IDTypeDescriptionImpactOwnerStatusDue DateMitigation / Action
2
R-01RiskUX designs are behind schedule, which may delay Sprint 4 development.HighUX LeadOpen
8/15/2026
Prioritize critical screens first, add interim design reviews, adjust sprint scope if necessary.
3
R-02RiskClient stakeholders may request additional features after Sprint Planning.HighProduct OwnerMonitoringOngoingReinforce change control process and evaluate new requests against backlog priorities.
4
A-01AssumptionBusiness stakeholders will provide timely feedback within two business days.MediumClient SponsorValidOngoingConfirm review schedule during weekly status meetings.
5
A-02AssumptionExisting CRM APIs will support required customer account functionality.MediumTechnical Lead
Pending Validation
8/22/2026
Complete API validation during Sprint 1.
6
I-01IssueContent for five website pages has not been approved by Marketing.HighMarketing ManagerOpen
8/12/2026
Escalate during steering committee meeting and identify temporary placeholder content if needed.
7
I-02IssueQA identified defects affecting mobile navigation on iOS devices.MediumQA LeadIn Progress
8/18/2026
Prioritize defects for next sprint and validate fixes before UAT.
8
D-01
Dependency
Single Sign-On integration cannot begin until Identity Provider configuration is completed by Infrastructure team.
High
Infrastructure Manager
Waiting
8/20/2026
Track dependency during weekly cross-functional sync meetings.
9
D-02
Dependency
Production deployment depends on completion of security and accessibility reviews.MediumSecurity TeamPlanned
8/28/2026
Schedule reviews two weeks before deployment to avoid release delays.