1 | Beryllium | |||||
2 | ||||||
3 | Project Statistics | |||||
4 | Total Beryllium Projects | 52 | ||||
5 | Total Offset 0 Projects | 6 | ||||
6 | Total Offset 1 Projects | 14 | ||||
7 | Total Offset 2 Projects | 32 | ||||
8 | ||||||
9 | M1 Statistics | |||||
10 | Description | Progress | Projects Completed | Projects Started | Projects Unreported | Projects Late |
11 | All Projects | 100.00% | 52 | 0 | 0 | 24 |
12 | Offset 0 Progress | 100.00% | 6 | 0 | 0 | 1 |
13 | Offset 1 Progress | 100.00% | 14 | 0 | 0 | 6 |
14 | Offset 2 Progress | 100.00% | 32 | 0 | 0 | 17 |
15 | ||||||
16 | M2 Statistics | |||||
17 | Description | Progress | Projects Completed | Projects Started | Projects Unreported | Projects Late |
18 | All Projects | 99.76% | 51 | 1 | 0 | 21 |
19 | Offset 0 Progress | 100.00% | 6 | 0 | 0 | 1 |
20 | Offset 1 Progress | 100.00% | 14 | 0 | 0 | 4 |
21 | Offset 2 Progress | 99.61% | 31 | 1 | 0 | 16 |
22 | ||||||
23 | M3 Statistics | |||||
24 | Description | Progress | Projects Completed | Projects Started | Projects Unreported | Projects Late |
25 | All Projects | 90.61% | 33 | 18 | 1 | 28 |
26 | Offset 0 Progress | 94.12% | 4 | 2 | 0 | 1 |
27 | Offset 1 Progress | 92.86% | 9 | 5 | 0 | 8 |
28 | Offset 2 Progress | 88.97% | 20 | 11 | 1 | 19 |
29 | ||||||
30 | M4 Statistics | |||||
31 | Description | Progress | Projects Completed | Projects Started | Projects Unreported | Projects Late |
32 | All Projects | 87.26% | 40 | 7 | 5 | 28 |
33 | Offset 0 Progress | 100.00% | 6 | 0 | 0 | 1 |
34 | Offset 1 Progress | 89.73% | 11 | 2 | 1 | 10 |
35 | Offset 2 Progress | 83.79% | 23 | 5 | 4 | 17 |
36 | ||||||
37 | M5 Statistics | |||||
38 | Description | Progress | Projects Completed | Projects Started | Projects Unreported | Projects Late |
39 | All Projects | 81.54% | 39 | 5 | 8 | 25 |
40 | Offset 0 Progress | 100.00% | 6 | 0 | 0 | 2 |
41 | Offset 1 Progress | 88.57% | 11 | 2 | 1 | 9 |