4 | Data Center Assessment | |||||||
5 | ||||||||
6 | ||||||||
7 | ||||||||
8 | Pros | Cons/Risks | Comments | |||||
9 | Tax Revenue | Significant source of revenue | Financial concentration risk | What is your maximum tolerance for such a concentration? Would you invest idle funds at that same tolerance, or at the risk level of the technology industry? | ||||
10 | Reliance on single taxpayer | Who is your data center developer: a primary user like Microsoft, a data center operator like QTS, or a speculator who plans to flip the building after completion? | ||||||
11 | Reliance on single industry | The tech industry is very fast-paced and innovates relentlessly. If this one project is a large percentage of land and a large percentage of your tax revenue, you are tying the future of your town to that industry. | ||||||
12 | Potential valuation fluctuation | Valuation of hyperscale data centers is very new. AI bubble raises likelihood of valuation fluctuation. | ||||||
13 | Property tax abatement | Are you planning on property tax abatement? If your primary motivation for the project is tax revenue, why are you abating it? | ||||||
14 | ||||||||
15 | ||||||||
16 | ||||||||
17 | ||||||||
18 | Pros | Cons | Comments | |||||
19 | Construction Labor | Job sites likely will employ 1500 or more construction jobs for multiple years. | Much of the labor will be itinerant given the specialities needed. | Assessment of job growth data from TX - https://michaeljhicks.substack.com/p/data-centers-and-local-job-creation | ||||
20 | Construction workers will generate some indirect economic impact -- eating at restaurants, shopping at local stores | Puts upward pressure on rental prices unless there is a major metro area nearby to absorb the workers. | ||||||
21 | ||||||||
22 | ||||||||
23 | ||||||||
24 | ||||||||
25 | ||||||||
26 | Pros | Cons | Comments | |||||
27 | Long-Term Labor | Data center will employ staff once operational, some of which will be high-tech, good-paying jobs | Data center staffing levels are low, and very low per acre of land | Northern Virginia averages 18 employees per data center building | ||||
28 | Assessment of job growth data from TX - https://michaeljhicks.substack.com/p/data-centers-and-local-job-creation | |||||||
29 | ||||||||
30 | ||||||||
31 | ||||||||
32 | ||||||||
33 | Pros | Cons | Comments | |||||
34 | Economic Development | Extension of public utilities -- water, sewer, electricity -- can create opportunity for other businesses to relocate to the area with the data center | There is very little evidence that this happens. | Check maps of West Des Moines IA, Prineville OR, Umatilla OR for examples of the absence of geographically nearby development over a decade past data center construction. | ||||
35 | Permanent jobs multiplier effect | Multiplier effect only works at scale. Small numbers of new jobs can be easily absorbed by even small towns without indirect economic benefit. | ||||||