Commissioning plan 2017 shift by shift
2
3
DateDayShiftStatusTimeActivity
4
01/05/2017
5
1M4Injection, first turn B1&B2, step around, screensOP
6
1M2RF capture B1&B2 - closed orbitOP/RF
7
1A4BI works: BPM phasing, BCT checks, multi-turn & AC dipoleOP/BI
8
1N6Pre-cycle to 6.5TeV, then Q, Q' at injection and feedbacks. OP
9
02/05/2017
10
2M4Coarse collimator set-up and loss map in preparation for rampABP/COLL/RF
11
2M4Ramp and squeezeOP
12
2A4New coupling tool testOP/ABP/OMC/RF
13
2A6Optics measurements at 450GeV.ABP/OMC
14
2N2First ULO checks (~2h)OP/ABP/COLL
15
2N4Ramp 2 for Q' measurements, decay measurements.OP
16
03/05/2017
17
3M4Ramp optics and Q' verificationOP
18
3M4New coupling tool testOP/ABP/OMC/RF
19
3A12Squeeze to 0.4 m and optics measurementsOP/ABP/OMC
20
3N4OP cycle tests: Q, Q' during ramp, squeeze smoothingOP
21
04/05/2017
22
4M4BLM: Transmission time, MPS functionality @ 450 GeVBI
23
4M4DOROS BPM collimators commissioning @450 GeVABP/COLL
24
4A12Ballistic/alignment opticsOP/ABP/OMC
25
4N4Squeeze to 0.4 m smoothing and C correctionOP
26
05/05/2017
27
5M4Splashes for ATLAS & CMSOP
28
5M4Setup of nominal bunch intensity - RFRF
29
5A8Setup of nominal bunch intensity - ADT & BIRF/BI
30
5N8Kmodulation measurements of BM offsetsOP
31
06/05/2017
32
6M12Optics correction at 6.5 TeV (FT+squeeze)ABP/OMC
33
6A4Variable AGK commissioningOP/ABT
34
6N8Kmodulation measurements of BM offsetsOP
35
07/05/2017
36
11M8RF cavity phasingRF
37
11A8ADT setupRF
38
11N8Probe to end of squeeze with bumpsOP
39
08/05/2017
40
7M8Optics correction at 6.5 TeV (FT+squeeze)OP/ABP/OMC
41
7A8Non-linear optics correctionsOP/ABP/OMC
42
7N8Squeeze cleanup after optics correctionOP
43
09/05/2017
44
8M4Reference orbit with nominal bunchOP
45
8M4Ramp with flat machine, squeeze check (coupling)OP
46
8M2Spectrometer experimental magnets ONOP
47
8A2Bumps on a injectionOP
48
8A4Ramp with bumps onOP
49
8N8Non-linear optics correctionsOP/ABP/OMC
50
10/05/2017
51
9M8Global aperture 450 GeVABP/COLL
52
9A8Collimation setup at injectionABP/COLL
53
9N4Injection and dump protection setupABT
54
9N4OP
55
11/05/2017
56
10M8Global aperture 450 GeVABP/COLL
57
10A4Collimator BPM checksABP/COLL
58
10A8Injection and dump protection setupABT
59
10N4OP
60
12/05/2017
61
11M8Probe to end of squeeze with bumpsOP
62
11A8Variable AGK commissioningOP/ABT
63
11N8
64
13/05/2017
65
12M8Injection and dump protection setupOP/ABP/COLL
66
12A8ADT setupRF/BI
67
12N8Ramp with tight collimation, optics checks
OP/ABP/COLL/OMC
68
14/05/2017
69
13M8Nominal on FT, first attemptOP
70
13A8Injection and dump protection setupABT
71
13N8Optics measurement in IR4 for BSRT (kmod inj, ft, collisions)ABP/OMC/BI/OP
72
15/05/2017
73
14M8Nominal on FT, collimator alignment FTOP/ABP/COLL
74
14A8Checks at injection (LBDS)ABT
75
14N8BBLR wire at injectionABP
76
16/05/2017
77
15M8Pilot squeeze, to collisionsOP
78
15A8Nominal bunch collisionsOP
79
15N8De-squeeze test with pilotsOP
80
17/05/2017
81
16M4Iteration on squeeze and collisions (pilot)OP
82
16M4Iteration on squeeze and collisions (nominal)OP
83
16A8BSRT calibrationOP/BI
84
16N8OP
85
18/05/2017
86
16M12TCTP alignment and aperture 40cm (2 nominals to be blown out)ABP/COLL
87
17A8TCDI setupABT
88
17N4
89
19/05/2017
90
18M8MP tests in preparation for trains (Interlocked BPMs, ...)OP
91
18A8LBDS synchronization and AGK window adjustmentABT
92
18N8Loss maps at injectionOP
93
20/05/2017
94
19M8Loss maps at injection & FTOP
95
19A8LBDS synchronization and AGK window adjustmentABT
96
19N8Quiet beamsOP
97
21/05/2017
98
20M8Desqueeze optics checkOP/ABP/OMC
99
20A8Cross-calibration BWS and BSRTOP/BI
100
20N8Loss maps + Async beam dump @ FTOP
Loading...
 
 
 
2017 SHIFT-by-SHIFT - plan
2017 SHIFT-by-SHIFT - realized
Parameters 2017
2017 Commissioning action