RENOVATION ORDER PLANNER
2
Sandra J Conner · Real Estate Growth Program — Flip Foundation Member Tool | Rule: Do NOT order an item until everything required to install it is already in place or confirmed on schedule.
3
Sandra's lesson: Appliances ordered before the draw was ready = $2,154 tied up for 13 weeks. Use this planner to prevent that mistake on YOUR flip.
4
LEGEND: 🟡 Yellow = fill in yourself ✅ Green = ready to order 🔴 Red = NOT ready — prerequisites missing Permit Required = confirm with your county BEFORE work begins
5
6
#Item / ProductWhat Must Be In Place First
(Prerequisites)
Permit
Required?
Lead Time
(Days)
Date to
Order
Expected
Delivery Date
Cost
Estimate ($)
Draw
Reimbursable?
Supplier /
Store
Status
7
1Pest / Bug Inspection & Treatment (Orkin)Keys in hand — do this FIRST before any demoNoSame daySchedule same week as closingCall for quoteCheck with lenderPending
8
2Dumpster DeliveryPest treatment confirmed safe to re-enterNo1Order 1-2 days after closingCall for quoteNoPending
9
3Demolition (cabinets, drywall, flooring removal)Dumpster on site · Pest treatment complete · Safety confirmedNoSame dayBegin same day dumpster arrivesDIY or labor quoteNoPending
10
4Electrical Rough-In (inside walls)Demo complete · Licensed electrician hired · Permit pulledYES ⚠️1After demo — before walls closeGet 3 quotesYes — confirm draw triggerPending
11
5Plumbing Rough-In (inside walls)Demo complete · Licensed plumber hired · Permit pulledYES ⚠️1After demo — before walls closeGet 3 quotesYes — confirm draw triggerPending
12
6HVAC Rough-InDemo complete · Contractor hired · Permit pulledYES ⚠️1After demo — before walls closeGet 3 quotesYes — confirm draw triggerPending
13
7Rough-In Inspections (electrical, plumbing, HVAC)ALL rough-in work complete — do NOT drywall until passedYES ⚠️Same daySchedule with county after rough-in completeCounty feeNoPending
14
8InsulationAll rough-in inspections PASSEDCheck county2Order after inspections passPer sq ft quoteYes — confirm draw triggerPending
15
9Drywall (hang and mud)Insulation in · All inspections passed · Walls clear to closeNo1Order/schedule after inspections passGet 3 quotesYes — confirm draw triggerPending
16
10Paint (walls, ceilings, trim)Drywall complete and dryNo1Order paint after drywall completePer gallon estimateYes — confirm draw triggerPending
17
11Cabinets (order early — long lead time!)Demo complete · Measurements confirmed · Paint color decided
⚠️ CUSTOM CABINETS: 6-8 week lead time — order AFTER demo, NOT before
No42Order immediately after demo + measurementsGet 3 quotesYes — confirm draw trigger + install requirementPending
18
12CountertopsCabinets installed · Template measurement doneNo14Order after cabinet install + templatingPer sq ft quoteYes — confirm draw triggerPending
19
13Flooring (hardwood, LVP, tile)Paint complete · Subfloor inspected and level · Cabinets inNo7Order after paint — install after cabinetsPer sq ft quoteYes — confirm draw triggerPending
20
14Fixtures (light fixtures, faucets, hardware)Paint complete · Electrical and plumbing finals doneNo7Order after paintBudget per roomYes — confirm draw triggerPending
21
15Appliances ⚠️ SANDRA'S LESSONCabinets IN · Countertops IN · Flooring IN · Draw trigger confirmed with lender in writing
DO NOT ORDER until you know EXACTLY when they'll be installed AND when lender will reimburse
No14Order ONLY when install date is confirmedBudget per applianceYES — but lender requires full install + photos firstPending
22
16Final Inspections (electrical, plumbing, building)All finish work completeYES ⚠️Same daySchedule with countyCounty feeNoPending
23
17Landscaping / ExteriorAll interior work complete · Final inspections passedCheck county3Schedule after interior completeGet 3 quotesYes — confirm draw triggerPending
24
18Deep CleanAll work complete · All inspections passedNo1Schedule 1-2 days before listingGet quoteNoPending
25
26
TOTAL ESTIMATED COST$0
27
28
YELLOW cells = fill in yourself. Cost Estimate column H: enter numbers only (no $ sign) — the total calculates automatically. Order Date (col F) and Delivery Date (col G): enter as MM/DD/YYYY. Status (col K): update to Ordered / Delivered / Installed / Inspected as work progresses. Permit Required column: always verify with your local county zoning office before work begins — requirements vary.
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
80
81
82
83
84
85
86
87
88
89
90
91
92
93
94
95
96
97
98
99
100