ProjectOwner
YearComplete
ScopeBike PlansLast UpdatedLatest Update
3
Bryant Ave S, phase 2City of Minneapolis2023Reconstructionelevated 2-way 8' bikeway from 42nd to Lake (next to 6' sidewalk)10/23/23complete!
4
2nd St SCity of Minneapolis2023Road Repavingin-street curb-protected 2-way bikeway from 3rd Ave S to 13th Ave S. 11/5/23complete!
5
Central/3rd St bridgeMnDOT2023Reconstructionbarrier-protected, 13' multiuse paths on both sides.10/28/23complete!
6
Plymouth Ave bridge over 94
MnDOT2023Road Repavingin-street curb-protected bike lanes on both sides. Previously only separated from car lanes by plastic delineators12/23/23complete!
7
37th Ave NECity of Minneapolis2023Reconstructionmulti-use sidewalk-level path on the north side of the street between Central Ave and Stinson Blvd12/8/23complete!
8
Marshall St NEHennepin County2023Road Repavingon-street bike lanes (mostly with painted buffer) from Lowry Ave to St. Anthony Pkwy, as part of mill-and-overlay repaving. 10/23/23complete!
9
Dowling Ave N / 33rd Ave NCity of Minneapolis2024Reconstruction
sidewalk-level 10' 2-way bikeway on south side of Dowling from Lyndale to Upper Harbor Terminal, 10-12' sidewalk-level shared used path on 33rd east of N 2nd St
6/1/24complete!
10
29th Ave NECity of Minneapolis2024Road Repaving2-way 10' bikeway with 2' buffer, from Central to Stinson8/1/24complete!
11
Park and Portland phase 1Hennepin County2024Road Repaving
reducing car lanes from 3:2 on both Park and Portland from Washington to E 17th St, adding buffer space for bike lanes between both parked cars and moving car traffic
8/1/24complete!
12
N Washington AveCity of Minneapolis2024Road RepavingConcrete curb protection added for on-street bike lane along East side of N Washington from Dowling to N 41st Ave9/1/24complete!
13
Lake St (E Bde Maka Ska to Humboldt)
​2024Reconstruction2-way protected on-street bikeway from E Bde Maka Ska Pkwy to Humboldt Ave S9/16/24complete!
14
Osseo RoadHennepin County2024Reconstructionnew 10' trail along southwest side of Osseo Rd from 44th to 49th Ave N 10/11/24complete!
15
Hennepin Ave S (Lake to 26th)
City of Minneapolis2024Reconstructionelevated 2-way 10' bikeway. Lake to 26th in 2024, 26th to Bryant in 2025. 10/17/24
essentially complete
16
Green Central Safe Routes to School
City of Minneapolis2024New Bikeway1.3 miles of walking and bicycle paths on East 34th Street and 10th/11th Avenues South10/17/24
essentially complete
17
Lowry Ave NE (Washington to Central)
Hennepin County2024Reconstruction8' multi-use path along north side from Washington St NE to Johnson St NE. Washington to Central in 2024, Central to Johnson in 202510/22/24complete!
18
Hiawatha-LakeHennepin County2024Reconstructionoff-street bike path on north side of Lake from 22nd Ave to Snelling (~ 3 blocks)10/26/24complete!
19
1st Ave NE / E Hennepin AveHennepin County2024Reconstructionone-way mix of elevated paths and protected bike lanes from Main St NE to 7th/8th St SE, plus an elevated two-way bike path on west side of Main St11/17/24complete!
20
4th St SE (from 35W to Oak St SE)
Hennepin County2024Reconstruction1-way concrete-buffered bike lane on 4th. 1 block of 2-way protected bikeway on Oak St SE north of 4th St SE to be built as well.11/17/24
nearing completion
21
Trail Connection: 26th Ave N and Ole Olson Park
MPRB2024New Construction1,000-foot trail connecting 26th Ave N bikeway to Ole Olson Park and the trail that goes south along the river. Target Nov 2024 for end of construction?10/17/24
construction continues
22
Johnson St & 14th Ave NECity of Minneapolis2024Repaving/Restriping
4:3 lane conversion on Johnson from 14th Ave to The Quarry, with quick-build 2-way delineator protected bikeway adjacent to west curb line. Made permanent with concrete in 2026 as part of Safe Streets for All? 14th Ave to become new bike boulevard
11/17/24
nearing completion
23
University Ave (from 35W to Oak St SE)
Hennepin County2025Reconstruction
2-way curb-protected bikeway on south side of University Ave. 2 more blocks of 2-way protected bikeway on Oak St SE will also be built by the county/city during this project or soon after.
10/17/24
split 2024 construction from 2025
24
Hennepin Dunwoody Bikeway
City of Minneapolis2025New Bikewayprotected bikeway from Linden Ave to N 12th St10/23/24
construction continues, 1+ blocks already complete
25
Hennepin Ave S (26th to Bryant)
City of Minneapolis2025Reconstructionelevated 2-way 10' bikeway. Lake to 26th in 2024, 26th to Bryant in 2025. 4/1/24
split 2024 construction from 2025
26
1st Ave S (Lake to Franklin)City of Minneapolis2025Reconstruction
two-way elevated bike path from Franklin to Lake St, plus a painted 2-way lane from Lake to 31st to connect with 31st bikeway. Construction to begin in 2024.
10/11/24
construction continues
27
24th St ECity of Minneapolis2025New Bikewayreplace existing one-way painted bike lanes with a 2-way curb-protected bikeway along the north side of the street between Portland and Cedar7/11/23
28
Whittier Safe Routes to School
City of Minneapolis2025New Bikewaylikely 2:1 traffic lane conversion with protected 2-way bikeway on 28th from Lyndale to Blaisdell. Unclear if 26th would see any improvements.11/4/24
15% design: proposed concept layout
29
Lowry Ave NE (Central to Johnson)
Hennepin County2025Reconstructionmulti-use path along north side from Washington St NE to Johnson St NE. Washington to Central in 2024, Central to Johnson in 20257/13/24
split 2024 construction from 2025
30
E Hennepin Ave repavingHennepin County2025Repaving/Restriping4:3 car lane conversion from 35W to Industrial Blvd. New buffered bike lanes to be added. 6/3/24new
31
Upper Harbor SiteMPRB2025New Constructionmulti-use path along river from 33rd Ave to Dowling. (Paths on 33rd Ave and Dowling were mostly completed in 2023.)10/19/24changed to 2025
32
Graco ParkMPRB2025New Constructiontrail underpass so users do not need to cross Plymouth Ave N9/25/24
trail through Graco Park complete, underpass work has not yet started
33
Nokomis-Hiawatha Regional Park Connectivity Improvements
MPRB2025New Constructionnew bikeway connection along Cedar Ave bridge over Lake Nokomis plus some a handful of other improvements and realignments11/14/23
34
E 42nd StCity of Minneapolis2025Repaving/Restriping
Concept removes 23 parking spots in north side of street so that there's a continuous painted bike lane from Cedar to Minnehaha. Closes what was previously a 4-block bike lane gap at 28th Ave
35
Nicollet Reopening (Kmart site)
City of Minneapolis2025New Constructionthe 4 concepts *do not* include dedicated bike facilities on Nicollet, but there could still be a bikeway diagonally through the 2-block site3/4/24
36
Franklin AveHennepin County2026Reconstructionpreliminary design has one-way bikeways above-the-curb between Lyndale and Chicago3/4/24
updated based on Feb 2024 PACBAC presentation
37
Northside Greenway Phase 1
City of Minneapolis2026​neighborhood greenway along Humboldt/Irving Ave N for 2.5 miles from 44th Ave N to 26th Ave N7/1/23
38
Hennepin Ave bridge over Mississippi
Hennepin County2026​TBD, "writing grant application for additional funding to modify the bridge deck's geometry and improve transit, bicycle and pedestrian access"7/1/23
39
1st Ave S (Grant to Franklin)City of Minneapolis2026Reconstructiontwo-way elevated bike path from Grant to Franklin.4/12/24
moving up by 2 years
40
Cedar AveHennepin County2026ReconstructionPreferred concept from 15% design would have a protected 2-way bikeway on the east side of Cedar from 24th to 28th. 2/7/24
updated based on Feb 2024 PACBAC presentation
41
Lyndale Ave SHennepin County2027Reconstruction2 of the 3 October 2024 survey options include a protected bikeway from I-94 to 29th11/4/24
shifted from 2026 to 2027
42
2nd St NCity of Minneapolis2027​2-way curb-protected cycletrack from Plymouth to Dowling (2.2 miles)7/1/23
43
Lowry Ave NE phase 2Hennepin County2027Reconstruction8-10' shared path along north side of Lowry from Marshall to Washington. Unclear plans within one block of University.4/29/24new
44
4th and University (from Central Ave to 35W)
MnDOT2027Road RepavingCurb-protected one-way bikeways. Scope was expanded in 2024 to include the bridges over 35W. 7/22/24
received funding through 2024 regional solicitation
45
3rd Ave S (1st to Washington)
MnDOT2027New Bikewayprotected bikeways + bumpouts from 1st St to Washington. Currently just paint and a few flex posts. (Project number 2710-60)3/4/24
46
Blue Line Extension connections
Met Council2027New Bikeway
2.5 miles of new protected bikeways including greenways/transit malls (3 blocks on 10th Ave N and 9 blocks on 21st Ave N including new bridge over I-94) in addition to reconstruction of high injury streets, new crossing medians, sidewalk and intersection improvements
8/5/24
municipal consent 30% design plan
47
9th / 10th St SCity of Minneapolis2027​
street-level one-way curb-separated bikeways on each, from 2nd Ave N to 14th St E (2.26 miles in total). Curb extension and protected intersection elements.
11/4/2415% design
48
University AveMnDOT2027Reconstructionbikeway facilities on both sides of University on the two blocks from Central to 1st Ave, as part of reconstruction from Central to 9th Ave NE7/22/24
received funding through 2024 regional solicitation
49
Park and Portland phase 2Hennepin County2027​
TBD, maybe "bike lane protection at intersections", "relocating the parking lane to provide additional protection for people biking". I-94 to Midtown Greenway, 38th to 42nd
10/23/23
50
21st Ave S Safe Routes to School
City of Minneapolis2027​
Lake St (or possibly 28th?) to 43rd St S (2 miles). Connects 3 MPS schools: South High, Folwell Elementary & Adult Education South Campus •Connects 3 parks: Corcoran, Sibley, Lake Hiawatha
3/5/24
Updated to 2027, rather than "2026-2029" based on Dec 2023 state document
51
Nicollet Ave bridge over Minnehaha creek
City of Minneapolis2027​new protected bikeway7/1/23
52
Northside Greenway Phase 2
City of Minneapolis2028​neighborhood greenway on Irving/Humboldt/Elwood Ave N for 1.9 miles from 26th Ave N to 4th Ave N/Van White Memorial Blvd7/22/24
received funding through 2024 regional solicitation
53
Hayes St NE Safe Routes to School
City of Minneapolis2028​
1.6 mile neighborhood greenway on Hayes from 22nd Ave to 33rd Ave NE, 33rd Ave NE from Hayes St NE to Ulysses St NE, and Ulysses St from 33rd Ave NE to Johnson St NE
7/22/24
received funding through 2024 regional solicitation
54
Marshall/Main St NE (1st Ave NE to Lowry)
Hennepin County2028ReconstructionTBD, likely 2-way protected bikeway. According to a county transportation planner, planning and public engagement likely to start in 2025.8/15/24
BAC presentation showed that completion year is 2028, not 2027
55
Cedar Lake Road BridgeCity of Minneapolis2028​2' raised concrete barrier will separate vehicle traffic from bike/ped lanes, as part of bridge replacement7/22/24
received funding through 2024 regional solicitation
56
18th Ave NE Trail GapCity of Minneapolis2028New Constructionbike trail connection between Marshall and California. BNSF owns land, negotiations difficult7/1/23
57
Washington Ave SHennepin County2028​one-way dedicated bikeways on Washington from 5th Ave S to 11th Ave S7/22/24
received funding through 2024 regional solicitation
58
Park and Portland phase 3City of Minneapolis2028​above-curb dedicated bike paths (separate from sidewalks) on 1.1 miles of Park and Portland from Midtown Greenway to 38th Street7/22/24
received funding through 2024 regional solicitation
59
Vision Zero / Safe Streets For All
City of Minneapolis
2026-2029
​
"new protected bicycle lanes along 4 miles of its high-injury network" + pedestrian refuge islands, systematic traffic signal Proven Safety Countermeasures at 526 intersections, road diets, intersection medians
12/15/23
60
Grand Rounds Missing LinkMPRB
2026-2029
New Construction$12.35M funding from state for planning, design, acquisition, and construction4/20/24
changed timeline from TBD to 2026-2028
61
7th St NCity of Minneapolis2029​"improved bicycle facilities" from 10th St N to E Lyndale Ave N7/1/23
62
13th Ave NECity of Minneapolis2029​
low-stress bikeway from Water St NE to Marshall St NE. On AAA network map. Public Works budget request mentions the addition of "bicycle facility" as part of the entire right-of-way being reconstructed from Water St to Marshall St.
9/24/23
63
Pleasant Ave Safe Routes to Schools
City of Minneapolis2029​
neighborhood greenway on Pleasant from 34th St W to 49th St W, and along 49th St W from Pleasant to Nicollet, with protected bikeways and other traffic calming features
7/22/24
received funding through 2024 regional solicitation
64
Chicago Ave SCity of Minneapolis2029​"improved bicycle accommodations within project limits" from Lake to 37th St E7/1/23
65
34th St E/WCity of Minneapolis2029​AAA bikeway on 34th Ave (and small segments on 35th) from Hennepin Ave to Hiawatha Ave7/22/24
received funding through 2024 regional solicitation
66
Central Ave NEMnDOT2029​4:3 conversion with sidewalk-level bikeways from the Mississippi River to 37th Ave11/4/24
15% design presentation
67
1st Ave NCity of Minneapolis2029​
AAA from Washington Ave N to 8th St N, but there had been a sort of "understanding" among some downtown stakeholders that bike facilities would be removed if they were added to Hennepin.
68
42nd St ECity of Minneapolis
2028-2030
​All Ages and Abilities bikeway -- protected bikeway physically separated from motor vehicle traffic.4/8/24new
69
38th St E (Blaisdell to Park)City of Minneapolis2030​consideration of bicycle accomodations through community engagement, from Blaisdell to Park7/1/23
70
3rd St SCity of Minneapolis2030​"improved bikeway" from Norm McGrew Pl to Hennepin Ave7/1/23
71
31st St ECity of Minneapolis2030​on AAA network, likely to be protected bikeway from Blaisdell to Bloomington7/1/23
72
Dowling Ave NCity of Minneapolis2030​"bicycle accommodations" from Thomas Ave to Lyndale Ave7/1/23
73
2nd St NECity of Minneapolis2030​AAA network map marks this as a planned low-stress bikeway in the long-term, likely to be protected bikeway from Broadway to Lowry. 9/22/23
not funded in mayor's 2024 budget, so the timing and scope is currently unclear
74
7th St SCity of Minneapolis2030​on AAA network as a connector or long-term low-stress bikeway. 7/22/24
received funding through 2024 regional solicitation
75
38th St E (10th Ave S to 23rd Ave S)
City of Minneapolis2030​consideration of bicycle accomodations through community engagement, from Blaisdell to Park7/1/23
76
Park and Portland Phase 4​TBD​from 42nd to 46th. Part of 2024 HSIP grant application.4/29/24new
77
38th & Chicago (George Floyd Square)
City of MinneapolisTBDReconstruction
Nov 2024 recommended concept includes 2-way protected bikeway on 38th from Park Ave to 10th Ave, 1-way protected bikeways on Chicago from 38th to 39th.
11/4/24new
78
3rd Ave S bus projectCity of MinneapolisTBD​3rd Ave would get protected bikeways during reconstruction if it is chosen as the bus alternative to Nicollet Malll10/11/24new
79
North 94 bike/ped bridgeMnDOTTBD​possible new bike/ped bridge over I-94, just north of Lowry. Part of environmental impact reduction for highway project.
80
Hwy 55/Olson Memorial/6thMnDOTTBD​Design alternatives presented in March 2024 include protected bikeways.3/5/24
81
Short Line Bridge (Midtown Greenway extension)
​TBDNew Constructionstate funding for study/design in 2023 session7/1/23
82
Southside Greenway​TBD​
A group has been advocating for a continuous bike greenway from Gold Medal Park (by the river) to Diamond Lake Park. Many sections already built or planned, but they're advocating for planning and funding to close gaps.
8/16/24
83
Great Northern Greenway river crossing
MPRBTBDNew Construction
Open house events and on-site tours in Jan/Feb 2024 for community engagement re: a new ~$30m bridge north of the BNSF bridge. Timing depends on funding, would take at least 3 years if full funding was available now. Previous efforts have been complicated by difficulties negotiating with BNSF to place at trail on the existing bridge, the age of the bridge, and modifications required to safely add a trail next to an active freight line.
2/1/24
84
​​
85
2 new access ramps for Midtown Greenway
​​1) from Hennepin Ave as part of The Mall project, 2) from Nicollet/Kmart site4/25/24
removed Soo Line ramp after MPRB voted against the plan
86
2 new access ramps for Cedar Trail (downtown)
​​1) from North Loop Green towers near 5th St, 2) from 2nd St, completed in Spring 20244/25/24
both ramps complete