Tiny-ish House Budget Costs. Brattleboro, VT Caleb Clark
 Share
The version of the browser you are using is no longer supported. Please upgrade to a supported browser.Dismiss

View only
 
ABCDEFGHIJKLMNOPQRST
1
NOTE: This spread sheet was Frozen Oct 1, 2012, one year after first tenant moved in to our tiny-ish house and started paying rent (and still is BTW.) We froze this sheet at the point where the outside shed roof and fence were finally done. All further costs count as maintenance to us. Total cost including first year completion of stray jobs to full plan completion was $53,481.00 for a per square foot cost of $134 (all inclusive, appliances, etc.). Rent is now $825/month utilities included except propane heat/dryer/cook stove. This comes out to a about a 12% Return on Investment a year for a 8 year payback, including 2 months vacancy a year and maintence. So far, no vacancies. - Caleb and Laura, Oct. 1, 2012.
2

3
ItemEstimatePlanPaidDIY SaveMORE INFO: http://www.tinyurl.com/tinyhousevt
4
Town Plumbing Hook Up Fee2,00035351,965Thought was $2000.00! but only two bedroom home, with one new bedroom vs. 3bed to 4.
5
Architect1,5001,5001,5000Flat. Only takes a few of these kind of jobs. We're blogging to get a lot of press to help him get more business
6
Permit Zoning & hearing250305305(55)
7
Permit Fire25016816882
8
Insurance for fire, vandalism0000Just increased ours with higher monthly for 50K separate building
9
Misc50138190(140)Lunches, mail comp to John, dump fee. front door lock 28. Vaccume bags, vapor barrier
10
Books30202010
11
General Contracting12,0000012,000Estimate 5hrs a week for 6 Months for Laura and Caleb.
12
BAAH local town grant(3,000)(3,000)(3,000)
13
Effeciency Vermont rebates(1,500)(1,700)0Version 2.5 changed things so we don't get a refund. HERS rating had to be below 60, we're 72 HERS due to electric hot water, bathroom fan, tier 1 fridge, etc. Very low blower door rating though, 188CFM on the "C" ring
14
Renew salvage(100)(100)(100)Renew store credit for stove and lights we didn't use.
15
Federal tax breaks? Researching.
16
Site
17
LABOR rigid foam in crawlspace50000500Laura and Caleb did this with rented impact drill
18
Foundation Concrete work (11 yards of concrete x 250)2,8002,5852,585216Brad King. Bid. Might go up or down a few dollars for rebar. 11 yards of concrete - L.F. rebar - qty of rigid insulation - qty of fill
19
Foundation and 2 trenches to house Excavation and driveway takeaway2,6002,6512,651(51)Low bid. 2 visits Can save by not doing asphalt and use as staging area then do later. 5/3 - 5/4. Pay with E*Trade check.
20
Demo Garage615703703(88)ReNew quoted $1,500 with labor. Dumpster and dump fee. 4.17 tons! Sawsall blades
21
Trenches: Conduit electric + 3/4 + rigid foam + cement200220220(20)
22
Frame to weather proof
23
12' T straps - (6)
24
Sheathing roof 22 sheets 5/8" ply wood
25
decking - 12 sheets 3/4" advantech
26
2 x 12 rafters (24) 2 x 12 x 12'
27
2 x 6 x 10' wall studs (54 )
28
2 x 8 x 10' headers (3)
29
2x6x16' plate(10)
30
2 x 4 x 16' (26) over insulation on roof - provides overhangs
31
Trim -south facade 1 x 10 x 12' (2) freize. 1 x 4 x 10' (2) corner boards. 1x8x12' (1) base. 5/4 x 4 x 10' (5) windows. 5/4 x 4 x 8' (2) door. 5/4 x 6 x 4' (1) door.
32
Trim Other Facades: 1 x 10 x 12 (6) freize. 1 x 4 x 10' (6) corner boards no base. 5/4 x 10' windows (6). 5/4 x 8' smaller windows (4).
33
Trim Roof soffit: 1 x 6 x 14' (8). 1 x 8 x 12' (4). 1 x 10 x 12' (4).
34
Trim Roof fascia: 1x4x14'(12) -4 rippedto11/2"
35
collar ties 2 x 8Can be salvaged for rustic look.
36
insulation: 2 x 8 x 1 1/2" xps rigid insulation 1400 s.f. (88 sheets).
37
Ridge beam: 2 x 12 x 12' (2)
38
Floor beam: 2 x 10 x 10' (3). 2 x 10 x 12' (3)
39
1 x 3 strapping in L.F. interior ceiling (300)
40
Interior Doors (1): interior - hollow core pre-hungRenew
41
Siding, Shiplap. 800sqft, Kerber Farms???
42
Nails/Screws/glue/bolts/nuts
43
Roofing: Metal sheets. Charcoal Gray
44
Exterior Door: Full glass fiberglass
45
Windows: Integrity Wood-Ultrex
Double Hung Windows Fiberglass 3456 (5). AND ICA 2135 Low E. No grill. (1).
46
1/2" sheetrock 1400 s.f.
47
m.r. sheetrock (bath) (350) square feet
48
ALL MATERIALS ABOVE5,5009,9199,9198215+1704. Used more materials then this list, prices went up since the first low estimate.
49
2 Used Octagon Windows replace one new bathroom window500128128372Have 2 octagon for North Side $56,and $72 Renew. .
50
Trim Paint200111111892 gallons of Bin and gloves. Walmart white paint 26
51
LABOR trim paint90000900
52
Spray foam walls and windows supplies10064643610x6>75
53
LABOR rigid foam exterior, gabe and scott didn't get30000300Laura, Caleb, David, Andrew
54
LABOR Carpenter to weather tight + extras vents, led trim, etc10,00010,00010,797
Paid: 3,307.50, 2,100.0, 2,047.50. 2205.00, 1137,00 Scott. Weather tight, with trim. "Not more, probably be able to do trim and interior walls, but not guarenteed."
55
Rigid foam Insulation, crawl space: 26 sheets, sqrews, drill, washers, caulk, foam70060960991Labor saved
56
2 x 4 x 8' interior wall studs (incl. plates) (32)165858580
57
Used 42 salvaged yellow pine 2x 8 floor joists 15' Long (16); 2 x 8 rafters (24) 2 x 8 x 12' with added rafter tails; or 2 x 8 x 14' and 2 x 10 x 16' loft floor joists (11) and for stair rails and railings. 600290290310.75 board foot yellow pine. 46 from ReNew. 235+65
58
Interior Main Space
59
Phase 2: LABOR interior walls and, interior bathroom walls + loft joists, stairs, railings, Sink and stove spaces made. Loft floor. metal roof, added new collar ties4,0004,0254,025
1995, 2030
60
Plumbing Labor and Supplies ALL.4,0004,5004,261Site, main house hookup, house all, water heater, shower, kitchen. Dale's "not more then, probably less" bid. Includes water heater and shower
61
LABOR AND SUPPLIES, ELECTRICAL, inc bathroom fan and smoke detectors6,7386,0007,250
Paid 3369 and 1812.50, 1812.50
62
LABOR AND SUPPLIES INSULATION2,0002,4002,551
63
LABOR phase III. Floor, kitchen shelves, railings, shiplap walls, window trim2,0002,103Rick to Oct. 21, $512. $362, Oct. 25. Dylan 112, 127, 127, 125, Gabe 735
64
Gas heater and Installation with tank1,4001,4001,803(403)"9K Design Load" so 11000 BTU Rinnai. $75 install stove
65
Water heater30000300On plumbing bill
66
Interior wall paint2007070130Guesstimate materials.
67
LABOR interior walls mud and paint800110110690Dylan
68
Fans (ceiling)20000200use ours
69
Flooring and bath walls Shiplap. 7007007000Shiplap
70
Poly window sills, floors1000120(20)50 minwax water poly, brushes 10
71
LABOR poly floors40000400
72
Lights50202030Renew
73
Bathroom
74
Shower30000300On plumbing bill
75
Sink100303070ReNew Salvage
76
Toilet2503535215Renew Guesstimate
77
Sink cabinate100404060
78
Light50101040Renew Guesstimate Guesstimate
79
Washer/Dryer. Stackable 20" propane Used1,200424424776Thought later purchase, but propane almost new one came at Renew
80
Kitchen
81
Counter, sink, cabinets2001001000Got Dave's used galley kitchen cheap counter and sink for free if we picked it up.
82
Refrigerator500530530(30)24" max wide. 26" max deep. Danby: DFF261WDB 9.2 CuFt. Bottom Mount Freezer, Frost Free,Crisper, 2 Glass Shelves. Central Appliance: $600.00. $500: http://www.appliancesconnection.com/i167061-danby-dff261wdb.html
83
Gas Stove, 24" four burner50000500Used our old one that came with house. Bought a new one for us.
84
Hood100101090Got renew used hood
85
Light100101090Guesstimate
86
Shed/Fence
87
Posts, pickets, metal new roof, joists600August 2012. All Canadian cedar pickets and 4x4s. No pressure treated. Shed scrap wood from Salvage.
88
Labor600August 2012
89
Radon 6mil white barrier in crawl space with piping800Months after done. Pipes in for vent, but not needed, vapor barrier enough and helped with condensation
90
TOTALS61,44847,14453,48120,035