JOB SAFETY ANALYSIS (JSA)Doc. No.
3
Title of Activity / Work:WORK AT HIGHT AND MARBLE INSTALLATIONDoc. Rev. Date13-Jul-16
4
Name of Project Site: SIATOUROJob No. :
5
Location of Project Site: RAILWAY LOOPPTW No.:
6
Name of Contractor: SINOSTEEL INT.JSA No.:TEIPL/JSA/001
7
Date of JSA Preparation: 02 MARS 2025 JSA PART A:-JSA PART B :-Activity / Work Location Name:
8
Sl. No.Subactivity / Steps Hazard EffectControl MeasuresResponsibility Compliance? Yes / No Remarks
9
PART A:- STANDARD JSA
10
1Site preparation & developmentSnakes or insects Poisoning due to Snake / Insects venom may cause fatality1) Spraying of chemicals/repellent to prevent Snakes or insects.
Execution Engineer & Job Supervisor; HSE -Monitoring & Training
11
2) Good Housekeeping and cleaning ground to make place inhabitat for snakes/insects.
12
3) Provide First Aid box. Tie up with near by hospital
13
4) First aid trainings.
14
2Site preparation & developmentMosquitosSkin Rash, dengue, fever, malaria , skin irritation1) Spraying of pest control chemicals to keep away mosquitoes and to kill it’s larvae.
Execution Engineer & Job Supervisor; HSE -Monitoring & Training
15
2) Maintain Good Housekeeping.

16
3) Regular cleaning of accumulated water from pits /ditches.
17
4) Dengue / Malaria awareness.
18
3Site preparation & development , transportationDust Skin and eye irritation, cough , lung irritation1) Proper leveling/compacting ground.
Execution Engineer & Job Supervisor; HSE -Monitoring & Training
19
2) Storing soil or other fine particles material in low height of the heap. Cover them with empty wet gunny bags.
20
3) Ensure all site traffic adhere to the site speed limit.
21
4) Vegetation clearing should be carried out on a need basis.
22
5) Cleaning eyes / face with water.
23
6) Provide windbreaks either natural or constructed that reduces the wind velocities. Natural wind breaks can be native shrubs or trees left in place during site clearing. Constructed barriers can be made from metal / wood sheets.
24
7) Air Monitoring for dust (Particulate Matters).
25
8) Water Sprinkling on ground.
26
4Cutting ground, transportationFlying stone while cutting ground, transportation, strong windContact with sharp object may cause severe injury1) Proper leveling/compacting ground.
Execution Engineer & Job Supervisor; HSE -Monitoring & Training
27
2) Ensure all site traffic adhere to the site speed limit.
28
3) Barricade and Put Safety Signage in cutting operation area.
29
4) Provide windbreaks either natural or constructed that reduces the wind velocities. Natural wind breaks can be native shrubs or trees left in place during site clearing. Constructed windbreaks can be made from metal / wood sheets.
30
5Tree Cutting, Use of toolsSharp Thorn /sharp edges Contact with sharp object may cause severe puncture injury.1) Cut the trees with thorns carefully by mechanical tools / cutter.
Execution Engineer & Job Supervisor; HSE -Monitoring & Training
31
2) Use gloves. PPE Assessment Audit
32
3) Guard the tools.
33
4) Hold the tool firmly while cutting.
34
5) HSE Training,
35
PART B:- LOCATION SPECIFIC JSA
36
37
38
39
40
41
Note:
42
Prepared by: MANAGEMENT BOARDReviewed by:AIME RAPHAEL HABAApproved by:
43
Note: This is standard JSA prepared based on general hazards. Site has to review this JSA & Update considering process involved, site & work location condition, equipments/machines/ tools use, people involved and activities near by job location.
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
80
81
82
83
84
85
86
87
88
89
90
91
92
93
94
95
96
97
98
99
100