Trams to Newhaven Timeline
2
DateActivityNotes
3
2017Updated outline business case approved by Council
4
Procurement process starts
5
2018Procurement of ISC and SPC contractors
6
Final Business Case preparation
7
Nov-18CCTT Formal meetings commence
8
19 Mar – 29 Apr2018First round of consultation
9
28-Aug-18Leith traders consulted on Support for Business package
10
1 Oct – 11 Nov 2018Second round of consultation – you said we didLink to summary report.
11
Mar-19Final Business Case approved by CouncilFurther information
12
Mar-19ISC and SPC contracts awardedFurther information
13
Mar-19Early Contractor Involvement Period begins
14
May-19Site investigation works begin along the routeFurther information
15
Nov-19First access letter issued to residents (Constitution Street)
16
Nov-19Meet the team event (Constitution Street)Further information
17
18-Nov-19Works begin on Constitution StreetFurther information
18
18-Nov-19Leith Walk enabling works startFurther information
19
27-Jan-20Meet the team event (Ocean Terminal)Further information
20
10-Feb-20First access letter issued (Newhaven - Melrose Drive)Further information
21
Feb-20Lothian Buses announce service diversions
22
21-Feb-20First access letter issued (Leith Walk) Further information
23
24-Mar-20COVID 19 - lockdown announced by Government
24
25-Mar-20COVID 19 - project shutdownFurther information
25
29-May-20Site preparation works for reopeningFurther information
26
12-Jun-20Project reopeningFurther information
27
15-Jul-20COVID 19 - pubs, restaurants and cafes open
28
14-Aug-20COVID 19 - hospitality venues to record contact details
29
22-Sep-20COVID 19 - new restrictions on hospitality venues introduced
30
7-Oct-20COVID 19 - Hospitality – 6am – 6pm for indoors pubs to close except takeaway
31
19-Oct-20Progress to date updateFurther information
32
6-Nov-20Updated Business Case (COVID 19)Further information
33
19-Nov-20First rail tracks installedFurther information
34
24-Nov-20COVID 19 - Limited relaxation of rules for Xmas announced
35
19-Dec-20COVID 19 - Tightening of restrictions announced for Xmas
36
26-Dec-20
COVID 19 - Scotland to level 4 - all hospitality and leisure venues close
37
5 Jan 2021Construction restartFurther information
38
28-Jan-21Stevedore Place landscaping design updateFurther information
39
28-Feb-21Changes to cycleway provision on Leith WalkFurther information
40
2-Apr-21COVID 19 - Stay at home restrictions lifted
41
6-Apr-21Start of FoTW tram stop constructionFurther information
42
26-Apr-21COVID 19 - Scotland to level 3 - hospitality reopens
43
14-May-21COVID 19 - Scotland to level 2
44
21-May-21Leith Walk cycleway updateFurther information
45
1-Jun-21Closure of Elm RowFurther information
46
10-Jun-21First drone footageFurther information
47
15-Jul-21Extension of site to Coatfield LaneFurther information
48
2-Aug-21Extension of site at FoTWFurther information
49
3-Aug-21Changes to traffic management on Leith WalkFurther information
50
18-Aug-21Opening of Halmyre Compound siteFurther information
51
22-Oct-21Changes to Leith Walk traffic managementFurther information
52
23-Nov-21Two year look backFurther information
53
26-Nov-21Notification of building fixings installationFurther information
54
8-Dec-21New drone footage showing progressFurther information
55
17-Dec-21First access letter issued (Queen Charlotte Street - Coatfield Lane)Further information
56
5-Jan-22Changes to Leith Walk traffic managementFurther information
57
5-Jan-22Site extension - Picardy Place to York PlaceFurther information
58
25-Jan-22Robert Burns Statute returnsFurther information
59
27-Jan-22Works starting - east side of Leith WalkFurther information
60
3-Feb-22Construction start at York PlaceFurther information
61
4-Feb-22Works to start on Melrose DriveFurther information
62
17-Feb-22Construction start - Rennie's Isle - Tower PlaceFurther information
63
18-Feb-22Reinstatement works at Elm Row to startFurther information
64
25-Mar-22Progress to date update, including programme updateFurther information
65
28-Mar-22York Place works completedFurther information
66
1-Apr-222-way traffic back on Lindsay RoadFurther information
67
26-May-22Traffic management changes - Picardy Place - Annandale StreetFurther information
68
1-Jun-22Traffic management changes - Pilrig Street - London RoadFurther information
69
13-Jun-22Traffic managent changes - Pilrig Street - Annandale StreetFurther information
70
20-Jun-22Updated drone footageFurther information
71
11-Jul-22Largest concrete pour to date - Rennie's IsleFurther information
72
13-Jul-22Pilrig Street - London Road reopens, including programme update Further information
73
17-Aug-22London Road clock returns to Elm RowFurther information
74
18-Aug-22
Changes to traffic management between Annandale Street and York Place
Further information
75
5-Sep-22Closure of Brunswick Street junctionFurther information
76
28-Sep-22Article on simulator for driver training including programme updateFurther information
77
18-Oct-22FoTW traffic management changesFurther information
78
19-Oct-22Annandale Street - Picardy Place traffic management changesFurther information
79
28-Oct-22Changes to Brunswick Road junctionFurther information
80
21-Nov-22London Road junction re-opens, banned left hand turn introducedFurther information
81
25-Nov-22FoTW - Manderston Street traffic management changesFurther information
82
29-Nov-22Overhead line out of hours workingFurther information
83
20-Dec-22Final tram track laidFurther information
84
21-Dec-22London Road left hand turn mitigation measuresFurther information
85
23-Dec-222022 update and progressFurther information
86
3-Feb-23Two way traffic to Leith Walk, programme update and electrificationFurther information
87
13-Mar-23Testing and commissioning starts on routeFurther information
88
13-Mar-23First trams on routeFurther information
89
17-Mar-23Leith Walk remedial worksFurther information
90