5 | ||||||||||||||||||||||||||
6 | PROGRAM OR PROJECT | LOCATION | TOTAL COST | DISBURSEMENTS | DATE STARTED | TARGET COMPLETION DATE | PROJECT STATUS | No. of Extensions, if any | REMARKS | |||||||||||||||||
7 | Total Disbursements from the previous quarter | Disbursements for the quarter | % of Completion | Total Cost Incurred to Date | ||||||||||||||||||||||
8 | DOTr - PANGLAO BOHOL INTERNATIONAL AIRPORT PROJECT | Panglao, Bohol | 159,073,600.00 | 152,712,560.81 | 83,029.00 | 96.05% | 152,795,589.81 | on-going project | ||||||||||||||||||
9 | ANIMAL RELIEF AND OPERATION FROM THE BUREAU OF ANIMAL INDUSTRY | N/A | 1,000,000.00 | 995,990.50 | - | 99.60% | 995,990.50 | project completed - remaining fund balance represents earmarked obligation payable to supplier but not yet paid | ||||||||||||||||||
10 | DOH - SUBSIDY FOR THE PURCHASE OF REPRODUCTIVE HEALTH COMMODITIES AND CONDUCT OF FAMILY PLANNING ACTIVITIES | N/A | 2,368,881.00 | 2,313,100.95 | - | 97.65% | 2,313,100.95 | Trust Fund account still for reconciliation | ||||||||||||||||||
11 | DOH - REPAIR/ENHANCEMENT OF HEALTH FACILITY OF CATIGBIAN DISTRICT HOSPITAL | Catigbian | 100,000.00 | - | - | 0.00% | - | on-going project | ||||||||||||||||||
12 | DOH - REPAIR/ENHANCEMENT OF HEALTH FACILITY OF CONG. NATALIO CASTILLO MEMORIAL HOSPITAL | Loon | 100,000.00 | 73,961.89 | - | 73.96% | 73,961.89 | on-going project | ||||||||||||||||||
13 | DOH - REPAIR/ENHANCEMENT OF HEALTH FACILITY OF CONG. SIMEON TORIBIO MEMORIAL HOSPITAL | Carmen | 100,000.00 | 93,963.08 | - | 93.96% | 93,963.08 | on-going project | ||||||||||||||||||
14 | DOH - REPAIR/ENHANCEMENT OF HEALTH FACILITY OF GARCIA MEMORIAL PROVINCIAL HOSPITAL | Talibon | 100,000.00 | 99,980.00 | - | 99.98% | 99,980.00 | project completed; remaining mimimal fund balance for return to the NGA | ||||||||||||||||||
15 | DOH - REPAIR/ENHANCEMENT OF HEALTH FACILITY OF PROV'L. HEALTH OFFICE | Tagbilaran City, Bohol | 700,000.00 | 464,000.00 | - | 66.29% | 464,000.00 | on-going project | ||||||||||||||||||
16 | DOH - REPAIR/ENHANCEMENT OF HEALTH FACILITY OF TEODORO B. GALAGAR DISTRICT HOSPITAL | Jagna | 200,000.00 | 141,956.50 | - | 70.98% | 141,956.50 | on-going project | ||||||||||||||||||
17 | DOH - PERFORMANCE BASED GRANT OF THE NATIONAL TUBERCULOSIS ELIMINATION PROGRAM | N/A | 1,200,000.00 | - | - | 0.00% | - | on-going program | ||||||||||||||||||
18 | DOH - TRAINING COURSES ON LEPROSY AND INTEGRATED DISABILITY MANAGEMENT | N/A | 725,000.00 | 113,439.00 | - | 15.65% | 113,439.00 | on-going program | ||||||||||||||||||
19 | DOH - ESTABLISHMENT AND OPERATION OF PROVINCIAL EMERGENCY OPERATION | N/A | 600,000.00 | 210,110.95 | - | 35.02% | 210,110.95 | on-going program | ||||||||||||||||||
20 | DOH - PERFORMANCE BASED GRANT TO THE NATIONAL RABIES PREVENTION & CONTROL PROGRAM | N/A | 150,000.00 | - | - | 0.00% | - | on-going program | ||||||||||||||||||
21 | FINANCIAL ASSISTANCE FOR MARIBOJOC HOSPITAL | Maribojoc | 5,000,000.00 | 4,994,571.08 | - | 99.89% | 4,994,571.08 | project completed: remaining fund for return to source agency | ||||||||||||||||||
22 | DOH - MEDICAL ASSISTANCE PROGRAM (MAP) - CATIGBIAN DISTRICT HOSPITAL | Catigbian | 2,794,416.57 | 2,793,827.09 | - | 99.98% | 2,793,827.09 | on-going program | ||||||||||||||||||
23 | DOH - MEDICAL ASSISTANCE PROGRAM (MAP) - CONG. NATALIO P. CASTILLO SR. MEMORIAL HOSPITAL | Loon | 2,218,416.57 | 2,168,583.75 | 48,826.00 | 99.95% | 2,217,409.75 | on-going program | ||||||||||||||||||
24 | DOH - CONSULTANCY SERVICES GEOTECH EVALUATION AND STRUCTURAL PLAN PREPARATION (LOON HOSPITAL BUILDING)) | Loon | 300,000.00 | - | - | 0.00% | - | Trust Fund account for verification | ||||||||||||||||||
25 | DOH - MEDICAL ASSISTANCE PROGRAM ( MAP) - PRES. CARLOS P. GARCIA MUNICIPAL HOSPITAL | Pitogo | 6,335,975.00 | 219,761.40 | 33,937.50 | 4.00% | 253,698.90 | on-going program | ||||||||||||||||||
26 | DOH - MEDICAL ASSISTANCE PROGRAM (MAP) - CLARIN COMMUNITY HOSPITAL | Clarin | 700,000.00 | 700,000.00 | - | 100.00% | 700,000.00 | on-going program | ||||||||||||||||||
27 | DOH - MEDICAL ASSISTANCE PROGRAM (MAP) -FRANCISCO DAGOHOY MUNICIPAL HOSPITAL | Dagohoy | 574,978.58 | 536,943.60 | - | 93.38% | 536,943.60 | on-going program | ||||||||||||||||||
28 | DOH - MEDICAL ASSISTANCE PROGRAM (MAP) -CANDIJAY COMMUNITY HOSPITAL | Candijay | 5,176,916.57 | 4,094,318.34 | - | 79.09% | 4,094,318.34 | on-going program | ||||||||||||||||||
29 | DOH - MEDICAL ASSISTANCE PROGRAM (MAP) - GARCIA MEMORIAL PROVINCIAL HOSPITAL | Talibon | 3,550,000.00 | 2,456,491.20 | 797,006.71 | 91.65% | 3,253,497.91 | on-going program | ||||||||||||||||||
30 | DOH - MEDICAL ASSISTANCE PROGRAM (MAP) -TEODORO B. GALAGAR DISTRICT HOSPITAL | Jagna | 4,966,816.57 | 4,286,753.68 | - | 86.31% | 4,286,753.68 | on-going program | ||||||||||||||||||
31 | DOH - MEDICAL ASSISTANCE PROGRAM (MAP) - CONG. SIMEON TORIBIO MEMORIAL HOSPITAL | Carmen | 6,218,866.57 | 4,564,870.49 | 370,147.55 | 79.36% | 4,935,018.04 | on-going program | ||||||||||||||||||
32 | DOH - MEDICAL ASSISTANCE PROGRAM (MAP) - MARIBOJOC COMMUNITY HOSPITAL | Maribojoc | 74,978.57 | - | - | 0.00% | - | on-going program | ||||||||||||||||||
33 | DOH - TSEKAP SURGICAL CARAVAN | N/A | 199,845.00 | 67,450.00 | - | 33.75% | 67,450.00 | on-going program | ||||||||||||||||||
34 | DOH - IMPLEMENTATION OF COMMUNITY BASED TREATMENT AND REHABILITATION PROGRAM | N/A | 999,840.00 | 484,800.00 | - | 48.49% | 484,800.00 | on-going program | ||||||||||||||||||
35 | DOH - PERFORMANCE BASED GRANT - NATIONAL DENGUE PREVENTION AND CONTROL PROGRAM ACTIVITIES | N/A | 250,000.00 | - | - | 0.00% | - | on-going program | ||||||||||||||||||
36 | DOH - PERFORMANCE BASED GRANT TO SOCIAL HYGIENE CLINIC AND NASPCP PROGRAMS OF LGU | N/A | 300,000.00 | - | - | 0.00% | - | on-going program | ||||||||||||||||||
37 | DOH - LIFESTYLE RELATED PREVENTION AND CONTROL PROGRAM (NCD MAINTENANCE MEDS) | N/A | 1,621,970.00 | 1,206,559.75 | - | 74.39% | 1,206,559.75 | on-going program | ||||||||||||||||||
38 | KOREA FOUNDATION BOHOL CRISIS INTERVENTION CENTER | N/A | 178,921.50 | 173,849.90 | - | 97.17% | 173,849.90 | Trust Fund account still for reconciliation | ||||||||||||||||||
39 | DOH - MATERNAL, NEONATAL, CHILD HEALTH AND NUTRITION | N/A | 12,564,238.69 | 10,039,901.50 | - | 79.91% | 10,039,901.50 | Trust Fund account still for reconciliation | ||||||||||||||||||
40 | DOH - START-UP FUNDS FOR THE PROVINCIAL INVESTMENT PLAN FOR HEALTH (PIPH) | N/A | 23,841,352.80 | 10,450,056.79 | 4,072,118.20 | 60.91% | 14,522,174.99 | on-going program; total cost still for reconciliation | ||||||||||||||||||
41 | DILG - BOHOL EARTHQUAKE ASSISTANCE PROGRAM | N/A | 2,389,494,190.00 | 2,383,016,015.93 | 6,478,174.07 | 100.00% | 2,389,494,190.00 | project completed; remaining fund balance returned to source agency already | ||||||||||||||||||
42 | FINANCIAL ASSISTANCE FOR ROLL-OUT STRATEGY OF THE LGU DISASTER PREPAREDNESS MANUALS | N/A | 250,000.00 | 164,700.00 | - | 65.88% | 164,700.00 | Trust Fund account still for reconciliation | ||||||||||||||||||
43 | DPWH - SLRF-MVUC GUINDULMAN MAYUGA-LOMBOG ROAD | Guindulman | 21,614,662.00 | 15,092,848.08 | - | 69.83% | 15,092,848.08 | on-going project | ||||||||||||||||||
44 | DBM - LGSF CONSTRUCTION OF MULTI-PURPOSE BUILDING AT CONG. PABLO MALASARTE NATIONAL HIGHSCHOOL | Cabad, Balilihan | 10,000,000.00 | 573,864.63 | - | 5.74% | 573,864.63 | Trust Fund account still for reconciliation | ||||||||||||||||||
45 | DILG - LGSF ( INTEGRATED COMMUNITY FOOD PRODUCTION) | Cortes | 4,200,000.00 | 3,806,549.50 | - | 90.63% | 3,806,549.50 | Trust Fund account still for reconciliation | ||||||||||||||||||
46 | PROVINCIAL ROAD MANAGEMENT FACILITY PRMF Project | N/A | 81,355,021.02 | 79,772,489.44 | - | 98.05% | 79,772,489.44 | Trust Fund account still for reconciliation | ||||||||||||||||||
47 | PHILIPPINE RURAL DEVELOPMENT PROJECT - PRDP (EQUITY) | N/A | 77,868,974.14 | 49,512,734.24 | 51,276.08 | 63.65% | 49,564,010.32 | LGU share for PRDP on-going projects | ||||||||||||||||||
48 | PRDP - REHABILITATION OF ALEGRIA - BUGHO FMR (LP) | Loboc, Bohol | 43,019,100.59 | 43,019,100.58 | - | 100.00% | 43,019,100.58 | on-going project; fund downloaded is based on WIP billings | ||||||||||||||||||
49 | PRDP - REHABILITATION OF ALEGRIA - BUGHO FMR (GOP) | Loboc, Bohol | 5,377,387.57 | 5,377,387.57 | - | 100.00% | 5,377,387.57 | on-going project; fund downloaded is based on WIP billings | ||||||||||||||||||
50 | PRDP - COCO BASED PRODUCTION AND MARKETING ENTERPRISE- LOON, BOHOL (LP) | Loon, Bohol | 480,000.00 | 480,000.00 | - | 100.00% | 480,000.00 | on-going project; waiting for the liquidaton report from the recipient proponent group | ||||||||||||||||||
51 | PRDP - COCO BASED PRODUCTION AND MARKETING ENTERPRISE- LOON, BOHOL (GOP) | Loon, Bohol | 160,000.00 | 160,000.00 | - | 100.00% | 160,000.00 | on-going project; waiting for the liquidaton report from the recipient proponent group | ||||||||||||||||||
52 | PRDP - BOHOL DAIRY PROCESSING AND MARKETING- UBAY, BOHOL (LP) | Ubay, Bohol | 4,372,200.00 | 4,208,332.80 | 163,867.20 | 100.00% | 4,372,200.00 | completed project: remaining fund returned to source agency already | ||||||||||||||||||
53 | PRDP - BOHOL DAIRY PROCESSING AND MARKETING- UBAY, BOHOL (GOP) | Ubay, Bohol | 1,457,400.00 | 1,402,777.60 | 54,622.40 | 100.00% | 1,457,400.00 | completed project: remaining fund returned to source agency already | ||||||||||||||||||
54 | PRDP - REHABILITATION OF DEL CARMEN WESTE VIA TAGUBAS (LP) | Balilihan, Bohol | 22,172,102.79 | 22,172,102.08 | - | 100.00% | 22,172,102.08 | project completed - remaining minimal fund balance represents payable to contractor due to overrecoupment | ||||||||||||||||||
55 | PRDP - REHABILITATION OF DEL CARMEN WESTE VIA TAGUBAS (GOP) | Balilihan, Bohol | 2,771,512.85 | 2,771,512.76 | - | 100.00% | 2,771,512.76 | project completed - remaining minimal fund balance represents payable to contractor due to overrecoupment | ||||||||||||||||||
56 | PRDP - VIRGIN COCONUT OIL (VCO) PROCESSING AND MARKETING ENTERPRISE (LP) | Jagna, Bohol | 2,046,000.00 | 1,950,600.00 | 95,400.00 | 100.00% | 2,046,000.00 | project completed; remaining fund returned to source agency already | ||||||||||||||||||
57 | PRDP - VIRGIN COCONUT OIL (VCO) PROCESSING AND MARKETING ENTERPRISE (GOP) | Jagna, Bohol | 682,000.00 | 650,200.00 | 31,800.00 | 100.00% | 682,000.00 | project completed; remaining fund returned to source agency already | ||||||||||||||||||
58 | PRDP - VIRGIN COCONUT OIL (VCO) PROCESSING AND MARKETING ENTERPRISE - CIVIL WORKS (LP) | Jagna, Bohol | 2,242,087.58 | 2,242,087.58 | - | 100.00% | 2,242,087.58 | project completed; remaining fund returned to source agency already | ||||||||||||||||||
59 | PRDP - VIRGIN COCONUT OIL (VCO) PROCESSING AND MARKETING ENTERPRISE CIVIL WORKS - (GOP) | Jagna, Bohol | 747,362.53 | 742,627.97 | 4,734.56 | 100.00% | 747,362.53 | project completed; remaining fund returned to source agency already | ||||||||||||||||||
60 | PRDP - SEAWEEDS PRODUCTION, CONSOLIDATION & MARKETING ENTERPRISE (LP) | Getafe, Bohol | 6,726,000.00 | 6,720,000.00 | - | 99.91% | 6,720,000.00 | on-going project | ||||||||||||||||||
61 | PRDP - SEAWEEDS PRODUCTION, CONSOLIDATION & MARKETING ENTERPRISE (GOP) | Getafe, Bohol | 2,242,000.00 | 2,240,000.00 | - | 99.91% | 2,240,000.00 | on-going project | ||||||||||||||||||
62 | PRDP - SEAWEEDS PRODUCTION, CONSOLIDATION & MARKETING ENTERPRISE - CIVIL WORKS (LP) | Getafe, Bohol | 4,365,138.82 | 4,353,000.00 | - | 99.72% | 4,353,000.00 | on-going project | ||||||||||||||||||
63 | PRDP - SEAWEEDS PRODUCTION, CONSOLIDATION & MARKETING ENTERPRISE - CIVIL WORKS (GOP) | Getafe, Bohol | 1,455,046.27 | 1,451,000.00 | - | 99.72% | 1,451,000.00 | on-going project | ||||||||||||||||||
64 | GEF - AGUINING MARINE SANCTUARY REHABILITATION PRES. CPG, BOHOL | CPG, BOHOL | 2,474,706.67 | 1,552,912.93 | - | 62.75% | 1,552,912.93 | on-going project | ||||||||||||||||||
65 | GEF - ASINAN FISH SANCTUARY REHABILITATION BUENAVISTA, BOHOL | Buenavista, Bohol | 2,041,466.67 | 1,447,572.34 | - | 70.91% | 1,447,572.34 | on-going project | ||||||||||||||||||
66 | GEF - BILANGBILANGAN EAST MARINE SANCTUARY REHABILITATION BIEN UNIDO | Bien Unido | 2,149,040.00 | 1,291,443.67 | - | 60.09% | 1,291,443.67 | on-going project | ||||||||||||||||||
67 | GEF - CATABAN MARINE SANCTUARY REHABILITATION, TALIBON | Talibon | 2,551,512.00 | 1,700,929.66 | - | 66.66% | 1,700,929.66 | on-going project | ||||||||||||||||||
68 | GEF - GUINDACPAN MARINE SANCTUARY | Guindacpan, Talibon | 2,660,496.00 | 1,754,192.49 | - | 65.93% | 1,754,192.49 | on-going project | ||||||||||||||||||
69 | GEF - HINGOTANAN WEST MARINE PROTECTED AREA | Bien Unido | 2,149,040.00 | 1,291,443.66 | - | 60.09% | 1,291,443.66 | on-going project | ||||||||||||||||||
70 | GEF - MARINE PROTECTED AREA REHABILITATION- SINANDIGAN, UBAY | Sinandigan, Ubay | 2,152,978.67 | 1,390,685.69 | - | 64.59% | 1,390,685.69 | on-going project | ||||||||||||||||||
71 | GEF - MARINE SANCTUARY REHABILITATION - SIDLAKAN, PRES. GARCIA | Sidlakan, Pres. Garcia | 2,314,706.67 | 1,699,201.74 | - | 73.41% | 1,699,201.74 | on-going project | ||||||||||||||||||
72 | PCSO - PAMASKONG ALAY FOR VICTIMS OF YOLANDA | N/A | 4,275,032.64 | 2,600,709.27 | - | 60.83% | 2,600,709.27 | Trust Fund account still for reconciliation | ||||||||||||||||||
73 | DSWD - GPBP PROJECT 2014 | N/A | 4,736,000.00 | 2,467,502.15 | - | 52.10% | 2,467,502.15 | Trust Fund account still for reconciliation | ||||||||||||||||||
74 | DBM - LGSF CONSTRUCTION OF FOOTBRIDGE JANOPOL-SEVILLA ; CONSTRUCTION OF MULTI-PURPOSE BUILDING AT CONG. PABLO MALASARTE HS CABAD, BALILIHAN | Balilihan | 10,000,000.00 | 3,397,237.09 | - | 33.97% | 3,397,237.09 | Trust Fund account still for reconciliation | ||||||||||||||||||
75 | FINANCIAL ASSISTANCE FOR ANTI-DENGUE CAMPAIGN | N/A | 181,740.00 | 39,990.00 | - | 22.00% | 39,990.00 | on-going project | ||||||||||||||||||
76 | NCCA - INSTITUTE OF LIVING TRADITIONS | N/A | 2,249,827.00 | 1,412,196.50 | 70,000.00 | 65.88% | 1,482,196.50 | on-going project | ||||||||||||||||||
77 | NCCA - TUBURAN BOHOL | N/A | 149,845.00 | 111,441.00 | - | 74.37% | 111,441.00 | on-going project | ||||||||||||||||||
78 | DANGEROUS DRUGS BOARD - CONSTRUCTION OF MULTI-PURPOSE BLDG FOR DRUG SURRENDERERS | N/A | 5,000,000.00 | - | - | 0.00% | - | Trust Fund account for verification | ||||||||||||||||||
79 | TPB - INNOVATING TOURISM PROMOTIONS THROUGH DASIG BOHOL'S DIGITAL STREAMING VIDEOS & OMNICHANNEL APPROACH | N/A | 9,749,850.00 | 8,787,850.00 | - | 90.13% | 8,787,850.00 | program completed; remaining fund balance for return to source agency | ||||||||||||||||||
80 | DBM - LOCAL GOVERNMENT SUPPORT FUND (LGSF) COVID-19 FINANCIAL ASSISTANCE TO LGUs | N/A | 10,000,000.00 | 9,761,577.84 | - | 97.62% | 9,761,577.84 | on-going program | ||||||||||||||||||
81 | OCD - FINANCIAL SUPPORT FROM NDRRMC TO PDRRMO INTENDED FOR THE ENHANCEMENT OF THE CAPABILITY OF THE PROVINCE EMERGENCY OPERATION CENTER | N/A | 3,044,684.64 | - | - | 0.00% | - | on-going project | ||||||||||||||||||
82 | DOT- FUND FOR RT-PCR TESTING FOR HOSPITALITY & TOURISM WORKERS IN THE PROVINCE OF BOHOL | N/A | 9,999,850.00 | - | - | 0.00% | - | on-going program | ||||||||||||||||||
83 | DOH - PROCUREMENT OF SUPPLIES & CONSUMABLES FOR BOHOL CONTAINERIZED PCR LABORATORY IN RESPONSE TO COVID-19**/*** | N/A | 9,999,850.00 | 5,000,000.00 | - | 50.00% | 5,000,000.00 | on-going program | ||||||||||||||||||
84 | DOLE - LIVELIHOOD/KABUHAYAN PROGRAM | N/A | 1,883,933.00 | - | - | 0.00% | - | on-going program | ||||||||||||||||||
85 | DOH - GRANT OF SPECIAL RISK ALLOWANCE (SRA) TO ELIGIBLE HEALTH WORKERS - 2ND TRANCHE**/*** | N/A | 109,875,761.55 | 89,746,504.05 | 12,028,203.63 | 92.63% | 101,774,707.68 | on-going program | ||||||||||||||||||
86 | DOT - DOMESTIC TOURISM PROJECTS | N/A | 1,866,500.00 | - | - | 0.00% | - | on-going project | ||||||||||||||||||
87 | DOE - DEVELOPMENT AND LIVELIHOOD FUND (DLF) | N/A | 610,417.71 | 900.00 | - | 0.15% | 900.00 | on-going program | ||||||||||||||||||
88 | DOE - REFORESTATION, WATERSHED MANAGEMENT, HEALTH, ENVIRONMENT ENHANCEMENT FUND (RWMHEEF) | N/A | 634,318.30 | 900.00 | - | 0.14% | 900.00 | on-going program | ||||||||||||||||||
89 | NHA - SPECIAL EMERGENCY HOUSING ASSISTANCE PROGRAM (EHAP) FOR TYPHOON ODETTE VICTIMS WITH DAMAGED HOUSES | N/A | 55,000,000.00 | 54,915,000.00 | 85,000.00 | 100.00% | 55,000,000.00 | program completed | ||||||||||||||||||
90 | DBM - LOCAL GOVERNMENT SUPPORT FUND (LGSF) FINANCIAL ASSISTANCE TO LGUs THAT WERE AFFECTED BY TYPHOON ODETTE | N/A | 41,095,133.00 | 29,064,091.20 | 1,731,750.00 | 74.94% | 30,795,841.20 | on-going program | ||||||||||||||||||
91 | DONATIONS - TYPHOON ODETTE RECOVERY AND REHABILITATION PROGRAM*** | N/A | 32,445,207.01 | 1,433,349.47 | 386,850.00 | 5.61% | 1,820,199.47 | on-going program | ||||||||||||||||||
92 | PCSO - ENDOWMENT FUND FOR TEODORO B. GALAGAR DISTRICT HOSPITAL | Jagna | 1,000,000.00 | 216,990.03 | 273,521.78 | 49.05% | 490,511.81 | on-going program | ||||||||||||||||||
93 | OP - FINANCIAL ASSISTANCE TO CATER & ADDRESS THE IMMEDIATE NEEDS OF THE PEOPLE AFFECTED BY TYPHOON ODETTE | N/A | 100,000,000.00 | - | - | 0.00% | - | on-going program | ||||||||||||||||||
94 | DBM - LOCAL GOVERNMENT SUPPORT FUND (LGSF) FINANCIAL ASSISTANCE TO LGUs - PROCUREMENT OF MEDICAL EQUIPMENT (DIALYSIS CHAIRS) | N/A | 30,000,000.00 | - | - | 0.00% | - | on-going program | ||||||||||||||||||
95 | DOH - UNIVERSAL HEALTH CARE GRANT | N/A | 2,756,634.56 | - | - | 0.00% | - | on-going program | ||||||||||||||||||
96 | DA - PURCHASE OF HAULING/CARGO TRUCK UNDER THE ENHANCE KADIWA NI ANI AT KITA FINANCIAL GRANT ASSISTANCE PROGRAM | N/A | 2,900,000.00 | - | - | 0.00% | - | on-going program | ||||||||||||||||||
97 | EMBASSY OF THE PEOPLE'S REPUBLIC OF CHINA - ENHANCEMENT OF THE FISHING VILLAGES IN BOHOL** | N/A | 15,000,000.00 | - | - | 0.00% | - | newly implemented project | ||||||||||||||||||
98 | DOH - PERFORMANCE BASED INCENTIVE (PBI) OF THE BARANGAY HEALTH WORKERS IN BOHOL** | N/A | 199,850.00 | - | - | 0.00% | - | newly implemented program | ||||||||||||||||||
99 | DOH - GRANT OF ONE COVID-19 ALLOWANCE (OCA) TO ELIGIBLE HEALTH CARE WORKERS AND NON-HEALTH CARE WORKERS** | N/A | 42,347,531.25 | - | 35,898,279.84 | 84.77% | 35,898,279.84 | newly implemented program | ||||||||||||||||||
100 | DOH - GRANT OF MEALS, ACCOMMODATION AND TRANSPORTATION (MAT) BENEFITS TO ELIGIBLE HEALTH CARE WORKERS** | N/A | 59,324,700.00 | - | - | 0.00% | - | newly implemented program | ||||||||||||||||||