| A | B | C | D | E | F | G | H | I | J | K | L | M | N | O | P | Q | R | S | T | U | V | W | X | Y | Z | |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1 | Project: Construction of Centralized Cooling System (CCS) for HDB in Tengah Park and Garden District | |||||||||||||||||||||||||
2 | Main Contractor: Bosh Engineering Pte Ltd | |||||||||||||||||||||||||
3 | Services: Mechanical Works | |||||||||||||||||||||||||
4 | Package: Tengah Park C1, Garden C3 and Garden C7 | |||||||||||||||||||||||||
5 | Sub-Contract Ref. No.: | |||||||||||||||||||||||||
6 | Sub-Contractor's Work Scope Table | |||||||||||||||||||||||||
7 | ||||||||||||||||||||||||||
8 | DESCRIPTION | SUPPLY | INSTALLATION | TESTING & COMMISSIONING | ||||||||||||||||||||||
9 | 1 | Equipment and Material Handling | ||||||||||||||||||||||||
10 | 1.1 | Crane for Hoisting of CCS Plant Equipment (Chiller, Cooling Tower, Pumps, Water Tanks, Skids) to Roof Level | MAIN CON | SUBCON | N/A | |||||||||||||||||||||
11 | 1.2 | Hoisting of Pipe, Support Materials to Building Roof Top | SUBCON | SUBCON | N/A | |||||||||||||||||||||
12 | 1.3 | Lifting team including Rigger, Signalman, Lifting Supervisor and other necessary manpower for hoisting activity | SUBCON | SUBCON | N/A | |||||||||||||||||||||
13 | 1.4 | Space for temporary storage space only | MAIN CON | SUBCON | N/A | |||||||||||||||||||||
14 | 1.5 | DFMA workshop and prefebrication workshop space | SUBCON | SUBCON | N/A | |||||||||||||||||||||
15 | 1.6 | Temporary storage hoarding sheet, scaffolding pipes, fire extinguisher, etc. | SUBCON | SUBCON | N/A | |||||||||||||||||||||
16 | 1.7 | Unloading from truck/trailer, transporter and etc at job site and / or temporary storage area | SUBCON | SUBCON | N/A | |||||||||||||||||||||
17 | 1.8 | Transportation (Job site to erection point and temporary storage area to job site) | SUBCON | SUBCON | N/A | |||||||||||||||||||||
18 | 1.9 | Receiving and transportation of materials and equipment (Job site to erection point and temporary storage area to job site) | SUBCON | SUBCON | N/A | |||||||||||||||||||||
19 | 1.10 | Scaffolding, boom lifts, scissors lift, ladders, tools and machineries necessary of installation works (Complying to MOM and/or site rules and regulations) | SUBCON | SUBCON | N/A | |||||||||||||||||||||
20 | 1.11 | Calibrated testing instruments required for T&C for installed works on site | SUBCON | SUBCON | N/A | |||||||||||||||||||||
21 | 2 | Manpower | ||||||||||||||||||||||||
22 | 2.1 | Manpower for Material receiving, unpacking, storing, loading/unloading, transportation, installation, testing, commissioning, defect clearing, etc. | SUBCON | SUBCON | N/A | |||||||||||||||||||||
23 | 2.2 | Lifting team for Plant Equipment unloading from truck and hoisting to proper position on plinth at roof top | SUBCON | SUBCON | N/A | |||||||||||||||||||||
24 | 2.3 | Site Supervisor to attend daily/ weekly/ monthly site meetings as required by Site Engineer | SUBCON | SUBCON | N/A | |||||||||||||||||||||
25 | 2.4 | Designated Site Supervisor (BCSS certified) to carry out site supervision and co-ordination on site, DFMA workshop and prefebrication workshop | SUBCON | SUBCON | N/A | |||||||||||||||||||||
26 | 2.5 | Site Supervisor (BCSS certified) to play the role of Site Safety Supervisor to conduct and attend safety meetings and tool box meetings as required by Site Engineer | SUBCON | SUBCON | N/A | |||||||||||||||||||||
27 | 2.6 | Attend and undertake inspection as requested | SUBCON | SUBCON | N/A | |||||||||||||||||||||
28 | 2.7 | Verification and mark-up of as-built DWG. to the Main Contractor's standards | SUBCON | SUBCON | N/A | |||||||||||||||||||||
29 | 3 | Mechanical Works | ||||||||||||||||||||||||
30 | 3.1 | CCS Plant Equipment (Chiller, Cooling Tower, Pumps, Water Tanks, Skids) | MAIN CON | SUBCON | SUBCON | |||||||||||||||||||||
31 | 3.2 | HDPE Pipe, Fittings (Elbow, Tee, Reducer, End Cap, Transition Coupler, Union, Flange, Electrofusion Coupler) | MAIN CON | SUBCON | SUBCON | |||||||||||||||||||||
32 | 3.3 | Carbon Steel Pipe, Fittings (Elbow, Tee, Reducer, End Cap, Coupling, Union, Flange) | MAIN CON | SUBCON | SUBCON | |||||||||||||||||||||
33 | 3.4 | Valve (Gate Valve, Butterfly Valve, Balancing Valve, Ball Valve, Strainer, Check Valve, Flexible Joint, Thermowell, Air Vent) | MAIN CON | SUBCON | SUBCON | |||||||||||||||||||||
34 | 3.6 | PU Chemical (Isocyanate (Black) / Polyol (White)) and GI Sheet for Pipe Field Joints and Fittings | SUBCON | SUBCON | SUBCON | |||||||||||||||||||||
35 | 3.6 | GI sheet forming and necessary accessories for Insulation of Pipe Joints and Fittings (at Site) | SUBCON | SUBCON | SUBCON | |||||||||||||||||||||
36 | 3.7 | Paint material for pipes (Roof Top Only) | MAIN CON | SUBCON | SUBCON | |||||||||||||||||||||
37 | 3.8 | Paint material for labeling, marking templates, legend plates, rubber mat etc. | SUBCON | SUBCON | SUBCON | |||||||||||||||||||||
38 | 3.9 | DurkFlex Insulation for HDPE Pipe (OD 40mm) and Fittings (K-Flex in stright length for Fittings) | MAIN CON | SUBCON | SUBCON | |||||||||||||||||||||
39 | 3.10 | Necessary accessories for Installation of DurkFlex Insulation for HDPE Pipe (OD 40 mm) and Fittings | SUBCON | SUBCON | SUBCON | |||||||||||||||||||||
40 | 3.11 | Supply, Fabrication and Installation of Steel Support for Plant Equipment, Pipe, etc., | SUBCON | SUBCON | SUBCON | |||||||||||||||||||||
41 | 3.12 | 3 nos of Access Platform at roof for chiller blocks | SUBCON | SUBCON | SUBCON | |||||||||||||||||||||
42 | 3.13 | Anchor bolts | SUBCON | SUBCON | SUBCON | |||||||||||||||||||||
43 | 3.14 | Hanger, Thread Rod, Angle, Channel, U-Bolt, Nuts, Washer, Pipe Shoes, Pipe Brackets, and necessary material for Pipe Support, Pipe Slippers, Ceiling Pipe | SUBCON | SUBCON | SUBCON | |||||||||||||||||||||
44 | 3.15 | Anchor bolts pull out test (if necessary) | SUBCON | SUBCON | SUBCON | |||||||||||||||||||||
45 | 3.16 | Anchor bolts torque test (if necessary) | SUBCON | SUBCON | SUBCON | |||||||||||||||||||||
46 | 3.17 | Valve and Instruments Tagging | SUBCON | SUBCON | N/A | |||||||||||||||||||||
47 | 3.19 | Replacement of Temporary Pipe in Riser to BTU meter | MAIN CON | SUBCON | SUBCON | |||||||||||||||||||||
48 | 3.20 | Welding Machines for HDPE Pipe | SUBCON | SUBCON | SUBCON | |||||||||||||||||||||
49 | 3.21 | Welder Test Piece for Welder Qualification | SUBCON | SUBCON | SUBCON | |||||||||||||||||||||
50 | 3.22 | NDT reports of welding joints | SUBCON | SUBCON | SUBCON | |||||||||||||||||||||
51 | 3.23 | Firestop Sealing of Pipe Penetration Wall, Beam, etc., | SUBCON | SUBCON | SUBCON | |||||||||||||||||||||
52 | 3.24 | Permanent safety signage and all other signages | SUBCON | SUBCON | SUBCON | |||||||||||||||||||||
53 | 3.25 | Fire stop for openings c/w QP certification | SUBCON | SUBCON | N/A | |||||||||||||||||||||
54 | 3.26 | Paints, marking templates, legend plates, etc. | SUBCON | SUBCON | N/A | |||||||||||||||||||||
55 | 3.27 | All other installations per drawings provided | SUBCON | SUBCON | SUBCON | |||||||||||||||||||||
56 | 3.28 | All other necessary tests before and during Testing and Commissioning | SUBCON | SUBCON | SUBCON | |||||||||||||||||||||
57 | ||||||||||||||||||||||||||
58 | Notes: | |||||||||||||||||||||||||
59 | 1 | To include installation of wall and floor mounted shock isolators c/w mounting accessories. | ||||||||||||||||||||||||
60 | 2 | Bracket sizes shown in the given drawings are subjected to QP’s calculation and approval. Sizes may subject to changes. | ||||||||||||||||||||||||
61 | 3 | Installation details in given drawings are for reference only, details may subject to changes after SP acceptance. | ||||||||||||||||||||||||
62 | 4 | To conduct all necessary tests by your own manpower, e.g. continuity test, Insulation test, initial run equipments, T&C, etc. | ||||||||||||||||||||||||
63 | ||||||||||||||||||||||||||
64 | ||||||||||||||||||||||||||
65 | ||||||||||||||||||||||||||
66 | ||||||||||||||||||||||||||
67 | ||||||||||||||||||||||||||
68 | ||||||||||||||||||||||||||
69 | ||||||||||||||||||||||||||
70 | ||||||||||||||||||||||||||
71 | ||||||||||||||||||||||||||
72 | ||||||||||||||||||||||||||
73 | ||||||||||||||||||||||||||
74 | ||||||||||||||||||||||||||
75 | ||||||||||||||||||||||||||
76 | ||||||||||||||||||||||||||
77 | ||||||||||||||||||||||||||
78 | ||||||||||||||||||||||||||
79 | ||||||||||||||||||||||||||
80 | ||||||||||||||||||||||||||
81 | ||||||||||||||||||||||||||
82 | ||||||||||||||||||||||||||
83 | ||||||||||||||||||||||||||
84 | ||||||||||||||||||||||||||
85 | ||||||||||||||||||||||||||
86 | ||||||||||||||||||||||||||
87 | ||||||||||||||||||||||||||
88 | ||||||||||||||||||||||||||
89 | ||||||||||||||||||||||||||
90 | ||||||||||||||||||||||||||
91 | ||||||||||||||||||||||||||
92 | ||||||||||||||||||||||||||
93 | ||||||||||||||||||||||||||
94 | ||||||||||||||||||||||||||
95 | ||||||||||||||||||||||||||
96 | ||||||||||||||||||||||||||
97 | ||||||||||||||||||||||||||
98 | ||||||||||||||||||||||||||
99 | ||||||||||||||||||||||||||
100 | ||||||||||||||||||||||||||