2010_AlaskaRIRPFinalReport.pdf, adjusted to 2020 $.
88
Total $ (38)million per year
89
90
91
Summary of Benefits and Costs
92
93
Upfront Capital Cost
94
95
Additional Capital Cost for Scenario 3 beyond Base Case:
$3,240million
96
97
Annual Fuel and O&M Impacts
98
99
Inputs for Converting Annual Impacts to a Present Value
100
Real Discount Rate:3%per year. AEA value for Renerwable Energy Fund analysis, also is rate used in DOE Life-Cycle Cost Analysis