FGHJKLMNPQRSXY
1
subrecipient_state
subapplication_benefitting_counties
subapplication_status
status_clean
subrecipient_name
recipient_name
primary_activity_type
project_type_simplifiedsubapplication_description
Total obligated
project_amount
federal_share_requested
Initial Obligation Date
Initial Obligation Fiscal Year
2
FloridaGILCHRISTClosedFunded
GILCHRIST COUNTY
205.8: Retrofitting Public Structures - Wind
Wind Retrofit
THIS PROJECT WILL RETROFIT COUNTY OWNED AND ELECTRICAL FACILITIES AT HART SPRINGS PARK. THE RETROFIT WILL BE A PHASED PROJECT.
PHASE 1 COST ESTIMATE - $3,500 (ENGINERRING DESIGN)
FEDERAL SHARE REQUESTED - $2,625 (75%)
STATE SHARE - $437 (12.5%)
LOCA MATCH - $438 (12.5%)

PHASE 2 COST ESTIMATE - $31,500 (CONSTRUCTION)
WORK SCHEDULE - APPLICANT ESTIMATE WORK WILL BE COMPELTED WITHIN 14-16 MONTHS.
ALTERNATIVES CONSIDERED:
1. NO ACTION - IF THE ELECTRICAL FACILITIES ARE NOT RETROFITTED, THEN THE ELECTRICAL JUNCTION BOXES AND ELECTRICAL FACILITIES WILL CONTINUE TO BE DESTROYED BY FLOOD WATERS.

2. REROUTE UTILITY ELECTRICAL LINES - CURRENTLY THE UTILITY POWER LINE RUNS THROUGH THE PARK. AN ALTERNATIVE WOULD BE TO REROUTE THE LINES AROUND THE PARK AND CREATE A SINGLE DISTRIBUTION LINE INTO THE PARK. THIS ALTERNATIVE WAS DETERMINED TO BE EXTREMELY EXPENSIVE AND COST-PROHIBITIVE.
$ 18,837 $ 25,116 $ 18,837 11/15/19992000
3
FloridaLEONClosedFundedTallahasseeStatewide
400.1: Utility Protective Measures (Electric, Gas, etc.)
Utility and Infrastructure Protection
The City of Tallahassee proposes a phased project to design and install an underground electrical feed from an alternate electrical substation to Pump Station 149 and to elevate an existing transformer. The pump is located at 3301 Springhill Road, Tallahassee, FL 32305. Phase I includes engineering, design and permitting, and Phase II will include the actual construction of all mitigation activities. The project will reduce the impact of power loss during and after severe weather events, as experienced during Hurricane Hermine, allowing Pump Station 149 to fully function. The project will also reduce the risk of flooding for the pump station's transformer. This is a review for Phase I approval. When completed, the applicant will need to provide designs and construction documents for Phase II review. Activities will be completed in strict compliance with Federal, State and Local Rules and Regulations.
$ 627,238 $ 836,318 $ 627,238 10/5/20172018
4
FloridaPALM BEACHApprovedFundedPalm BeachStatewide
400.1: Utility Protective Measures (Electric, Gas, etc.)
Utility and Infrastructure Protection
The Town of Palm Beach proposes to bury overhead utility infrastructure, consisting of electrical, telephone, and cable communications in the north area of town that consists of properties between Country Club Road south to Southland Road and the south area of town that consists of properties between South Lake Drive and Hibiscus Avenue, from Peruvian Avenue to Royal Palm Way, and the properties between the Intracoastal Waterway and the Atlantic Ocean, from Royal Palm Way to Seaspray Avenue, in the Town of Palm Beach FL 33480.

The Town of Palm Beach is predominantly served with electric and communications services through a network of overhead wires mounted to an estimated 2,000 wood or concrete poles. There are approximately 37 pole-miles of overhead infrastructure within the Town limits. The removal of utility poles and overhead lines provides increased survivability for wind storms and improved safety benefits by reducing the potential of hazardous conditions occurring in the event of natural disasters. Severe wind events can cause poles and/or overhead lines to fall and impact property and possibly cause live electric lines to be exposed. Downed electric lines and vegetation overgrowth onto electric lines pose a potential threat of property fire and injury due to electric shock and can restrict ingress and egress of residents and emergency services.

The project shall provide protection against a 170 MPH winds or the wind speed protection and impact requirements indicated by the effective Florida Building Code at the time permits are issued.
$ 8,465,355 $ 17,881,831 $ 8,465,355 9/27/20192019
5
FloridaMONROEApprovedFunded
FLORIDA KEYS ELEC CO-OP
Statewide
400.1: Utility Protective Measures (Electric, Gas, etc.)
Utility and Infrastructure Protection
SOWC: Florida Keys Electric Cooperative proposes to protect 115 water crossing transmission poles highly vulnerable to a number of natural forces due to their location in a saltwater environment by installing a Galvanic Cathodic Protection System. This jacket technology would be fitted to the base/caisson of a pole and the zinc/sacrificial anode system would be activated and tested to ensure proper operation. The proposed project, will mitigate the corrosion and reinforce the structures to provide a measurable increase in localized strength and an added measure of protection of natural corrosive effects. This project will greatly reduce the risk of a failure of one or more transmission structures, thereby avoiding a significant power outage to all of FKEC¿s system and an estimated 50 percent of Florida Keys energy services system. The project will provide protection against a 70-year event. Activities will be completed in strict compliance with Federal, State and Local Rules and Regulations. *This is a review for the SOWC, for a complete list of locations, attachments, and
applicable conditions refer to the EHP review conducted for 4337-0228* - plargo - 05/18/2021 15:52:26 GM
$ 7,940,297 $ 11,092,313 $ 7,819,730 3/6/20202020
6
FloridaMONROEApprovedFunded
KEY WEST UTILITY BOARD
Statewide
400.1: Utility Protective Measures (Electric, Gas, etc.)
Utility and Infrastructure Protection
KEYS Energy Services proposes utility mitigation activities for its transmission poles beginning immediately north and east of the north end of Seven Mile Bridge in Marathon Florida, running roughly parallel to U.S 1 (Overseas Highway) south and west to Key West Florida. Project affects zip codes: 33050, 33040 and 33042.

The project proposes to protect one hundred and nineteen (119) water crossing transmission poles highly vulnerable to several natural forces due to their location in a saltwater environment by installing a Galvanic Cathodic Protection System. This jacket technology will act to mitigate the structural steel within concrete utility poles from damage caused by the natural forces interacting with these poles due to their location within the marine environment. This protection is accomplished by both enveloping the base(s) of the pole(s) and by drawing the weakening effects of water and salt air away from the internal structural steel and towards the GCP anodes. As a result, the poles are more resistant to the natural hazards that would otherwise work to cause damage and ultimately failure, resulting in a more resilient electrical grid for southern Monroe County. Taking this action will also eliminate the need for frequent repairs and emergency replacements as the GCP will completely encompass and protect the base of the poles, the most vulnerable element of the poles and one that is vital to their overall integrity and functioning.

The project will provide protection against a 70-year event. Activities will be completed in strict compliance with Federal, State and Local Rules and Regulations.

$ 5,595,016 $ 7,193,354 $ 5,395,016 7/21/20212021
7
FloridaMONROEApprovedFunded
FLORIDA KEYS ELEC CO-OP
Statewide
400.1: Utility Protective Measures (Electric, Gas, etc.)
Utility and Infrastructure Protection
Florida Keys Electric Cooperative proposes utility mitigation activities for its transmission poles located in the Sea Oats Area of Lower Matecumbe Key in the Village of Isla Morada, FL 33036. The proposal is to Project consists of the relocation and replacement of thirty-seven (37) transmission poles and three (3) distribution pole structures for new material poles with a 3-phase transmission circuit. The project includes installation of concrete drilled pier foundations, installation of galvanized steel monopole deadened structures, installation of round spun concrete poles and installation of cylinder pile foundation in water. The total length of this project is roughly 2 miles and is necessary to mitigate erosion issues, the relocation will drastically reduce the vulnerability of FKEC's transmission infrastructure. The project will provide protection against a 20-year event. Activities will be completed in strict compliance with Federal, State and Local Rules and regulations.
$ 4,835,353 $ 6,281,548 $ 4,711,161 6/21/20212021
8
FloridaMONROEApprovedFunded
FLORIDA KEYS ELEC CO-OP
Statewide
400.1: Utility Protective Measures (Electric, Gas, etc.)
Utility and Infrastructure Protection
Florida Keys Electric Cooperative proposes utility mitigation activities for its transmission poles located Northeastern Monroe County, South and West along U.S. 1 to the City of Marathon, Florida 33001, 33036, 33037, 33050, 33051, 33052, and 33070.

The proposal is to upgrade eighty two (82) of its distribution poles, currently relying on guy-wire anchoring systems, with stand-alone, self-supporting ductile iron poles. The protection provided by the proposed project will result in a higher design wind-load rating for many of FKEC's most vulnerable transmission poles. In addition to a higher design/wind load rating, the removal of the guy wires will eliminate a functional vulnerability for these particular poles. Subject to corrosive failure, and easily damaged by high winds as associated wind-driven debris, the elimination of guy-wires not only allows for a stronger, self-supporting pole system, it also eliminates the need for response calls, costly repairs, and the potential failure of non- or under-supported electrical transmission poles.

The project shall provide protection against 180 to 210 MPH winds or the wind speed protection and impact requirements indicated by the effective Florida Building Code at the time permits are issued.

$ 2,174,276 $ 2,805,520 $ 2,104,140 7/30/20212021
9
FloridaPALM BEACHApprovedFundedVillage of GolfStatewide
400.1: Utility Protective Measures (Electric, Gas, etc.)
Utility and Infrastructure Protection
MODIFIED SCOPE OF WORK:

Village of Golf proposes to bury underground the power distribution and telecommunication lines serving the community of Village of Golf, Florida, 33436.

The proposal is to bury the power and telecommunication lines underground to protect the Village of Golf from power outages and fallen power and telecommunication lines during severe storms. Protecting the power lines will reduce the duration and frequency of power outages for the residents within the community.

The project shall provide protection against 170 MPH winds or the wind speed protection and impact requirements indicated by the effective Florida Building Code at the time permits are issued.
$ 1,667,767 $ 2,151,957 $ 1,613,968 3/6/20202020
10
FloridaCLAYApprovedFunded
Green Cove Springs
Statewide
103.1: Feasibility, Engineering and Design Studies;
400.1: Utility Protective Measures (Electric, Gas, etc.)
Utility and Infrastructure Protection
SCOPE OF WORK
Proposed project located in the City of Green Cove Springs, FL 32043, at N. Orange Avenue and Governors Creek, extending approximately 100 feet north and south on both sides of the creek.

This is a review for Phase I approval, which includes but is not limited to surveying, engineering, designing, plans preparation, permitting and bidding for the proposed project, for Phase II approval. When completed, the applicant will need to provide necessary information for Phase II review. No construction activities for this project have been approved.

Scope of work includes installation of the transmission line crossing underground, under Governors Creek, significantly reducing the exposure of the line to storm force winds that includes directional drill (bore) the line under the creek. The City of Green Cove Springs project designed to eliminate susceptibility of the electrical supply/power lines during the storm event(s).

The project will provide protection for 100-year storm event. Activities will be completed in strict compliance with Federal, State and Local Rules and regulations.

Phase II SOW:
The City of Green Cove Springs proposes to provide protection to power lines during a storm event locaqted at North Orange Avenue and governors Creek in Green Cove Springs, Florida 32043, extend approximately 100 feet north and south on both sides of the creek. The Phase II proposed scope of work includes installtion of the transmission line crossing underground, under Governors creek, significantly reducing the exposure of the line to storm force winds. The project designed to eliminate suceptibility of the elctric supply/power lines during storm events. The project shall provide protection against a 500-year storm event. Activities shall be completed in strict complinance with Federal, State and Local applicable Rules and Regulations.
$ 562,500 $ 750,000 $ 562,500 3/22/20182018
11
FloridaMONROEApprovedFunded
FLORIDA KEYS ELEC CO-OP
Statewide
103.1: Feasibility, Engineering and Design Studies;
400.1: Utility Protective Measures (Electric, Gas, etc.)
Utility and Infrastructure Protection
REVISED SOW: Florida Keys Electric Cooperative proposes utility mitigation activities for its transmission poles located Northeastern Monroe County, South and West along U.S. 1 to the City of Marathon, Florida 33001, 33036, 33037, 33050, 33051,333052, and 33070.

This is an approval for Phase I only, which includes but is not limited to surveying, engineering, design, plans preparation, permitting and bidding for the proposed project, for Phase II approval. No construction activities for this project have been approved. The proposal is to upgrade eleven (11) of its transmission poles, currently relying on guywire anchoring systems, with stand-alone, self-supporting poles. The protection provided by the proposed project will result in a higher design wind-load rating for many of FKEC¿s most vulnerable transmission poles. In addition to a higher design/wind load rating, the removal of the guy wires will eliminate a functional vulnerability for these particular poles. Subject to corrosive failure, and easily damaged by high winds as associated wind-driven debris, the elimination of guy-wires not only allows for a stronger, self-supporting pole system, it also eliminates the need for response calls, costly repairs, and the potential failure of non- or under-supported electrical transmission poles.

The project will provide protection against a 100-year event. Activities will be completed in strict compliance with Federal, State and Local Rules and Regulations.
$ 346,767 $ 7,059,492 $ 4,500,000 5/11/20202020
12
FloridaLEEApprovedFunded
LEE COUNTY ELECTRIC COOP INC
Statewide
400.1: Utility Protective Measures (Electric, Gas, etc.)
Utility and Infrastructure Protection
Lee County Electrical Cooperative proposes to install approximately 6 miles of electrical power line to connect two service areas that are currently fed radially by two sources. This will ensure that a single point failure will no longer result in loss of power to the entire service area and will eliminate or reduce the duration of an outage caused by a single point of failure.

The project shall provide protection against a 140 MPH winds (in the range of a Category 4 on the Saffir-Simpson Hurricane Wind Scale) or the wind speed protection and impact requirements indicated by the effective Florida Building Code at the time permits are issued.

This is a review for Phase I approval, which includes but is not limited to surveying, engineering, designing, plans preparation, permitting and bidding for the proposed project, for Phase II approval. When completed, the applicant will need to provide necessary information for Phase II review. No construction activities for this project have been approved.
$ 184,566 $ 1,312,331 $ 984,248 9/26/20192019
13
FloridaLEEApprovedFunded
LEE COUNTY ELECTRIC CO-OP INC
Statewide
400.1: Utility Protective Measures (Electric, Gas, etc.)
Utility and Infrastructure Protection
Lee County Electrical Cooperative Inc. Proposes to install an updated transmission line in Lee County, FL 33903. The location of the purposed updated line will start at LCEC¿s tropic isles substation and run east along Hancock Bridge Parkway, turn north on Orange Grove Boulevard to Pondella Road, then run east to U.S 41, then turn northwest and terminate at LCEC¿s substation.

The proposal is to purchase and install 3.2 miles of 138,000-volt transmission line consisting of 41 transmission poles. This project will provide a redundant path around sections of the radial transmission line, reducing the duration and severity of outages.

This is an approval for Phase I only, which includes but is not limited to surveying, engineering, design, plans preparation, permitting and bidding for the proposed project, for Phase II approval. No construction activities for this project have been approved.

The project will provide protection against a 120 mph wind. Activities will be completed in strict compliance with Federal, State and Local Rules and Regulations
$ 110,459 $ 1,775,195 $ 1,331,396 11/19/20192020
14
FloridaCOLLIERApprovedFunded
LEE COUNTY ELECTRIC CO-OP INC
Statewide
103.1: Feasibility, Engineering and Design Studies;
400.1: Utility Protective Measures (Electric, Gas, etc.)
Utility and Infrastructure Protection
Lee County Electrical Cooperative proposes to reinforce with rip-rap 22 utility poles along County Road 92 in Collier County, Florida 34114. This activity will stabilize the wet soil and prevent structural failure of the pole during a severe wind event. The poles being functional and available as a back feed will reduce the duration of electrical utility outage in the event of an outage due to severe weather. The project shall provide protection against a 140 MPH winds (in the range of a Category 4 on the Saffir-Simpson Hurricane Wind Scale) or the wind speed protection and impact requirements indicated by the effective Florida Building Code at the time permits are issued.
$ 31,200 $ 297,066 $ 222,800 10/17/20192020
15
FloridaMONROEObligatedFunded
Utility Board of the City of Key West dba Keys Energy Services
Florida Division of Emergency Management - Mitigation
402.3: Infrastructure Protective Measures
Utility and Infrastructure Protection
The focus of this project is the protection and resiliency of critical infrastructure by harden the electrical services between critical government facilities and the substations that power them. The solution is to reduce or eliminate pole failure which increase downtime during severe storm and/or man-made events by replacing 491 non-storm hardened distribution poles with ductile iron poles. The 491 wood distribution poles do not meet PSC wind load standard of 150 mph, the goal of which is to be more resistant to damage from high winds and associated debris from tropical systems and other storms. The wooden distribution poles tend to fail due to either rot and decay in the sub-tropical environment of the Florida Keys or rust/corrosion of the guy- wires. This is exacerbated by tropical weather events, which place further loads on the already degrading poles and supports.
KEYS began transitioning from non-storm hardened and concrete poles to ductile poles in 2015. The ductile poles are completely resistant to rot, insects and woodpeckers and require less maintenance. They are made of 96 percent recyclable materials and are 100 percent recyclable and do not leach harmful chemicals.

The replacement of the 491 non-storm hardened poles with ductile poles will:
¿ Mitigate damage from events having winds of up to 150 mph
¿ Will reduce power outage time by eliminating the need to replace or stand up leaning poles making KEYS and the community more resilient
¿ Will reduce maintenance costs such as:
o Repair of rotting poles
o Ductile iron poles are completely resistant to rot, insects, and woodpeckers, so they require less maintenance than other poles.
o With a 75-year plus expected service life and low maintenance requirement, McWane¿s Poles have a lower life cycle cost than other poles.
o Ductile iron poles are engineered and manufactured for consistent strength and appearance, and, unlike wood, they will not shrink or warp over time.
o Inspection time will be reduced
¿ Reduce installation/replacement time in the event that a catastrophic event, beyond the Level of Protection (LOP) for this design does occur.
¿ Ductile iron poles weigh less than wood and much less than concrete poles and are much easier to drill than steel and concrete.
$ 4,467,345 $ 5,956,460 $ 4,467,345 9/24/20202020
16
FloridaLIBERTYApprovedFunded
TALQUIN ELECTRIC COOPERATIVE, INC.
Statewide
400.1: Utility Protective Measures (Electric, Gas, etc.)
Utility and Infrastructure Protection
Talquin Electric Cooperative proposes a utility mitigation project in Liberty County. The total project covers approximately 10.2 miles located entirely in Talquin¿s existing electrical right-of-way. The project area starts approximately 500 feet Northeast from the intersection of FL-65 N and FL-20 E in Hosford, Florida 32334, and ends approximately 1,000 feet South from the intersection of Hoecake Road and FL-20 E in Bristol, Florida 32321.

The applicant proposes to harden the existing electrical system and provide a secondary source of electrical power to the communities served by the Bristol Substation. These communities are particularly vulnerable to outages, as they are radially served from a single distribution source. The proposal is to upgrade the existing 69kV line with a three-phase conductor, upgrade approximately 24 existing wooden poles with new higher-rated class wooden poles and install approximately 23 new wooden poles to support the increased conductor size and shorten the length between each span. Additionally, breakers / switches will be installed to create a double circuit, which will allow the Bristol Substation to be fed from either the Hosford Substation or the Lake Talquin Substation. The protection provided by this backfeed loop will reduce service restoration time during storm-related outages and minimize the number of customers affected in these vulnerable Liberty County communities.

The project shall provide protection against 133 MPH winds or the wind speed protection and impact requirements indicated by the effective Florida Building Code at the time permits are issued.
$ 656,555 $ 842,073 $ 631,555 6/8/20222022
17
18
19
20
21
Total obligated: $ 37,683,531
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
80
81
82
83
84
85
86
87
88
89
90
91
92
93
94
95
96
97
98
99
100