ABCEGJLMNOPQRSTUVW
1
2110 Yewpon Court
2
Addition
3
Prepared For: Kim Triff
4
Prepared By: Apex Genesis, LLC
5
TradeBase1GSF. W/Pk.% of line itemNotes
6
BudgetPer Unit5,062
7
Appliances ALLOWANCE$0.00$0.00$0.750%Installation by supplier
8
Architectural Metals ALLOWANCE$0.00$0.00$0.600%NIC
9
Cabinets ALLOWANCE$13,515.54$13,515.54$2.67100%Allowance for kitchen, bath and common area cabinets
10
Cabinets - Islands ALLOWANCE$0.00$0.00$2.670%Allowance for kitchen island tables
11
Carpentry - Balcony Install/Window Install$0.00$0.00$1.500%Allowance for alum. pref. balcony and window install
12
Carpentry - Framing and Rough$72,892.80$72,892.80$16.0090%Carpentry framing misc. materials and rough labor, sheathing, cornice, decking, and install windows and exterior doors
13
Carpentry - Eisen/Wood Panels System$0.00$0.00$10.110%Eisen steel framing system and wood panel wall system
14
Carpentry - Interior Trim/Finish Carpentry$5,675.54$5,675.54$3.1136%Carpentry labor for interior trim, doors and common areas
15
Carpet & Hardwood$13,691.00$13,691.00$4.1066%Carpet and vinyl flooring throughout units, tile and cc in common
16
Closet Shelving ALLOWANCE$1,214.88$1,214.88$0.24100%Allowance for wire shelving throughout
17
Concrete - Foundation$25,816.20$25,816.20$15.0034%Spread footings and slab foundation under parking assembly
18
Concrete - Topping$7,593.00$7,593.00$5.0030%Concrete finishes( poly, epoxy, etc)
19
Concrete Fire Walls (aerated) $0.00$0.00$0.910%NIC
20
Countertops ALLOWANCE$3,290.30$3,290.30$0.65100%Allowance for kitchen, bath and common area tops
21
Courtyard Amenities ALLOWANCE$0.00$0.00$0.460%Allowance for courtyard amenities and structures
22
Demolition$5,540.00$5,540.00$1.09100%Demo the exterior and the driveway.
23
Div. 10 - Lockers/Bike Racks/Signage$0.00$0.00$0.230%Allowance for division 10 items
24
Div. 10 - Mailboxes ALLOWANCE$0.00$0.00$0.150%Allowance for division 10 items
25
Div. 10 Toilet Accessories/Partitions$1,214.88$1,214.88$0.24100%Allowance for partitions and bath accessories
26
Drywall$14,583.12$14,583.12$2.9797%Drywall and taping throughout
27
Electric - Fire Emergency System$0.00$0.00$1.040%Radio fire emergency system allowance
28
Electric, Fire Alarm, Fixtures and LV$30,878.20$30,878.20$6.10100%Electric service, rough, trim, fixtures, LV, fire alarm , etc.
29
Elevators$0.00$0.00$8.300%Four elevators and associated equipment
30
Excavation$0.00$0.00$2.740%Excavation for foundation, garage and site structures
31
FF & E$16,704.60$16,704.60$3.30100%Plumbing and Electrical Finishes
32
Fiber Cement Siding$0.00$0.00$6.020%Fiber cement siding and trim on majority of exterior surfaces
33
Final Cleaning$1,265.50$1,265.50$0.25100%Final cleaning of units and common areas before turnover
34
Fire Caulking/Caulking/Coring/Joint Sealants$0.00$0.00$0.380%Fire caulking, coring, joint sealants, etc.
35
Fire Extinguishers$0.00$0.00$0.120%Fire Extinguishers throughout
36
Fire Protection$0.00$0.00$5.010%Wet and dry fire protection system throughout
37
Fireplaces$0.00$0.00$0.160%Common area fireplaces for amenity spaces
38
Fireproofing$0.00$0.00$0.270%Fireprrofing beams at amenity spaces
39
General Requirements$7,593.00$7,593.00$1.50100%General requirements during construction plus Permits
40
HVAC & Piping$15,186.00$15,186.00$3.00100%PTAC System in units in the units, mixed in common
41
Insulation$13,161.20$13,161.20$2.60100%Insulation and fireproofing throughout
42
Interior Amenity Finishes ALLOWANCE$0.00$0.00$0.820%Allowance for interior amenity finishes for amenity spaces
43
Masonry and exterior$54,669.60$54,669.6010.8100%Brick and siding allowance
44
exterior Finishes$1,771.70$1,771.700.35100%gutters, etc
45
Millwork and Doors$5,568.20$5,568.20$1.10100%Millwork, doors, hardware, etc. units and common areas
46
Mirrors & Shower Doors$1,518.60$1,518.60$0.30100%Allowance for mirrors and shower doors
47
Monument Signage ALLOWANCE$0.00$0.00$0.380%Allowance for entry monumentation
48
Overhead Doors$3,796.50$3,796.50$0.75100%Commercial overhead doors and openers
49
Painting/Wall Coverings$14,011.33$14,011.33$5.7544%Painting and wall covers for units and common areas
50
Plumbing & Fixtures$20,248.00$20,248.00$4.00100%Estimate for plumbing and fixtures throughout
51
Roof deck Paver and Amenity ALLOWANCE$0.00$0.00$0.440%Allowance for roof deck amenities
52
Roofing & Sheet Metal$14,047.05$14,047.05$7.5037%Building and garage roofing and flashing
53
Site - Survey, Layout$0.00$0.00$7.450%Site layout and construction staking
54
Structural - Balconies/Railings$0.00$0.00$2.320%Prefinished aluminum balconies and railings
55
Structural Steel & Misc. Metals$0.00$0.00$2.570%Estimate for structural steel and connections
56
Tile$3,543.40$3,543.40$7.0010%Tile in baths and common
57
Trash Chutes$0.00$0.00$0.200%Trash chutes per plan
58
Window Treatments ALLOWANCE$0.00$0.00$0.000%NIC
59
Windows$12,655.00$12,655.00$2.50100%White vinyl windows and patio doors
60
Windows - Storefront/Curtain Wall$0.00$0.00$1.970%Estimate for storefront glass and frames
61
Winter Conditions ALLOWANCE$0.00$0.00$0.000%Allowance for winter conditions
62
Subtotal - Hard Costs$381,645.13$381,645.13$75.3941.55%Subtotal - Hard Costs
63
Sitework
64
Paving$0.00$0.00$5.000.00%Repairs of existing street paving and structures
65
Concrete Flatwork, Curb Sidewalks$3,644.64$3,644.64$9.008.00%New city walk, drives, curb and approaches
66
Landscaping ALLOWANCE$2,531.00$2,531.00$0.50100.00%Allowance for landscaping
67
Landscaping - Irrigation ALLOWANCE$0.00$0.00$3.000.00%Allowance for site landscape irrigation
68
Site Utilities - Sewer and Water$0.00$0.00$5.000.00%Estimate for detention, sewer and water mains
69
TDOT Intersection Work ALLOWANCE$0.00$0.00$5.000.00%TDOT Intersection work
70
Fencing$0.00$0.00$5.000.00%Allowance for site fencing and gates around perimeter of site
71
Earthwork & Site Preparation$0.00$0.00$5.000.00%Site prep and associated earthwork
72
Aquatics - Pool/Site Lighting$0.00$0.00$5.000.00%Allowance for pool construction and site lighting splash pad
73
Subtotal - Sitework$6,175.64$6,175.64$1.2212.00%Subtotal - Sitework
74
75
Precast Concrete Deck/Podium$0.00$0.00$0.000.00%Estimate for precast parking garage
76
77
78
Construction Subtotal$387,820.77$387,820.77$76.6126.77%Construction Subtotal
79
80
Contingency 10%$38,782.08$38,782.08$7.66Construction contingency
81
Insurance0.00%$0.00$0.00$0.00General liability and workman's comp insurance (for GC)
82
General Conditions10.00%$38,782.08$38,782.08$7.66General conditions for duration of construction
83
General Contracting Fee10.00%$38,782.08$38,782.08$7.66General Contracting Fees
84
Total Hard Costs$504,167.00$504,167.00$99.60Total Hard Costs
85
86
Design-Build Cost Subtotal
$465,384.92
w/o contigency
87
Design-Build Cost $504,167.00
w/ contingency
88
89
90
91
Per buildable sqft: 91.93696605
92
Per Liveable205.7404607
93
94
95
96
97
98
99
100