1 | SMART AW 2021-22 | |||||||
2 | Sl No. | ICDS | LSGI | AWC No. | Order number &Date | Present status | Date of updating status | Remarks |
3 | 1 | Nedumangad Addl | Aruvikkara | 84 | Smart AW 2021-22 ICDS/A8-2572/21, dtd 07.06.2021 | Structure completed Finishing work ongoing Will complete in Sept 2022 | 23/08/2022 | Tile laying in floor going on |
4 | 2 | Vellanad Adl | Aryanaadu | 6 | Smart AW 2021-22 ICDS/A8-2572/21, dtd 07.06.2021 | Estimate under preparation | 26/08/2022 | |
5 | 3 | Vellanad Adl | Aryanaadu | 9 | Smart AW 2021-22 ICDS/A8-2572/21, dtd 07.06.2021 | Estimate under preparation | 26/08/2022 | |
6 | 4 | Ettumanoor | Athirambuzha | 66 | Smart AW 2021-22 ICDS/A8-7935/21, dtd 04.11.2021 | G F structure works complete,F F brick works started | 23/08/2022 | Work Ongoing |
7 | 5 | Nenmara Adl | Ayiloor | 43 | Smart AW 2021-22 ICDS/A8-2572/21, dtd 12.07.2021 | GF Lintel level works ongoing | 24/08/2022 | Work Ongoing |
8 | 6 | Vadakara | Azhiyoor | 19 | Smart AW 2021-22 ICDS/A8-2572/21, dtd 02.11.2021 | work completed. part bill paid for Rs.357896/- | 10/5/23 | final bill prepared |
9 | 7 | Pothencode | Azhoor | 169 | Smart AW 2021-22 ICDS/A8-7935/21, dtd 04.11.2021 | സോയിൽ ഇൻവെസ്റ്റിഗേഷൻ റിപ്പോർട്ട് ലഭ്യമായിട്ടുണ്ട്. Excavation പ്രവൃത്തികൾ ആരംഭിച്ചിട്ടുണ്ട്. | 23/08/2022 | |
10 | 8 | Sulthan Batheri | Batheri | 81 | Smart AW 2021-22 ICDS/A8-7935/21, dtd 04.11.2021 | Agreement Executed ,Not started | 27.08.2022 | Not started started due to Land Dispute |
11 | 9 | Karadukka Adl | Bedadukka | 45 | Smart AW 2021-22 ICDS/A8-2572/21, dtd 29.07.2021 | Work Ongoing | 22/08/2022 | Roof structure work started |
12 | 10 | Kanjikkuzhi Adl | Cherthala Municipality | 30 | Smart AW 2021-22 ICDS/A8-2572/21, dtd 10.09.2021 | No Response in first tender | 22/08/2022 | |
13 | 11 | Kallyasseri | Cherukunnu | 15 | Smart AW 2021-22 ICDS/A8-2572/21, dtd 07.06.2021 | Based on soil investigation report, pile foundations upto a depth of 18 m needed. Estimate amount comes to be 53 lakhs. Got AS for 34 lakhs only. So submitted for revised AS. | 23/8/22 | |
14 | 12 | Kallyasseri | Cherukunnu | 16 | Smart AW 2021-22 ICDS/A8-2572/21, dtd 07.06.2021 | Applied for KCZMA approval as the available site comes under CRZ. | 23/8/22 | |
15 | 13 | Vazhoor | Chirakkadavu | 14 | Smart AW 2021-22 ICDS/A8-7935/21, dtd 04.11.2021 | NON AVAILABILITY OF LAND | 23/08/2022 | |
16 | 14 | Nilambur Adl | Edakara | 54 | Smart AW 2021-22 ICDS/A8-2572/21, dtd 10.09.2021 | 90% Work compleeted will complete by 30.11.2022 | 26/08/2022 | Fininshing Stage |
17 | 15 | Parakkode | Enaadhimangalam | 42 | Smart AW 2021-22 ICDS/A8-7935/21, dtd 04.11.2021 | Tender published, opening on 28.12.2022 | 2022-12-19 | Fund allocation as per no p4-2002/22 dtd:21/11/2022 of block panchayath |
18 | 16 | Parakkode | Enaadhimangalam | 52 | Smart AW 2021-22 ICDS/A8-7935/21, dtd 04.11.2021 | Tender published, opening on 28.12.2022 | 2022-12-19 | Fund allocation as per no p4-2002/22 dtd:21/11/2022block panchayath |
19 | 17 | Kuttippuram | Iribiliyam | 39 | Smart AW 2021-22 ICDS/A8-2572/21, dtd 07.06.2021 | Work compieted with district panchayath fund. Letter given to director to change the fund to Anganvady no 6. | 27/08/2022 | |
20 | 18 | Pothencode | Kadinamkulam | 103 | Smart AW 2021-22 ICDS/A8-7935/21, dtd 04.11.2021 | Structure work completed | 27-08-2022 | Fund CFC basic grant (Total amount 25lakhs) |
21 | 19 | Parakkode | Kalanjoor | 64 | Smart AW 2021-22 ICDS/A8-7935/21, dtd 04.11.2021 | Foundation works Completed | 27.08.2022 | |
22 | 20 | Ithikkara | Kalluvathukkal | 90 | Smart AW 2021-22 ICDS/A8-2572/21, dtd 07.06.2021 | Ground floor roof slab reinforcement work started | 27.08.2022 | |
23 | 21 | Vazhoor | Kangazha | 38 | Smart AW 2021-22 ICDS/A8-2572/21, dtd 29.07.2021 | 23/08/22 | Land pocession details not yet given | |
24 | 22 | Vazhoor | Kangazha | 40 | Smart AW 2021-22 ICDS/A8-2572/21, dtd 29.07.2021 | Agreement Executed on 22.08.2022 | 23/08/22 | Work not started |
25 | 23 | Panamaram | Kaniyambatta | 66 | Smart AW 2021-22 ICDS/A8-7935/21, dtd 04.11.2021 | agreement Executed | 23/08/2022 | demolishing process of old building is going on ,survey report of building submitted to Panchayath |
26 | 24 | Vengara | Kannamangalam | 40 | Smart AW 2021-22 ICDS/A8-2572/21, dtd 07.06.2021 | Estimate Preparation | 27/08/2022 | |
27 | 25 | Vengara | Kannamangalam | 43 | Smart AW 2021-22 ICDS/A8-2572/21, dtd 07.06.2021 | Estimate Preparation | 27/08/2022 | |
28 | 26 | Karadukka | Karadukka | 64 | Smart AW 2021-22 ICDS/A8-2572/21, dtd 12.07.2021 | work ONGOING | 26.08.2022 | UP TO PLINTH BEAM COMPLETED (KATTATHABAYAL MINI) |
29 | 27 | Karadukka | Karadukka | 67 | Smart AW 2021-22 ICDS/A8-2572/21, dtd 12.07.2021 | WORK ONGOING | 26.08.2022 | GROUND FLOOR STRUCTURE COMPLETED,(Kattathabayal anganwadi) |
30 | 28 | Karadukka | Karadukka | 70 | Smart AW 2021-22 ICDS/A8-2572/21, dtd 12.07.2021 | AGREEMENT EXECUTED, Not started | 26.08.2022 | Mallavara anganwadi |
31 | 29 | Karadukka | Karadukka | 73 | Smart AW 2021-22 ICDS/A8-2572/21, dtd 12.07.2021 | WORK ONGOING | 26.08.2022 | GROUND FLOOR STRUCTURE COMPLETED,(Koyakudalu anganwadi) |
32 | 30 | Karadukka | Karadukka | 86 | Smart AW 2021-22 ICDS/A8-2572/21, dtd 12.07.2021 | AGREEMENT EXECUTED, Not started | 26.08.2022 | ADUKKAM ANGANWADI |
33 | 31 | Karadukka Addl | Kuttikkol | 85 | Smart AW 2021-22 ICDS/A8-7935/21, dtd 04.11.2021 | Estimate prepared and submitted for TS | 26.08.2022 | |
34 | 32 | Kallyasseri Adl | Madayi | 99 | Smart AW 2021-22 ICDS/A8-2572/21, dtd 29.07.2021 | The approved plan is not suitable for the land available and it can not be constructed satisfying KPBR. | 26-08-2022 | New plan submitted for approval |
35 | 33 | Kasargod | Madhur | 67 | Smart AW 2021-22 ICDS/A8-937/22, dtd 30.03.2022 | Estimate under scrutiny | 26-08-2022 | |
36 | 34 | Mankada | Makkaraparamb | 77 | Smart AW 2021-22 ICDS/A8-2572/21, dtd 07.06.2021 | FOUNDATION WORK STARTED | 22.08.2022 | |
37 | 35 | Manjeswaram Addl | Mangalpady | 63 | Smart AW 2021-22 ICDS/A8-7935/21, dtd 04.11.2021 | Estimate Submitted for TS | 23.08.2022 | Estimate return from E.E for Correction |
38 | 36 | Devikulam Adl | Mankulam | 60 | Smart AW 2021-22 ICDS/A8-2572/21, dtd 19.01.2022 | Existing anganvady is unfit. The survey report for the same is being prepared. Project executed by Block Panchayath | 23.08.2022 | |
39 | 37 | Aryad | Mannacheri | 38 | Smart AW 2021-22 ICDS/A8-2572/21, dtd 07.06.2021 | Ground floor structure completed, first floor work starts | 25.08.2022 | Part bill under preparartion |
40 | 38 | Aryad | Mannacheri | 122 | Smart AW 2021-22 ICDS/A8-2572/21, dtd 07.06.2021 | First floor structure completed | 25.08.2022 | Part bill submitted |
41 | 39 | Aryad | Mannacheri | 123 | Smart AW 2021-22 ICDS/A8-2572/21, dtd 07.06.2021 | Ground floor structure completed, first floor work starts | 25.08.2022 | Part bill under preparartion |
42 | 40 | Iritty Adl | Mattannur Municipality | 79 | Smart AW 2021-22 ICDS/A8-7935/21, dtd 04.11.2021 | Work up to plinth Completed, Wall under construction | 26/08/2022 | |
43 | 41 | Sulthan Bathery | Meenangadi | 84 | Smart AW 2021-22 ICDS/A8-2572/21, dtd 10.09.2021 | Estimate Prepared. | 2022-08-23 | Estimate Prepared. |
44 | 42 | Kalpetta Adl | Meppadi | 28 | Smart AW 2021-22 ICDS/A8-7935/21, dtd 04.11.2021 | ongoing | 26/08/2022 | Sloping terrain ,difficult to work in rainy season |
45 | 43 | Karadukka Adl | Mooliyar | 1 | Smart AW 2021-22 ICDS/A8-2572/21, dtd 29.07.2021 | Work on going up to lintel level | 24/8/2022 | work |
46 | 44 | Karadukka Adl | Mooliyar | 20 | Smart AW 2021-22 ICDS/A8-2572/21, dtd 29.07.2021 | Agreement executed | 24/8/2022 | Site Boundary couldn't identify |
47 | 45 | Karadukka Adl | Mooliyar | 23 | Smart AW 2021-22 ICDS/A8-2572/21, dtd 29.07.2021 | Work on going up to plinth level | 24/8/2022 | |
48 | 46 | Sasthamkotta Adl | Mynagapally | 93 | Smart AW 2021-22 ICDS/A8-2572/21, dtd 07.06.2021 | Work on going up to first floor lintel level | 25/8/22 | |
49 | 47 | Thuneri | Nadapuram | 183 | Smart AW 2021-22 ICDS/A8-7935/21, dtd 04.11.2021 | not started | 26/08/2022 | |
50 | 48 | Chittoor Adl | Nallepilli | 49 | Smart AW 2021-22 ICDS/A8-2572/21, dtd 12.07.2021 | not started | 20/08/2022 | The land is in dispute, not prepared the estimate. Reported to the LB&ICDS office |
51 | 49 | Ochira | Ochira | 63 | Smart AW 2021-22 ICDS/A8-2572/21, dtd 07.06.2021 | First floor completed | 24/08/2022 | |
52 | 50 | Vadakara | Onchiyam | 35 | Smart AW 2021-22 ICDS/A8-7935/21, dtd 04.11.2021 | Founation work going on | 26.08.2022 | The road to the construction site was very slushy .so the materials could not be delivered in monsoon season. So delay occurs to start the work. |
53 | 51 | Vadakara | Onchiyam | 50 | Smart AW 2021-22 ICDS/A8-7935/21, dtd 04.11.2021 | Structure work ongoing . Lintel concrete completed. Side protection wall work completed. | 26.08.2022 | |
54 | 52 | Parappa Adl | Panathady | 100 | Smart AW 2021-22 ICDS/A8-2572/21, dtd 29.07.2021 | DPR Approved. Estimate Prepared and TS Obtained. | 26/08/2022 | To be tendered |
55 | 53 | Ithikkara | Paravoor Municipality | 173 | Smart AW 2021-22 ICDS/A8-2572/21, dtd 07.06.2021 | Building civil works finished.Electrical works pending | 23/08/2022 | |
56 | 54 | Ithikkara | Paravoor Municipality | 175 | Smart AW 2021-22 ICDS/A8-2572/21, dtd 07.06.2021 | Finishing works ongoing. | 23/08/2022 | |
57 | 55 | Ithikkara | Paravoor Municipality | 193 | Smart AW 2021-22 ICDS/A8-2572/21, dtd 07.06.2021 | Building civil works finished.Electrical works pending | 23/08/2022 | |
58 | 56 | Nileswaram Adl | Pilicode | 87 | Smart AW 2021-22 ICDS/A8-2572/21, dtd 29.07.2021 | Lintel level completed | 23/08/2022 | |
59 | 57 | Malappuram Adl | Pookkottor | 58 | Smart AW 2021-22 ICDS/A8-2572/21, dtd 07.06.2021 | first floor slab completed , work ongoing | 26/8/2022 | |
60 | 58 | Ponnani | Thavanur | 16 | Smart AW 2021-22 ICDS/A8-2572/21, dtd 12.07.2021 | Plinth Level work completed. | 23/08/2022 | |
61 | 59 | Thiroor | Thiroor Municipality | 25 | Smart AW 2021-22 ICDS/A8-2572/21, dtd 12.07.2021 | Structure work completed, work ongoing, will be completed on 28/02/2023 | 23/08/2022 | |
62 | 60 | TVM Urban II | Tvm Corporation | 24 | Smart AW 2021-22 ICDS/A8-2572/21, dtd 19.01.2022 | Lintel level completed | 24/08/2022 | Work Ongoig |
63 | 61 | Vellanad Adl | Uzhamalaikkal | 49 | Smart AW 2021-22 ICDS/A8-2572/21, dtd 07.06.2021 | Estimate under preparation | 26/08/2022 | |
64 | 62 | Kuttippuram | Valacherry Municipality | 19 | Smart AW 2021-22 ICDS/A8-2572/21, dtd 07.06.2021 | plastering completed, finishing works ongoing | 23/08/22 | |
65 | 63 | Vamanapuram | Vamanapuram | 22 | Smart AW 2021-22 ICDS/A8-2572/21, dtd 07.06.2021 | structure completed. plastering works ongoing | 24/08/2022 | |
66 | 64 | Vengara | Vengara | 20 | Smart AW 2021-22 ICDS/A8-2572/21, dtd 07.06.2021 | Agreement Executed | 24/08/2022 | |
67 | 65 | Vellanad Adl | Vithura | 111 | Smart AW 2021-22 ICDS/A8-2572/21, dtd 07.06.2021 | DPC approved | 26/08/2022 | |