1 | UTILIZATION OF THE 20% COMPONENT OF IRA FOR DEVELOPMENT PROJECTS (NATIONAL TAX ALLOTMENT) | ||||||||||||||||||||||||
2 | AS OF DECEMBER 31, 2022 | ||||||||||||||||||||||||
3 | 4th QUARTER - 2022 | ||||||||||||||||||||||||
4 | |||||||||||||||||||||||||
5 | Province, City or Municipality: CAINTA, RIZAL | ||||||||||||||||||||||||
6 | |||||||||||||||||||||||||
7 | Program or Project | Location | TOTAL | Date Started | Target Completion Date | Project Status | No. of Extensions, if any | Remarks | |||||||||||||||||
8 | % of Completion | Total Cost Incurred to Date | |||||||||||||||||||||||
9 | Social Development | ||||||||||||||||||||||||
10 | Maintenance and Other Operating Expenses | 91,240,138.75 | 84,315,633.49 | ||||||||||||||||||||||
11 | Welfare Goods Expenses | 10,074,242.00 | Jan '22 | Dec. '22 | 100% | 10,068,722.00 | Reprogrammed, SB1, SB3 | ||||||||||||||||||
12 | Drugs and Medicines Expenses | 8,072,896.75 | Jan '22 | Dec. '22 | 96% | 7,731,687.70 | |||||||||||||||||||
13 | Repair and Maintenance - | ||||||||||||||||||||||||
14 | Other Infrastructure Assets | 34,583,000.00 | Jan '22 | Dec. '22 | 100% | 34,476,233.52 | Reprogrammed, SB3 | ||||||||||||||||||
15 | Other Structures | 16,800,000.00 | Jan '22 | Dec. '22 | 75% | 12,600,527.05 | Reprogrammed, SB3 | ||||||||||||||||||
16 | Hospitals and Health Centers | 4,400,000.00 | Jan '22 | Dec. '22 | 92% | 4,062,991.52 | Reprogrammed, SB3 | ||||||||||||||||||
17 | Donations * | 13,000,000.00 | Jan '22 | Dec. '22 | 86% | 11,150,000.00 | Reprogrammed, SB3 | ||||||||||||||||||
18 | Taxes, Duties and Licenses *** | 2,000,000.00 | Dec '22 | Dec. '22 | 98% | 1,950,871.70 | SB7 | ||||||||||||||||||
19 | Other Maintenance and Operating Expenses | 2,310,000.00 | Jan '22 | Dec. '22 | 98% | 2,274,600.00 | Reprogrammed, SB1 | ||||||||||||||||||
20 | |||||||||||||||||||||||||
21 | Other Structures | 34,300,000.00 | 29,394,782.85 | ||||||||||||||||||||||
22 | Repair/Improvement of Barangay Hall at Brgy. San Isidro (Phase 2) | 3,465,000.00 | Jan '22 | Dec. '22 | 70% | 2,426,193.10 | 1st & Partial Payment with CAF | ||||||||||||||||||
23 | Construction of Niches, Cainta Public Cemetery, Brgy. San Juan | 5,000,000.00 | Jan '22 | Dec. '22 | 100% | 4,975,500.00 | |||||||||||||||||||
24 | Refurbishment of One Cainta College Outside Wall, Hunter's ROTC, Brgy. San Juan | 1,036,408.95 | Jan '22 | Dec. '22 | 99% | 1,023,710.62 | with Certificate of Availability of Funds (CAF) | ||||||||||||||||||
25 | Proposed Construction of Sports Track and Field Oval (Second Phase) at Montevista Subd, Brgy. Sto. Niño (Asphalt) | 5,595,373.24 | Jan '22 | Dec. '22 | 100% | 5,574,907.46 | with Certificate of Availability of Funds (CAF) | ||||||||||||||||||
26 | Proposed Construction of Sports Track and Field Oval (Final Phase) at Montevista Subd, Brgy. Sto. Niño (Rubber Track) | 12,969,700.00 | Jan '22 | Dec. '22 | 100% | 12,950,736.75 | with Certificate of Availability of Funds (CAF) | ||||||||||||||||||
27 | Improvement/Construction of Senior Citizens Hall at Municipal Compound, Brgy. Sto. Domingo | 1,433,517.81 | Jan '22 | Dec. '22 | 99% | 1,422,824.37 | |||||||||||||||||||
28 | Proposed Construction of Property Fence of Animal Shelter and Substance Abuse Treatment Facility | 4,800,000.00 | Aug '22 | Dec. '22 | 21% | 1,020,910.55 | SB5 | ||||||||||||||||||
29 | Economic Development | ||||||||||||||||||||||||
30 | Land | 23,650,000.00 | Jan '22 | Dec. '22 | 94% | 22,183,343.78 | |||||||||||||||||||
31 | |||||||||||||||||||||||||
32 | Road Networks | 14,002,861.25 | 13,957,656.58 | ||||||||||||||||||||||
33 | Asphalt Overlay Along Vista Road, Brgy. Sto. Niño | 1,893,863.83 | Jan 31 '22 | Dec. '22 | 99% | 1,883,494.39 | With (CAF) / Reprogrammed, SB1 | ||||||||||||||||||
34 | Asphalt Overlay Along Oriole St. (Greenland Gate), Falcon St., Seagull St., Brgy. San Juan | 5,243,908.57 | Jan 31 '22 | Dec. '22 | 100% | 5,227,719.12 | With (CAF) / Reprogrammed, SB1 | ||||||||||||||||||
35 | Asphalt Overlay St. (Amang Rodriguez to Sitio Victoria Bridge), Brgy. San Roque | 6,865,088.85 | Jan 31 '22 | Dec. '22 | 100% | 6,846,443.07 | With (CAF) / Reprogrammed, SB1 | ||||||||||||||||||
36 | |||||||||||||||||||||||||
37 | Construction and Heavy Equipment | 13,100,000.00 | May 30 '22 | Dec. '22 | 100% | 13,074,270.00 | SB3 / SB5 | ||||||||||||||||||
38 | |||||||||||||||||||||||||
39 | Other Machinery and Equipment | 5,990,000.00 | Jan '22 | Dec. '22 | 78% | 4,643,396.00 | SB3, SB4 & SB5 | ||||||||||||||||||
40 | |||||||||||||||||||||||||
41 | Flood Control Systems | 1,217,000.00 | Oct '22 | Dec. '22 | 100% | 1,198,467.80 | SB6 | ||||||||||||||||||
42 | Riprap, along Sunset Drive, Brookside Hills Subd., Brgay. San Isidro, Cainta, Rizal | 1,217,000.00 | 98% | 1,198,467.80 | |||||||||||||||||||||
43 | |||||||||||||||||||||||||
44 | Environmental Management | ||||||||||||||||||||||||
45 | |||||||||||||||||||||||||
46 | Parks, Plazas and Monuments | 20,000,000.00 | Jan '22 | Dec. '22 | 100% | 19,999,352.86 | |||||||||||||||||||
47 | |||||||||||||||||||||||||
48 | TOTAL | 203,500,000.00 | - | - | 188,766,903.36 | ||||||||||||||||||||
49 | |||||||||||||||||||||||||
50 | We hereby certify that we have reviewed the contents and hereby attest to the veracity and correctness of tha data or information contained in this document. | ||||||||||||||||||||||||
51 | |||||||||||||||||||||||||
52 | |||||||||||||||||||||||||
53 | |||||||||||||||||||||||||
54 | MAY ANGELIQUE I. TALAGA | Atty. MARIA ELENITA D. NIETO | |||||||||||||||||||||||
55 | Municipal Budget Officer | Mayor | |||||||||||||||||||||||
56 | |||||||||||||||||||||||||
57 | #REF! | ||||||||||||||||||||||||
58 | |||||||||||||||||||||||||
59 | |||||||||||||||||||||||||
60 | |||||||||||||||||||||||||
61 | |||||||||||||||||||||||||
62 | |||||||||||||||||||||||||
63 | |||||||||||||||||||||||||
64 | |||||||||||||||||||||||||
65 | |||||||||||||||||||||||||
66 | |||||||||||||||||||||||||
67 | |||||||||||||||||||||||||
68 | |||||||||||||||||||||||||
69 | |||||||||||||||||||||||||
70 | |||||||||||||||||||||||||
71 | |||||||||||||||||||||||||
72 | |||||||||||||||||||||||||
73 | |||||||||||||||||||||||||
74 | |||||||||||||||||||||||||
75 | |||||||||||||||||||||||||
76 | |||||||||||||||||||||||||
77 | |||||||||||||||||||||||||
78 | |||||||||||||||||||||||||
79 | |||||||||||||||||||||||||
80 | |||||||||||||||||||||||||
81 | |||||||||||||||||||||||||
82 | |||||||||||||||||||||||||
83 | |||||||||||||||||||||||||
84 | |||||||||||||||||||||||||
85 | |||||||||||||||||||||||||
86 | |||||||||||||||||||||||||
87 | |||||||||||||||||||||||||
88 | |||||||||||||||||||||||||
89 | |||||||||||||||||||||||||
90 | |||||||||||||||||||||||||
91 | |||||||||||||||||||||||||
92 | |||||||||||||||||||||||||
93 | |||||||||||||||||||||||||
94 | |||||||||||||||||||||||||
95 | |||||||||||||||||||||||||
96 | |||||||||||||||||||||||||
97 | |||||||||||||||||||||||||
98 | |||||||||||||||||||||||||
99 | |||||||||||||||||||||||||
100 | |||||||||||||||||||||||||