Program/Project TitleImplementing AgencyImplementation ScheduleSectorFund SourceFunding AgencyTotal Program/ Project Cost
(PHP)
Financial Status (in PHP exact figures)Physical AccomplishmentEmployment GeneratedRemarks
7
Start Date
(mm-dd-yyyy)
End Date
(mm-dd-yyyy)
AppropriationsAllotmentObligationsDisbursementsFunding Support (%)Fund Utilization (%)Target OWPA to date (%)Actual OWPA to date (%)Slippage (%)MF
8
A. OFFICIAL DEVELOPMENT ASSISTANCE (ODA)-FUNDED PROGRAMS/ PROJECTS
9
1Philippine Rural Development Project (PRDP) Scale UpDA RFO 2Official Development Assistance (ODA) - LOANWORLD BANK, DA, P/MLGU 1,392,407,299.08 1,528,210,000.00 1,393,084,134.89 1,358,080,764.53 499,382,835.77 91.16 35.85 44.88 39.83 -5.05 566 26
10
a) Rehabilitation/Construction of Nanauatan-Lattut Farm-to-Market RoadDA RFO 211-27-2412-12-26Economic ServicesOfficial Development Assistance (ODA) - LOANWORLD BANK, DA, P/MLGU252,919,097.84257,921,000.00252,919,097.84252,919,097.83105,275,868.05 98.06 41.62 57.3942.43-14.96 80 - Severe delays occurred due to insufficient manpower and frequent equipment breakdowns. Operations were further delayed due to: 1) heavy rains, and 2) unpaid progress billing for 54 calendar days due to the absence of the MLGU Rizal Treasurer.

Despite weekly meetings, a required catch-up plan, a May 4, 2026 final warning, and an approved work suspension, the contractor did not comply. The project was terminated on June 6, 2026.
11
b) Rehabilitation of Poblacion-Labang Farm to Market RoadDA RFO 210-18-2506-11-26Economic ServicesOfficial Development Assistance (ODA) - LOANWORLD BANK, DA, P/MLGU78,147,352.7988,709,000.0078,147,352.7978,147,352.7947,363,229.83 88.09 60.61 69.4964.53-4.96 34 3 Insufficient manpower and equipment delayed stone masonry and grouted riprap works, while bad weather prompted a Work Suspension Order. The Municipal Project Management and Implementing Unit (MPMIU) subsequently directed the contractor to deploy adequate resources immediately upon work resumption to prevent further negative slippage.
12
c) Rehabilitation of Bugallon Proper-Villa Carmen-San Antonio Farm to Market Road (FMR)DA RFO 201-25-2507-06-26Economic ServicesOfficial Development Assistance (ODA) - LOANWORLD BANK, DA, P/MLGU117,612,650.00144,310,000.00117,612,650.00117,612,650.0070,967,924.90 81.50 60.34 90.3581.32-9.03 91 1 The delay was due to late manpower and equipment deployment. Following a joint National Project Coordination Office (NPCO) Regional Infrastructure Engineer (RIE) and Regional Project Coordination Office 02 (RPCO 02) inspection, the PRDP team directed the contractor to submit a catch-up plan by June 15, 2026, for the remaining two-month period. Contractor was reminded that unfinished works past the contract expiry date will incur liquidated damages.
13
d) Rehabilitation of Sta. Lucia - Sta. Catalina Farm to Market Road with BridgeDA RFO 211-22-2404-24-26Economic ServicesOfficial Development Assistance (ODA) - LOANWORLD BANK, DA, P/MLGU183,831,191.67204,279,000.00183,831,191.68183,831,191.68164,502,312.18 89.99 89.49 99.2995.63-3.66 60 1 Delayed reinforcing steel and structural concrete works caused negative slippage. During a coordination meeting with the MLGU Resident Engineer, the contractor was directed to expedite all delayed activities.
14
e) Rehabilitation of Rizal- Abra Farm to Market RoadDA RFO 211-27-2410-08-25Economic ServicesOfficial Development Assistance (ODA) - LOANWORLD BANK, DA, P/MLGU75,890,644.5377,450,000.0075,890,644.5375,890,644.5273,430,325.51 97.99 96.76 1001000.00 58 - Project completed as of Q1. The subproject was declared completed on January 26, 2026. A final joint inspection was conducted on January 28, 2026.
15
f) Rehabilitation of Sinsayon-Cabulay Farm to Market RoadDA RFO 211-27-2506-19-27Economic ServicesOfficial Development Assistance (ODA) - LOANWORLD BANK, DA, P/MLGU131,821,270.93 133,827,000.00 131,821,270.93 131,821,270.93 25,981,860.95 98.50 19.71 19.73 16.08 -3.65 900Despite positive monthly progress, overall slippage remains negative due to earlier delays in manpower and equipment deployment.
16
g) Rehabilitation/Improvement of Union-Barcolan Farm to Market RoadDA RFO 206-25-2504-10-26Economic ServicesOfficial Development Assistance (ODA) - LOANWORLD BANK, DA, P/MLGU14,323,164.20 15,000,000.00 15,000,000.00 14,323,164.20 2,171,368.62 100.00 14.48 61.41 58.33 -3.08 4619By maintaining adequate materials, manpower, and extended work hours during favorable weather, the contractor accelerated PCCP works. Weekly coordination meetings and site instructions by RPCO 02 and LGU representatives led to an augmented workforce, reducing negative slippage.
17
h) Rehabilitation/Improvement of M.H. Del Pilar - Salvacion Farm to Market RoadDA RFO 202-04-2610-21-27Economic ServicesOfficial Development Assistance (ODA) - LOANWORLD BANK, DA, P/MLGU215,332,127.14 262,700,000.00 215,332,127.14 197,739,414.42 9,689,945.73 81.97 4.50 11.28 8.93 -2.35 412Slow progress on grouted riprap and structure excavation caused negative slippage. To resolve this, weekly coordination meetings was held with the MLGU Resident Engineer and contractor staff, who were instructed to expedite works to recover the schedule.
18
j) Rehabilitation of Oscariz-Burgos-Purok Ni Bulan-Pabil FMRDA RFO 205-07-2603-30-28Economic ServicesOfficial Development Assistance (ODA) - LOANWORLD BANK, DA, P/MLGU188,367,999.98 199,754,000.00 188,367,999.98 188,367,999.98 - 94.30 - 0.81 0.37 -0.44 660Because key personnel were not deployed onsite, the contractor plans to replace the Project Manager, Project Engineer, and Materials Engineer II, requiring immediate submission of their bio-data for evaluation. RPCO 02 directed the MPMIU to issue an official reminder letter regarding deployment.
19
k) Upgrading of Agusi Farm-to-Market RoadDA RFO 206-04-2606-29-27Economic ServicesOfficial Development Assistance (ODA) - LOANWORLD BANK, DA, P/MLGU134,161,800.00 144,260,000.00 134,161,800.00 117,427,978.18 - 93.00 - 0.10 - -0.10 00No significant accomplishment was recorded during this reporting period because the contractor had only recently mobilized its resources. The contractor was directed to immediately deploy equipment and manpower to prevent negative slippage.
20
2Second Additional Financing for the Philippine Rural Development Project (AF-2)DA RFO 2--Economic ServicesOfficial Development Assistance (ODA)-0.00 - - - - - - - - 0.00 00Projects under AF-2 completed. No additional funding received under AF-2
21
3Adapting Philippine Agriculture to Climate ChangeDA RFO 2--Economic ServicesOfficial Development Assistance (ODA)-- - - - - - - - ----No funds downloaded for project implementation in the region as of the reporting period.
22
4Rebuilding agricultural livelihoods affected by multiple cyclones in Cagayan ProvinceFAONo submission during the reporting period
23
5Water District Development Sector Project (WDDSP) - Design, Supply, Construction, Installation, Testing and Commissioning of Caggay Surface Water Treatment Plant
Metro Tuguegarao Water District
01-31-23
01-31-23
05-19-25
02-21-26
Economic Services
Official Development Assistance (ODA) - LOAN
Asian Development Bank (ADB) through Local Water Utilities Administration (LWUA)
320,000,000.00 332,216,181.30 332,216,181.30 223,050,271.12 197,188,348.49 100.00 59.36 59.51 58.01 -1.50 302Total Time Extension = 490 days

(1) Suspension No. 1 = 48 days from October 21 to December 9, 2024 due to continuous rains and flooding that rendered the site inaccessible for construction activities.
(2) Extension No. 1 = 30 days, to account for weather-related disruptions—such as rains, typhoons, and flooding—experienced between April 1, 2024, and December 15, 2024. The suspension period was not included in the approved time extension.
(3) Suspension No. 2 = 120 days due to delays in the processing of Progress Billing Nos. 3 and 4.
(4) Extension No. 2= 69 days to account for weather-related disruptions—such as rains, typhoons, and flooding—experienced between December 20, 2024, and August 31, 2025.
(5) Suspension No. 3 = 33 to account for weather-related disruptions—such as rains, typhoons, and flooding—experienced between September 1, and October 31, 2025.
(6) Project Variation No. 1 = 90 days
(7) Project Variation No. 2 = 100 days
24
6Supporting Innovation in the Philippine Technical and Vocational Education and Training System (SIPTVETS) Project
TESDA RO210/03/202501/09/2026General Public ServicesOthersAsian Development Bank (ADB)163,047,336.22163,047,336.22163,047,336.22163,047,336.2270,632,106.05 100.00 43.32 82.9343.32-39.61 446Limited availability of materials;
Locally hired workers did not initially possess NC II certification upon employment resulting in Delays in meeting the required percentage of NC II-certified skilled workers."
25
7Philippine Digital Infrastructure Project (PDIP) National Broadband ProjectDICT RO2-----------------Awaiting actual downloading of funds from the Project Management Team - Central Office (the realization of project implementation in the region is based on the prioritization). As to the RNIP, the next downloading of fund for the Establishment of New GovNet in Region 2 is 2027.
26
8Philippines Health System Resilience Project (HSRP)DOHNo dataNo dataSocial ServiceOfficial Development Assistance (ODA) - Health System Resillience Project (World Bank Funded)World Bank0.00 - - - - - - - - 0.00 No dataNo dataNo funding received yet, awaiting approval of the Approved Project Cost for the eight proposed projects
27
9Health System Enhancement to Address and Limit
(HEAL) COVID-19
DOHNo dataNo dataSocial ServiceNo dataNo data0.00 - - - - - - - - 0.00 No dataNo dataNo project implemented or reported by DOH- CVCHD
28
10Disaster Risk Reduction Enhancement at the Local
Level Technical Assistance Program
DILGNo dataNo dataSocial ServiceNo dataNo dataNo project implemented or reported by DILG
29
11Rural Agro-Enterprise Partnership for Inclusive Development and Growth Project (RAPID Growth)DTIThe RAPID Growth Project is not being implemented in the region according to DTI2 per letter dated May 7, 2026.
30
B. PUBLIC PRIVATE PARTNERSHIP (PPP) FUNDED PROJECTS
31
1Baggao Water Supply Project MLGU Baggao/ ME
Sicat Construction,
Inc.
General Public ServicesPublic-Private Partnership (PPP) According to LGU Baggao, drilling is ongoing to determine sites for groundwater extraction due to inadequate data from previous identified sites.
32
C. LOCALLY-FUNDED PROGRAMS AND PROJECTS
33
a. Agricultural Development Programs and Projects
34
1Tumauini River Multi-Purpose Project (TRMP)NIA06-01-1812-31-26Economic ServicesLocally Funded Project -NIA2,777,795,045.162,777,795,045.16781,237,838.76 733,869,730.18 728,181,705.22 28.12 93.21 29.94 26.19 -3.75 721 22 All contracts for calendar years 2018 to 2024 have been completed. For calendar year 2025, there are three active contracts: one has been completed, one is ongoing, and one is currently suspended due to typhoons and heavy rainfall.
35
2Calapangan Small Reservoir Irrigation Project (CSRIP)NIA05-08-2312-31-26Economic ServicesLocally Funded Project -NIA1,060,000,000.001,060,000,000.00 1,055,558,000.00 1,000,234,015.92 471,901,229.06 99.58 44.71 52.37 54.57 2.20 232 16 For CY 2026, the total program allocation amounts to PhP210,000,000.00, distributed as follows:
Regional Office: PhP 122,034,207.68
Central Office: PhP 87,965,792.32

One (1) contract commenced, specifically the Construction of
Access Road and Ancillary Structures Leading to the Dam Site and Project Facilities.

The Construction of the Calapangan Small Reservoir Irrigation
Project and its Appurtenant Structures is ongoing, with a total
contract amount of PhP 738,453,619.84 and an original contract
duration of 1,225 calendar days, of which PhP 87,965,792.32 is
allocated under CY 2026.

The Construction of Irrigation Facilities (Main Canal, Laterals A &
B, Sublaterals A-1, A-2, and B-1), including the Supply, Delivery,
and Installation of Steel Gates for Headgates, just started on June 24, 2026. However, its implementation is being funded from the CY 2025 program allocation; consequently, no funds were
allocated under CY 2026 for the contract.
36
3Balasig Small Reservoir Irrigation Project (BSRIP) FY 2023- 50M
FY 2024- 5M
FY 2025- 0
NIA05-03-2312-31-26Economic ServicesLocally Funded Project -NIA50,000,000.0055,000,000.0055,000,000.0055,000,000.0054,673,244.56 100.00 99.41 98.811001.19 311Early completion of the following output Indicators:
- PCCP - 0.07km
- Access Road Structures- 1 unit
- Gabion Slope Protection - 56 metres
37
4Lusod Intergrated National Irrigation Project (LINIP)

FY 2023- 50M
FY 2024- 100M
FY 2025- 200M
FY 2026- 100M
NIA04-07-2312-31-26Economic ServicesLocally Funded Project -NIA450,000,000.00450,000,000.00447,779,000.00 380,368,091.94 249,628,413.52 99.51 55.75 74.78 74.40 -0.38 210 5 Two (2) new contracts are currently ongoing

Protection works- 735m
Canal Structure- 3 units
Project Facilities- 1 unit
38
b. Infrastructure Development Programs/ Projects
39
1CEZA Port Development
40
a) Retroffing and Rehabilitation Works at Port IreneCEZA09-01-2009-30-26EconomicCorporate FundCEZA400,000,000.00 400,000,000.00 400,000,000.00 395,313,171.02 395,313,171.02 100.00 98.83 100.00 98.91 -1.09 - -
41
b) Construction of Data Center / Upgrade of Telecomunication FacilityCEZA12-1-202410-30-26EconomicGAACEZA 150,000,000.00 150,000,000.00 150,000,000.00 98,214,411.56 98,214,411.56 100.00 65.48 70.62 65.96 -4.66 54 6
42
c) Repair, Rehabilitation and Maintenance of the Breakwater at Cagayan Economic Zone - Phase ICEZA6-1-202507-30-26EconomicGAACEZA 156,492,000.00 156,492,000.00 156,492,000.00 156,338,780.95 156,338,780.95 100.00 99.90 96.36 100.00 3.64 17 1 Phase 1 was completed on June 30, 2026
43
d) Dredging and Reclamation at
Port Irene
44
d.1) Dredging and Reclamation Project, Phase 2CEZA09-01-2409-30-2026EconomicGAACEZA228,844,000.00 228,844,000.00 228,844,000.00 220,132,752.23 220,132,752.23 100.00 96.19 91.78 96.36 4.58 17 2 Phase 1 was completed on March 31, 2024
45
d.2) Dredging and Reclamation at Port Irene (Phase III & IV)CEZA9-1-202511-30-2026EconomicGAACEZA 743,508,000.00 743,508,000.00 743,508,000.00 181,062,560.67 181,062,560.67 100.00 24.35 16.77 24.36 7.59 17 1
46
2
Amulung Bridge and Approaches
DPWH03-12-2406-13-25Economic ServicesLocally Funded ProjectDPWH RO2140,904,816.34 151,000,000.00 151,000,000.00 140,904,816.34 21,135,722.45 100.00 14.00 10090.84-9.16 33 5 Completion of the remaining works is delayed, pending the approval of Variation Order No. 01.
47
3Bambang By-Pass Road, Nueva Vizcaya (FY 2025)DPWH02-27-2509-24-25Economic ServicesLocally Funded ProjectDPWH RO293,333,935.49 100,000,000.00 100,000,000.00 93,333,935.49 18,527,077.50 100.00 18.53 100.00 75.06 -24.94 0 - The project has been suspended since January 2, 2026, due to RROW issues.
48
4 Tuguegarao West Diversion Road (Jct. Carig-Linao-Atulayan-Bagay-Buntun) Package 1, Cagayan (FY 2024)DPWH08-01-2403-29-25Economic ServicesLocally Funded ProjectDPWH RO2149,423,431.36 155,000,000.00 155,000,000.00 149,423,086.13 128,634,328.97 100.00 82.99 100.00 100.00 0.00 40 5Completed as of November 17, 2025.
49
5Tuguegarao-Enrile Bridge and Approaches

Construction of Bypass and
Diversion Roads Tuguegarao-
Enrile Diversion Road
(Including Tuguegarao-Enrile
Bridge and Approaches),
Phase 1
DPWH RO209-20-202311-23-2024Economic ServicesLocally Funded ProjectDPWH R02

186,874,492.51200,000,000.00200,000,000.00 186,766,374.69 138,863,808.84 100.00 69.43 100.00 100.00 0.00 no datano dataCompleted as of July 15, 2025
50
Phase 3DPWH RO204-11-202404-10-2025Economic ServicesLocally Funded ProjectDPWH R02

237,863,500.75280,000,000.00280,000,000.00 237,863,500.75 101,067,999.34 100.00 36.10 100.00 80.14 -19.86 0.000.00The project is delayed due to site inaccessibility. Contract Time Extension No. 2, which corresponds to the approved Work Suspension Order No. 2, is currently being processed. If approved, the revised expiry date will be August 8, 2026.
51
Flood Control Projects
52
6
Abulug Flood Control Projects

Construction of Canayun Flood Control Structure along Abulug-Apayao River, Barangay Canayun, Abulug, Cagayan
DPWH Cagayan 2nd DEO02-21-2510-19-25General Public ServicesLocally Funded Project - Flood Mitigation Facility

DPWH-CSDEO

96,350,935.37100,000,000.0096,500,000.0096,350,935.37 96,350,935.37 96.50 99.85 100 100.00 0.00 no data no dataCompleted as of July 25, 2025.
53
7Construction of Dugo Flood Control along Abulug River, Package 2, Barangay Dugo, Abulug, CagayanDPWH Cagayan 2nd DEO03-07-2511-2-25General Public ServicesLocally Funded Project - Flood Mitigation Facility

DPWH-CSDEO

96,349,581.49100,000,000.0096,500,000.0096,349,581.49 86,716,921.64 96.50 89.86 100 100.00 0.00 - - Completed as of June 1, 2026.
54
8Construction of Dugo Flood Control Structure along Abulug River, Barangay Dugo, Abulug, CagayanDPWH Cagayan 2nd DEO03-07-2511-2-25General Public ServicesLocally Funded Project - Flood Mitigation Facility

DPWH-CSDEO

96,349,144.71100,000,000.0096,500,000.0096,349,144.71 86,715,434.46 96.50 89.86 100 100.00 0.00 - - Completed as of June 1, 2026.
55
9Construction of Libertad Flood Control along Abulug-Apayao River, Package 2, Barangay Libertad, Abulug, CagayanDPWH Cagayan 2nd DEO02-27-2510-25-25General Public ServicesLocally Funded Project - Flood Mitigation Facility

DPWH-CSDEO

96,349,531.70100,000,000.0096,500,000.0096,349,531.70 86,714,578.53 96.50 89.86 100 100.00 0.00 no data no dataCompleted as of July 15, 2025.
56
10Construction of Libertad Flood Control Structure along Abulug-Apayao River, Package 1, Barangay Libertad, Abulug, CagayanDPWH Cagayan 2nd DEO02-21-2510-19-25General Public ServicesLocally Funded Project - Flood Mitigation Facility

DPWH-CSDEO

96,349,818.22100,000,000.0096,500,000.0096,349,818.22 96,349,818.22 96.50 99.84 100 100.00 0.00 no data no dataCompleted as of July 15, 2025.
57
11Construction of Santo Tomas Flood Control along Abulug-Apayao River, Package 2, Barangay Sto. Tomas, Abulug, CagayanDPWH Cagayan 2nd DEO02-21-2510-19-25General Public ServicesLocally Funded Project - Flood Mitigation Facility

DPWH-CSDEO

95,535,102.35100,000,000.0096,500,000.0095,535,102.35 77,383,432.91 96.50 80.19 100 100.00 0.00 no data no dataCompleted as of November 28, 2025.
58
12Construction of Bank Protection Structure along Guiddam River, Guiddam, Abulug,CagayanDPWH Cagayan 2nd DEO04-11-259-27-25General Public ServicesLocally Funded Project - Flood Mitigation Facility

DPWH-CSDEO

16,688,705.7517,652,000.0017,034,180.0016,688,705.75 15,186,723.95 96.50 89.15 100 100.00 0.00 no data no dataCompleted as of July 15, 2025.
59
13Construction of Canayun Flood Control along Abulug-Apayao River, Package 2, Barangay Canayun, Abulug, CagayanDPWH Cagayan 2nd DEO02-21-2510-19-25General Public ServicesLocally Funded Project - Flood Mitigation Facility

DPWH-CSDEO

96,395,395.99100,000,000.0096,500,000.0096,395,395.9977,136,039.10 96.50 79.93100 100.00 0.00 - - Completed as of May 15, 2026.
60
14Construction of Abulug River Revetment 9 along Abulug River, Dugo, Abulug, CagayanDPWH Cagayan 2nd DEO06-11-252-6-26General Public ServicesLocally Funded Project - Flood Mitigation Facility

DPWH-CSDEO

96,299,249.05100,000,000.0096,500,000.0096,299,249.05 86,669,324.15 96.50 89.81 100 100.00 0.00 no data no dataCompleted as of January 31, 2026.
61
15Construction of Alannay Flood Control Structure along Zinundungan River, Lasam, CagayanDPWH Cagayan 2nd DEO03-07-259-16-25General Public ServicesLocally Funded Project - Flood Mitigation Facility

DPWH-CSDEO

48,935,000.0150,000,000.0049,000,000.0048,935,000.01 21,657,949.42 98.00 44.20 100 100.00 0.00 - - Completed as of May 15, 2026.
62
16Construction of Malinta Flood Control Structure along Zinundungan River, Barangay Malinta, Lasam, CagayanDPWH Cagayan 2nd DEO02-28-259-9-25General Public ServicesLocally Funded Project - Flood Mitigation Facility

DPWH-CSDEO

48,973,756.0150,000,000.0049,000,000.0048,973,756.01 39,758,876.39 98.00 81.14 100 100.00 0.00 no data no dataCompleted as of October 15, 2025.
63
17Construction of Flood Control Structure along Cagayan River, Package 2, Barangay Aggunetan, Lasam, CagayanDPWH Cagayan 2nd DEO02-21-2510-19-25General Public ServicesLocally Funded Project - Flood Mitigation Facility

DPWH-CSDEO

96,264,699.87100,000,000.0096,500,000.0096,264,699.87 86,638,229.88 96.50 89.78 100 100.00 0.00 no data no dataCompleted as of March 31, 2026.
64
18Construction of Sanchez Mira Flood Control Structure along Sanchez Mira River, Package 1, Sanchez Mira, CagayanDPWH Cagayan 2nd DEO02-21-259-26-25General Public ServicesLocally Funded Project - Flood Mitigation Facility

DPWH-CSDEO

71,997,432.1475,000,000.0072,375,000.0071,997,432.14 58,320,432.07 96.50 80.58 100 100.00 0.00 no data no dataCompleted as of September 26, 2025.
65
19Construction of Sicatna River Control along Chico River, Package 1, Barangay Sicatna, Piat, CagayanDPWH Cagayan 2nd DEO02-21-259-28-25General Public ServicesLocally Funded Project - Flood Mitigation Facility

DPWH-CSDEO

72,274,996.9675,000,000.0072,375,000.0072,274,996.96 59,551,588.43 96.50 82.28 100 100.00 0.00 no data no dataCompleted as of March 31, 2026.
66
20Construction of Tuguegarao Circumferential Dike Road, Tuguegarao City, Cagayan - Package 4 (FY2024)DPWH RO203-12-246-23-25Economic ServicesLFPDPWH RO2183,025,826.31200,000,000.00200,000,000.00183,025,826.31 173,876,124.46 100.00 86.94 100 100.00 0.00 no data no dataCompleted as of September 02, 2025.
67
Phase 3(FY 2025)DPWH RO203-17-259-23-25Economic ServicesLFPDPWH RO277,098,486.6180,000,000.0080,000,000.0077,098,486.6111,564,772.99 100.00 14.46100 48.13 -51.87 no data no dataThe project has been suspended since January 27, 2026, due to plan revisions.
• Reason for plan revision: The realignment that occurred during the previous phase was not reflected in the 2025 Detailed Engineering Design (DED). Additionally, the site lacks a drainage outlet; therefore, a drainage pipe is proposed to provide an exit for the water.
68
21Health Facilities Enhancement Program (HFEP, FY 2022-2026)
69
a) HFEP 2022 LGU/ CVCHD20222026Social servicesLocally Funded Project

DOH-CVCHD5,000,000.005,000,000.005,000,000.005,000,000.003,476,751.73 100.00 69.54 80.00 80.00 0.00 no data no dataAs of this reporting period, of the 59 projects under the HFEP 2022, 58 were already completed. One project (Completion of Sto Tomas Super Health Center) is currently at 80 percent completion rate.
70
b) HFEP 2023LGU/ CVCHD20232026Social servicesLocally Funded Project

DOH-CVCHD56,000,000.0056,000,000.0056,000,000.0056,000,000.0010,200,000.00 100.00 18.21 75.8975.890.00 no data no dataAs of this reporting period, of the 110 projects under the HFEP 2023, 107 were already completed. Two (Nagtipunan and Quirino Provincial Medical Center) are ongoing while funding for one project (Diura BHS) was reverted to the National Treasury.
71
c) HFEP 2024LGU/ CVCHD20242026Social servicesLocally Funded Project

DOH-CVCHD73,390,000.0073,500,000.0073,305,000.0071,684,085.8535,912,862.88 99.73 48.99 37.2137.210.00 no data no dataAs of this reporting period, of the 75 projects under the HFEP 2024, 28 were already completed, 47 are ongoing. Out of the 47 ongoing projects, three are substantially completed and awaiting final billing.
72
c) HFEP 2025LGU/ CVCHD20252026Social servicesLocally Funded Project

DOH-CVCHD11,238,044.4115,000,000.0014,700,000.0011,238,020.141,343,198.70 98.00 - 96.2293.123.10 no data no dataAs of this reporting period, of the 4 projects under the HFEP 2025, 3 are ongoing and 1 project (Completion/Upgrading/Repair of Burgos Rural Health Unit) is already completed
73
22DOT-DPWH Convergence Program (2024-2025)DPWH2-15-202312-05-2024Economic ServicesLocally Funded ProjectDPWH RO2 401,141,500.58 370,000,000.00 362,635,000.00 354,635,924.42 170,315,979.34 98.01 46.97 64.86 54.97 - 9.89 69 1
74
23Construction/ Improvement of Access Roads Leading to Trades, Industries and Economic Zones (Roads Leveraging Linkages for Industry and Trade Infrastructure Program - ROLL-IT)DPWH02-15-202302-06-2025Economic ServicesLocally Funded ProjectDPWH RO2 249,624,806.56 238,370,000.00 234,142,600.00 230,024,935.96 87,728,002.09 98.23 37.47 91.29 82.32 -8.97 121 9
75
24Alicia-Angadanan-San Guillermo-Cauayan City-Naguilian Alternate Route, San Guillermo

Package 1, Isabela (P00801533LZ)
DPWH RO203-31-2511-26-25Economic ServicesLFPDPWH RO2115,523,684.02 122,900,000.00 122,900,000.00 115,523,684.02 46,229,704.82 100.00 37.62 100.00 80.69 -19.31 - - The project has been suspended since May 5, 2026, due to an obstruction at the project site.
76
25Aritao-Quirino Road
- Package 1, Quirino Aglipay, Quirino (P00914998LZ-CW1)
DPWH RO203-17-259-20-25Economic ServicesLFPDPWH RO272,304,702.69 75,000,000.00 75,000,000.00 72,304,702.69 43,968,468.31 100.00 58.62 100.00 100.00 0.00 - - Completed on November 29, 2025
77
26Aritao-Quirino Road, Nueva Vizcaya (Phase II)DPWH RO203-17-259-23-25Economic ServicesLocally Funded ProjectDPWH RO276,019,992.24 78,881,000.00 78,881,000.00 76,019,992.24 26,614,034.71 100.00 33.74 89.86 79.42 -10.44 - - The negative slippage is attributed to Proposed Variation Order No. 1 (Plan Revision).
Reason for revision: Solid rock was noted in intermittent sections from Sta. 4+120.00 to Sta. 4+520.00.
78
Cagayan Bridge Projects for Economic Development
79
27Tuguegarao - Solana Bridge and Approaches, Package 1, 2025DPWH04-10-2503-05-26
06-19-26
General Public ServicesLocally Funded ProjectDPWH RO2141,706,353.54 150,000,000.00 150,000,000.00 141,706,353.54 21,255,953.03 100.00 14.17 100.00 50.90 -49.10 0 - The project is delayed due to unfavorable weather conditions. Contract Time Extension No. 8 is currently being processed; if approved, the revised expiry date would be July 23, 2026
80
Package 2, FY 2025DPWH04-10-2503-05-26
06-19-26
General Public ServicesLocally Funded ProjectDPWH RO2141,706,325.34 150,000,000.00 150,000,000.00 141,706,325.34 21,255,948.80 100.00 14.17 100.00 49.75 -50.25 0 - The project is delayed due to unfavorable weather conditions. Contract Time Extension No. 8 is currently being processed; if approved, the revised expiry date would be July 23, 2026
81
Package 2, FY 2024DPWH04-11-2404-10-25
03-25-26
General Public ServicesLocally Funded ProjectDPWH RO2269,862,556.29280,000,000.00280,000,000.00269,862,556.29 143,760,067.04 100.00 51.34 100 100.00 0.00 0 - The project was completed on May 30, 2026.
82
28Pinacanauan Bridge 2

Package 2, FY 2023
DPWH RO205-25-2311-18-24Economic ServicesLocally Funded ProjectDPWH RO2285,919,061.33300,000,000.00300,000,000.00285,919,061.33 214,872,200.26 100.00 71.62 100 78.28 -21.72 The project is recommended for termination. Onsite works have been stopped.Termination documents have been processed and are awaiting formal approval.
83
Package 2, FY 2024DPWH RO204-11-202404-10-2025Economic ServicesLocally Funded ProjectDPWH RO2264,489,713.09280,000,000.00280,000,000.00264,489,713.09 70,205,648.58 100.00 25.07 100 63.54 -36.46 The project has been suspended since March 16, 2026, while awaiting the completion and construction of other prerequisite phases.
84
FY 2025DPWH RO204-10-202503-04-2026General Public ServicesLocally Funded ProjectDPWH RO2139,598,578.83150,000,000.00150,000,000.00 139,598,578.83 20,939,786.82 100.00 13.96 81.61 57.83 -23.78 The project is delayed due to unfavorable weather conditions. Variation Order No. 1, due to a revision of plan, is being processed.
85
Package 2, FY 2025DPWH RO212-05-202504-24-2027Economic ServicesLocally Funded Project -DPWH RO3264,010,208.54300,000,000.00300,000,000.00 264,010,208.54 - 100.00 - 34.65 - -34.65 The project has been suspended since February 12, 2026, while awaiting the completion and construction of other prerequisite phases.
86
29Alcala Bridge

Construction of Bypass and
Diversion Roads – Alcala-
Santo Niño-Lasam Road,
Package 1 (FY2023)
DPWH RO209-21-202305-27-2024 03-03-26Economic ServicesLocally Funded ProjectDPWH RO266,811,501.2775,000,000.0075,000,000.00 66,783,471.73 59,822,424.71 100.00 79.76 100.00 96.85 -3.15 no data no data
87
Package 2, FY 2023
DPWH RO209-27-202310-03-2024Economic ServicesLocally Funded ProjectDPWH RO2113,275,546.20120,000,000.00120,000,000.00113,275,546.20 27,324,587.86 100.00 22.77 99.00 38.47 -60.53 no data no dataThe project is delayed due to unfavorable weather conditions.
88
Package 1, FY 2024DPWH RO203-12-202411-19-2025Economic ServicesLocally Funded ProjectDPWH-RO2

192,891,064.09200,000,000.00200,000,000.00192,896,059.00 45,228,359.73 100.00 22.61 100.00 39.72 -60.28 - - The project is delayed due to unfavorable weather conditions. Contract Time Extension No. 14 is being processed; if approved, the revised expiry date will be July 2, 2026. A Work Suspension Order was also issued due to a revision of the plan caused by an unforeseen obstruction (a wooden log) underneath Pier 3.
89
Package 2, FY 2024DPWH RO202-14-202509-28-2025Economic ServicesLocally Funded ProjectDPWH RO228,850,109.3730,000,000.0030,000,000.0028,850,109.37 4,327,516.41 100.00 14.43 100.00 4.88 -95.12 0.00 - The project has been suspended since March 3, 2025, pending the completion of its prerequisite phases
90
Construction of Bypass and
Diversion Roads – Alcala-
Santo Niño-Lasam Road,
Package 1 (25B00041)
DPWH RO204-03-2502-07-26Economic ServicesLocally Funded ProjectDPWH RO270,203,914.50 75,000,000.00 75,000,000.00 70,203,914.50 10,530,587.18 100.00 14.04 100.00 0.15 -99.85 - - The project has been suspended since April 18, 2025, pending the completion of other prerequisite phases.
91
Daang Maharlika Improvement: Bridges
92
30Replacement of Permanent Weak Bridge - Minanga Br. (B01129LZ) along Maharlika Highway Tumauini, Isabela (FY2025)DPWH RO203-07-2506-27-26Economic ServicesLFPDPWH RO2241,150,001.36 250,000,000.00 250,000,000.00 241,150,001.36 36,172,500.20 100.00 14.47 76.83 18.62 -58.21 - - The project is delayed due to the mechanical breakdown of the drilling equipment, which resulted in minimal accomplishment.
93
31Widening of Permanent Bridges - Malalam Br. (B01121LZ) Along Maharlika Highway Ilagan City, Isabela (FY2025)DPWH RO203-17-2505-10-26Economic ServicesLFPDPWH RO2253,509,603.37 271,409,000.00 271,409,000.00 253,509,603.37 104,001,207.20 100.00 38.32 95.64 90.93 -4.71 - -
94
32 Widening of Permanent Bridges - Namuac Br. (B04427LZ) along Manila North Rd, Sanchez Mira, CagayanDPWH RO203-17-2501-12-26Economic ServicesLFPDPWH-RO2

114,892,835.42 120,000,000.00 120,000,000.00 114,892,835.42 17,233,925.31 100.00 14.36 95.77 65.64 -30.13 - - The project is delayed due to unfavorable weather conditions.
95
33 Widening of Permanent Bridges - Bangan Br.2 (B04426LZ) Along Manila North Rd located at Sanchez Mira, CagayanDPWH RO206-23-2512-25-25Economic ServicesLFPDPWH-RO2

14,202,665.39 15,000,000.00 15,000,000.00 14,202,665.39 0.00 100.00 0.00 100.00 70.58 -29.42 no data no dataThe project has been suspended since April 1, 2026, due to plan revision.
96
34 Widening of Permanent Bridges - Lucban br. (b04771lz) along Manila North RoadDPWH RO203-17-2505-02-26General Public ServicesLFPDPWH-RO2

160,696,842.22 167,705,000.00 167,705,000.00 160,696,842.22 24,104,526.33 100.00 14.37 62.53 60.71 -1.82 - - The project is delayed due to unfavorable weather conditions.
97
35Replacement of Permanent Weak Bridges: Nagantatapian Bridge (B01094LZ) along Maharlika Highway (Cagayan Valley Rd) (Phase II)DPWH RO203-07-2509-15-25General Public ServicesLFPDPWH-RO2

14,370,965.98 15,000,000.00 15,000,000.00 14,370,965.98 2,156,245.49 100.00 14.37 100.00 88.80 -11.20 no data no dataThe project has been suspended since March 04, 2026, due to plan revision.
98
36Widening Of Permanent Bridges Caroronan Br. (B04773LZ) Along Manila North Rd. Aparri, CagayanDPWH RO206-23-2501-24-26Economic ServicesLFPDPWH-R02

22,069,473.46 25,000,000.00 25,000,000.00 22,069,473.46 0.00 100.00 0.00 100.00 0.53 -99.47 no data no dataThe project has been suspended since July 16, 2025, due to obstructions (houses and a utility pole).
99
37Widening of Permanent Bridges - Pattung Br. (B04774LZ) along Manila North Rd Aparri, CagayanDPWH RO207-11-2502-11-26Economic ServicesLFPDPWH-RO2

22,926,914.74 25,000,000.00 25,000,000.00 22,926,914.74 3,439,037.21 100.00 13.76 100.00 2.11 -97.89 no data no dataThe project has been suspended since August 27, 2025, due to obstructions (houses and utility posts).
100
38Construction of New Bridges - Claveria Viaduct along Maharlika North RdDPWH RO203-07-2505-28-26Economic ServicesLFPDPWH-R02

282,757,606.91 300,000,000.00 300,000,000.00 282,757,606.91 0.00 100.00 0.00 100.00 64.59 -35.41 - - The project has been suspended since December 9, 2025, due to plan revision.
101
39Replacement of Permanent Weak Bridge Maluyo Br. 3 (B02009LZ) along Bangag - Magapit Road, Allacapan, CagayanDPWH RO203-17-2510-28-25Economic ServicesLFPDPWH-RO2

45,856,603.98 48,000,000.00 48,000,000.00 45,856,603.98 22,920,213.94 100.00 47.75 100.00 72.00 -28.00 no data no dataThe project has been suspended since February 13, 2026, due to plan revisions.
102
40Rehabilitation/Major Repair of Permanent Bridges - Balasig Br. (B01134LZ) along Maharlika HighwayDPWH RO206-23-25
06-23-25
09-13-25
10-26-25
Economic ServicesLFPDPWH-R02

5,615,721.00 6,000,000.00 6,000,000.00 5,615,721.00 0.00 100.00 0.00 100.00 100.00 0.00 no data no dataCompleted as of February 19, 2026.
103
41Widening of Permanent Bridges, Guising Br. (B01092LZ) Along Maharlika Highway (Cagayan Valley Rd.)DPWH RO207-10-2505-09-26Economic ServicesLFPDPWH-R02

67,485,460.79 72,096,000.00 72,096,000.00 67,485,460.79 10,122,819.12 100.00 14.04 100.00 0.38 -99.62 - - The project has been suspended since July 29, 2025, due to obstructions (utility poles).
104
Daang Maharlika Improvement: Roads
105
42Design and Build (DB) Construction of Missing Link/New Roads: Manila North Road (Jct. Bangag – Paruddun Section) – Jct. Cagayan Valley Road (Camalaniugan) Cagayan ProvinceDPWH RO205-10-2002-24-26Economic ServicesLFPDPWH RO22,028,562,304.91 2,436,960,000.00 2,147,656,000.00 2,095,872,721.28 1,991,081,620.93 100.00 81.70 100.00 99.95 -0.05 no data no data