Home Building Budget7/19/2026
5
Color
WBS Number
Task name / TitleAssigned to
Planned start date
Planned end date
Deadline
Progress (%)
Duration (hours)
Estimated hours
Time log (minutes)
StatusPriority
Task description
Cost
Actual cost
6
1GENERAL REQUIREMENTS10/19/202612/28/202604080000
7
1.1Plans & Specifications10/19/202612/20/2026036000OpenMedium00
8
1.2Plan Review10/22/202612/21/2026036000OpenMedium00
9
1.3
Permits: Zoning, Building, Environemental
10/22/202612/21/2026036000OpenMedium00
10
1.4Survey10/22/202612/21/2026036000OpenMedium00
11
1.5Impact Fee10/23/202612/24/2026036000OpenMedium00
12
1.6Adminstrative Costs10/24/202612/25/2026036000OpenMedium00
13
1.7Financing Costs10/25/202612/26/2026036000OpenMedium00
14
1.8Legal Fees10/26/202612/27/2026036000OpenMedium00
15
1.9Engineering Fees10/29/202612/28/2026036000OpenMedium00
16
1.10Other10/29/202612/28/2026036000OpenMedium00
17
2SITE PREP12/31/20263/14/202704320000
18
2.1Demolition (Remodel)12/31/20263/1/2027036000OpenMedium00
19
2.2Jacking & Shoring (Remodel)1/1/20273/4/2027036000OpenMedium00
20
2.3
Dust control, Surface Protection
1/2/20273/5/2027036000OpenMedium00
21
2.4Job-Site Access1/3/20273/6/2027036000OpenMedium00
22
2.5Job-Site Security1/4/20273/7/2027036000OpenMedium00
23
2.6Dumpster & Removal1/4/20273/7/2027036000OpenMedium00
24
2.7Clear Lot1/4/20273/7/2027036000OpenMedium00
25
2.8Storage On Site1/7/20273/8/2027036000OpenMedium00
26
2.9Portable Toilet1/8/20273/11/2027036000OpenMedium00
27
2.10Temporary Power1/9/20273/12/2027036000OpenMedium00
28
2.11Temporary Heat1/10/20273/13/2027036000OpenMedium00
29
2.12Scaffolding Rental1/11/20273/14/2027036000OpenMedium00
30
2.13Tool/Equipment Rental1/11/20273/14/2027036000OpenMedium00
31
2.14Other1/11/20273/14/2027036000OpenMedium00
32
3ON-SITE WATER/SEWER3/15/20275/23/202704000000
33
3.1Soil & Perc Tests3/15/20275/16/2027036000OpenMedium00
34
3.2Septic System Design3/18/20275/17/2027036000OpenMedium00
35
3.3
Septic Permits, Inspections, Fees
3/19/20275/20/2027036000OpenMedium00
36
3.4
Septic System Installation, Tie in to House
3/20/20275/21/2027036000OpenMedium00
37
3.5Dewatering (High Water Table)3/20/20275/21/2027036000OpenMedium00
38
3.6
Well, Pump, Trenching, Plumbing to House
3/20/20275/21/2027036000OpenMedium00
39
3.7Well Permits & Fees3/21/20275/22/2027036000OpenMedium00
40
3.8Other3/22/20275/23/2027036000OpenMedium00
41
4UTILITIES11/23/20261/31/202704000000
42
4.1
Town Water: Tap Fees & Hookup
11/23/20261/24/2027036000OpenMedium00
43
4.2
Town Sewer: Tap Fees & Hookup
11/26/20261/25/2027036000OpenMedium00
44
4.3
Electrical: Permit, Connection Fee, Installation
11/26/20261/25/2027036000OpenMedium00
45
4.4
Gas: Permit, Connection Fee, Installation
11/26/20261/25/2027036000OpenMedium00
46
4.5LPN: Tank installation, Hookup11/27/20261/28/2027036000OpenMedium00
47
4.6Oil Tank Installation11/28/20261/29/2027036000OpenMedium00
48
4.7Telecom Hookup11/29/20261/30/2027036000OpenMedium00
49
4.8Other11/30/20261/31/2027036000OpenMedium00
50
5EXCAVATION & EARTHWORK12/3/20262/20/202704640000
51
5.1Cut & Fill12/3/20262/1/2027036000OpenMedium00
52
5.2Blasting12/3/20262/1/2027036000OpenMedium00
53
5.3Removal of Stone/Dirt12/4/20262/4/2027036000OpenMedium00
54
5.4Rough Grading12/5/20262/5/2027036000OpenMedium00
55
5.5Trenching For Utility Hookups12/6/20262/6/2027036000OpenMedium00
56
5.6Foundation Excavation12/7/20262/7/2027036000OpenMedium00
57
5.7Foundation Footing Drains12/10/20262/8/2027036000OpenMedium00
58
5.8Curtain Drains12/10/20262/8/2027036000OpenMedium00
59
5.9Culverts12/10/20262/8/2027036000OpenMedium00
60
5.10Swales12/11/20262/11/2027036000OpenMedium00
61
5.11Retaining Walls12/12/20262/12/2027036000OpenMedium00
62
5.12Ponds12/13/20262/13/2027036000OpenMedium00
63
5.13Other Site Drainage12/14/20262/14/2027036000OpenMedium00
64
5.14Backfill12/17/20262/15/2027036000OpenMedium00
65
5.15Compaction12/17/20262/15/2027036000OpenMedium00
66
5.16Top Soil12/17/20262/15/2027036000OpenMedium00
67
5.17Finish Grading12/18/20262/18/2027036000OpenMedium00
68
5.18Seeding/Sod12/19/20262/19/2027036000OpenMedium00
69
5.19Other12/20/20262/20/2027036000OpenMedium00
70
6FOUNDATION12/24/20263/11/202704480000
71
6.1Footings/Pads12/24/20262/22/2027036000OpenMedium00
72
6.2
Foundation walls/stem walls/grade beams
12/24/20262/22/2027036000OpenMedium00
73
6.3Piers12/24/20262/22/2027036000OpenMedium00
74
6.4
Slabs - Foundation, Basement, Garage
12/25/20262/25/2027036000OpenMedium00
75
6.5Steel Reinforcing12/26/20262/26/2027036000OpenMedium00
76
6.6Anchor Bolts, Hold Downs12/27/20262/27/2027036000OpenMedium00
77
6.7Buikheads12/28/20262/28/2027036000OpenMedium00
78
6.8Sub-Slab Vapor Barrier12/31/20263/1/2027036000OpenMedium00
79
6.9Sump Pump12/31/20263/1/2027036000OpenMedium00
80
6.10Crawlspace Vapor Barrier12/31/20263/1/2027036000OpenMedium00
81
6.11Crawlspace Vents1/1/20273/4/2027036000OpenMedium00
82
6.12Foundation Windows1/2/20273/5/2027036000OpenMedium00
83
6.13Damproofing, Water-proofing1/3/20273/6/2027036000OpenMedium00
84
6.14Foundation Drain Board1/4/20273/7/2027036000OpenMedium00
85
6.15Slab insulation: Edge/Blow1/7/20273/8/2027036000OpenMedium00
86
6.16Exterior Foundation Insulation1/7/20273/8/2027036000OpenMedium00
87
6.17
Exterior Insulation Coating/ Protection
1/7/20273/8/2027036000OpenMedium00
88
6.18Other1/8/20273/11/2027036000OpenMedium00
89
7OTHER MASONRY/PAVING1/10/20273/19/202703920000
90
7.1Patios1/10/20273/13/2027036000OpenMedium00
91
7.2Exterior Stairs1/11/20273/14/2027036000OpenMedium00
92
7.3Masonry Chimneys1/14/20273/15/2027036000OpenMedium00
93
7.4Fireplaces/Hearths1/14/20273/15/2027036000OpenMedium00
94
7.5Driveway1/14/20273/15/2027036000OpenMedium00
95
7.6Walkways1/15/20273/18/2027036000OpenMedium00
96
7.7Other1/16/20273/19/2027036000OpenMedium00
97
8ROUGH FRAMING1/18/20274/1/202704160000
98
8.1Sill & Seal1/18/20273/21/2027036000OpenMedium00
99
8.2
Steel/Wood Carrying Beam, Lolly Columns
1/21/20273/22/2027036000OpenMedium00
100
8.3Floor Framing1/21/20273/22/2027036000OpenMedium00