ABCDEFGHIJKLMNOPQRSTUVWXYZ
1
CHECKLIST FOR ON-SITE INSPECTION
2
ACTIVITY: GRANITE/ MARBLE TILING
3
4
Project:Date:
5
Location:
6
7
NOTE:- Please tick appropriate box or enter readings as per requirements
8
Sl. No.ITEMYESNONARemarks
9
1Name,date and number of the drawing
10
PRE-TILING CHECKS
11
2Has the floor slab been prepared for granite work ?
12
3Is the floor free from dust and other contaminations?
13
4Are there any necessary works pending?
14
5Have the bull markings done according to architectural specifications?
15
6Have the tiles matched, numbered and available in required number for laying?
16
7Are the required tools available on-site?
17
8Are there any specific requirements of the client?
18
9Are the tiles dry matched and cut to exact size ?
19
10Has the tile code number and tile name ensured?
20
CHECKS DURING TILING
21
11Has the work started by taking right angles for existing walls?
22
12Has the laying procedure followed?
23
13Has the laying started as per the previously numbered tiles?
24
14Is the floor moist and provided with cement slurry for bonding?
25
15Has the levelling done with an aluminium straight edge and rubber hammer?
26
16Has the joint filling done as per colour of the granite/ marble?
27
17Have the tiles been gently tapped after laying on the motar bed?
28
POST-TILING CHECKS
29
18Have the joints been cleaned to remove loose mortar?
30
19Are the joints properly aligned?
31
20Is the work carried out to plump and horizontally to line?
32
21Is the finished floor level?
33
22Are all the layed floor surfaces properly covered?
34
23Has it been ensured that grouting is done after 24hrs of laying of tiles?
35
24 Has the area been barricaded so as not to allow foot movement?
36
Checked by:
Approved by:
37
SignSign
38
NameName
39
DateDate
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
80
81
82
83
84
85
86
87
88
89
90
91
92
93
94
95
96
97
98
99
100