ABCDEFGHIJKLMNOPQRSTUVWXYZ
1
RESIDENTIAL CONSTRUCTION ESTIMATE
2
This estimate is based on the defined scope, assumptions, selections, and site conditions. Work outside the agreed scope requires a written change order.
3
4
Contractor DetailsHomeowner Details
5
Contractor NameHomeowner Name
6
AddressBilling Address
7
TelephoneProperty Address
8
EmailContact Name
9
Company Details
Contact Information
10
11
Estimate & Project Details
12
Estimate NumberEstimate DateValid Through
13
Estimate StatusProject NameProject Type
14
Project Reference
Estimated Start Date
Estimated Duration
15
Drawing / Specification References
16
Project Description
17
18
19
Occupied Property?
Permits Required?
Customer-Supplied Items?
20
21
Scope of Work
22
23
24
25
26
27
28
29
Customer-Facing Cost Summary
30
Project PhaseRoom / AreaWork DescriptionPrice TreatmentSupply ResponsibilityTaxAmountNotes
31
-
32
-
33
-
34
-
35
-
36
-
37
-
38
-
39
-
40
-
41
-
42
-
43
-
44
-
45
-
46
47
48
Pricing Summary
49
Direct Cost Subtotal-
50
Overhead-
51
Contingency-
52
Cost Before Profit-
53
Profit-
54
Base Project Price-
55
Allowance Total-
56
Additive Alternates-
57
Deductive Alternates-
58
Tax-
59
Final Estimated Price-
60
61
Project Area (m²)
Estimated Cost per m²
-Target Price-
62
63
Payment Schedule
64
MilestoneDescriptionPercentageAmountDue Event / DateStatus
65
Deposit-
66
Mobilisation-
67
Progress Payment 1
-
68
Progress Payment 2
-
69
Practical Completion
-
70
Final Payment-
71
72
73
Commercial Terms
74
Exclusions
75
76
77
Assumptions
78
79
80
81
Customer-Supplied Items
82
83
84
Work by Others
85
86
87
Change-Order Terms
88
89
90
Warranty / Workmanship Note
91
92
93
Customer Acceptance
94
Accepted BySignature
95
96
Date
Purchase Order / Reference
97
98
99
Internal Review
100
Reviewed By
Internal Approval
Review Date