GENERAL SUMMARY
2
3
PROJECT:6740 2ND STREET NW.DATE:7/8/2024
4
ADDRESS:6740 2ND STREET NW WASHINGTON DC 20012.
5
SCOPE:EVERYTHING
TOTAL BASE BID:
$ 695,630
6
7
DIVISION #DESCRIPTIONTOTAL COST
8
DIV-01GENERAL REQUIREMENTS ADDED BY CONTRACTOR $ -
9
DIV-02DEMOLITIONS /EXISTING CONDITIONS $ 23,805.41
10
DIV-03CONCRETE $ 21,964.96
11
DIV-05METALS $ 11,866.43
12
DIV-06WOOD, PLASTICS & COMPOSITIES $ 66,030.16
13
DIV-07THERMAL & MOISTURE PROTECTION $ 34,313.41
14
DIV-08OPENINGS $ 37,820.00
15
DIV-09FINISHES $ 185,120.16
16
DIV-10SPECIALITIES $ 1,880.00
17
DIV-11EQUIPMENT $ 9,525.00
18
DIV-12FURNISHINGS $ 34,243.67
19
DIV-22PLUMBING $ 22,856.60
20
DIV-23HEATING, VENTILATING & AIR CONDITIONING (HVAC) $ 24,633.94
21
DIV-26ELECTRICAL $ 38,461.00
22
DIV-31EARTHWORK $ 2,761.00
23
24
SUB-TOTAL $ 515,281.74
25
26
OVERHEAD & PROFIT
20% $ 103,056.35
27
INSURANCE0% $ -
28
TAX8.5% $ 43,798.95
29
BID BOND1.5% $ 7,729.23
30
CONTIGENCIES5% $ 25,764.09
31
TOTAL BASE BID $ 695,630.34
32
33
BREAKDOWN OF ITEMS
34
ITEM #DWG #CSI #/SUB DETAILDESCRIPTIONQTY.WASTEQTY. W/ WASTEUNIT UNIT LABOR UNIT MATERIAL TOTAL LABOR TOTAL MATERIAL UNIT COST TOTAL COSTTRADE COST
35
DIV-01GENERAL REQUIREMENTS
36
1Submittal Procedures10%1LS $ - $ - $ - $ -
37
2Temporary Facilities and Controls10%1LS $ - $ - $ - $ -
38
3Closeout Procedures 10%1LS $ - $ - $ - $ -
39
4Payment Procedures10%1LS $ - $ - $ - $ -
40
5Contract Modification Procedures10%1LS $ - $ - $ - $ -
41
6Maintenance & Traffic Protection 10%1LS $ - $ - $ - $ -
42
7Allowance for Site Staff (Guard, Manager Etc.)10%1LS $ - $ - $ - $ -
43
8Allowance for Permits10%1LS $ - $ - $ - $ -
44
9Allowance for Rental Equipment10%1LS $ - $ - $ - $ -
45
10Allowance for Cleaning & Protection10%1LS $ - $ - $ - $ -
46
11Misc. Allowances10%1LS $ - $ - $ - $ -
47
48
SUB-TOTAL $ -
49
50
DIV-02DEMOLITIONS /EXISTING CONDITIONS
51
52
CELLER PLAN
53
1266Remove Existing Single Door 50%5EA $ 100.00 $ - $ 500.00 $ - $ 100.00 $ 500
54
1366Remove Existing Window30%3EA $ 80.00 $ - $ 240.00 $ - $ 80.00 $ 240
55
1466Washer/ Dryer to be Removed10%1EA $ 60.00 $ - $ 60.00 $ - $ 60.00 $ 60
56
1566Remove Plumbing Fixture40%4EA $ 120.00 $ - $ 480.00 $ - $ 120.00 $ 480
57
1666Interior Wall to be Removed10430%1043SF $ 1.20 $ - $ 1,251.74 $ - $ 1.20 $ 1,252
58
1766Exterior Wall to be Removed1470%147SF $ 1.50 $ - $ 220.20 $ - $ 1.50 $ 220
59
1866Exterior Stair Wall to be Removed410%41SF $ 1.50 $ - $ 61.68 $ - $ 1.50 $ 62
60
1966Existing Stair to be Removed420%42SF $ 8.80 $ - $ 370.48 $ - $ 8.80 $ 370
61
2066Remove Countertop220%22SF $ 18.00 $ - $ 396.54 $ - $ 18.00 $ 397
62
2166Remove Flooring5540%554SF $ 2.00 $ - $ 1,108.26 $ - $ 2.00 $ 1,108
63
2266Remove Tile Flooring250%25SF $ 2.50 $ - $ 62.88 $ - $ 2.50 $ 63
64
2366Existing Concrete Slab To Be Removed5790%579SF $ 3.10 $ - $ 1,794.90 $ - $ 3.10 $ 1,795
65
2466Existing Electrical Fixture To Be Removed (579 SF)10%1LS $ 1,000.00 $ - $ 1,000.00 $ - $ 1,000.00 $ 1,000
66
67
1ST FLOOR
68
2566Remove Existing Single Door 70%7EA $ 100.00 $ - $ 700.00 $ - $ 100.00 $ 700
69
2666Remove Existing Window20%2EA $ 80.00 $ - $ 160.00 $ - $ 80.00 $ 160
70
2766Equipment to be Removed30%3EA $ 60.00 $ - $ 180.00 $ - $ 60.00 $ 180
71
2866Remove Plumbing Fixture40%4EA $ 120.00 $ - $ 480.00 $ - $ 120.00 $ 480
72
2966Existing Closet to be Removed30%3LF $ 18.00 $ - $ 47.88 $ - $ 18.00 $ 48
73
3066Existing Linen Cabinet to be Remove40%4LF $ 18.00 $ - $ 79.92 $ - $ 18.00 $ 80
74
3166Interior Wall to be Removed8670%867SF $ 1.20 $ - $ 1,040.52 $ - $ 1.20 $ 1,041
75
3266Create New Opening For Window - 5'-2" High90%9SF $ 5.00 $ - $ 43.40 $ - $ 5.00 $ 43
76
3366Create New Opening For Door & Sidelight - 7'-2" High410%41SF $ 5.00 $ - $ 204.26 $ - $ 5.00 $ 204
77
3466Existing Stair to be Removed460%46SF $ 8.80 $ - $ 405.24 $ - $ 8.80 $ 405
78
3566Existing Porch to be Removed280%28SF $ 2.80 $ - $ 78.43 $ - $ 2.80 $ 78
79
3666Remove Countertop420%42SF $ 18.00 $ - $ 751.50 $ - $ 18.00 $ 752
80
3766Remove Flooring5440%544SF $ 2.00 $ - $ 1,087.68 $ - $ 2.00 $ 1,088
81
3866Remove Tile Flooring370%37SF $ 2.50 $ - $ 91.25 $ - $ 2.50 $ 91
82
3966Existing Framing To Be Removed5800%580SF $ 1.87 $ - $ 1,084.60 $ - $ 1.87 $ 1,085
83
4066Existing Electrical Fixture To Be Removed (580 SF)10%1LS $ 1,000.00 $ - $ 1,000.00 $ - $ 1,000.00 $ 1,000
84
85
2ND FLOOR
86
4166Remove Existing Single Door 70%7EA $ 100.00 $ - $ 700.00 $ - $ 100.00 $ 700
87
4266Remove Existing Window50%5EA $ 80.00 $ - $ 400.00 $ - $ 80.00 $ 400
88
4366Remove Plumbing Fixture30%3EA $ 120.00 $ - $ 360.00 $ - $ 120.00 $ 360
89
4466Existing Closet to be Removed250%25LF $ 18.00 $ - $ 445.50 $ - $ 18.00 $ 446
90
4566Interior Wall to be Removed9680%968SF $ 1.20 $ - $ 1,161.97 $ - $ 1.20 $ 1,162
91
4666Exterior Wall to be Removed9430%943SF $ 1.50 $ - $ 1,414.26 $ - $ 1.50 $ 1,414
92
4766Remove Flooring5390%539SF $ 2.00 $ - $ 1,078.84 $ - $ 2.00 $ 1,079
93
4866Remove Tile Flooring370%37SF $ 2.50 $ - $ 92.68 $ - $ 2.50 $ 93
94
4966Existing Electrical Fixture To Be Removed (576 SF)10%1LS $ 1,000.00 $ - $ 1,000.00 $ - $ 1,000.00 $ 1,000
95
96
ROOF
97
5066Existing Roof to be Removed7540%754SF $ 2.88 $ - $ 2,170.80 $ - $ 2.88 $ 2,171
98
99
SUB-TOTAL $ 23,805.41 $ - $ 23,805