Highway Construction - Daily Progress Report
2
3
By: Parag Pal
4
1. General Information
5
Project Name:NH-44 Upgrade (KM 150 to KM 180)Report Date:2025-07-17
6
Report No:DPR-2024-125Weather:Sunny, Max Temp: 38°C
7
8
2. Work Progress Summary
9
ActivityLocation (Chainage)UnitPlanned TodayAchieved TodayCumulative Achieved
10
Earthwork (Excavation)155+200 to 155+5001,5001,65045,000
11
Granular Sub-Base (GSB)
152+000 to 152+400
1,2001,20032,000
12
Wet Mix Macadam (WMM)151+500 to 151+80080075025,000
13
Asphalt Concrete (BC)150+000 to 150+300Ton4004108,500
14
Culvert Construction (Box)153+750Nos115
15
Road Markings150+000 to 151+000m1,0001,0001,000
16
17
3. Resource Summary
18
Manpower CategoryPlannedActualMachinery/EquipmentPlanned (Hrs)Actual (Hrs)
19
Project Manager11Excavator1618
20
Site Engineer33Dump Truck6065
21
Supervisor54Grader88
22
Surveyor22Roller1616
23
Skilled Labor4038Asphalt Paver87
24
Unskilled Labor8085Water Tanker88
25
26
4. Material Consumption
27
MaterialUnitOpening BalanceReceived TodayConsumed TodayClosing Balance
28
Aggregate (20mm)5,000.001,500.001,100.005,400.00
29
Aggregate (10mm)3,500.001,000.00800.003,700.00
30
Bitumen VG-30Ton800.00200.00150.00850.00
31
CementBags1,200.000.0050.001,150.00
32
Steel ReinforcementTon250.0020.0015.00255.00
33
34
5. Notes, Issues & Delays
35
1. Minor delay in WMM laying due to a temporary breakdown of one roller.
2. All safety protocols were followed. No incidents reported.
3. Extra dump trucks were deployed to accelerate earthwork.
36
37
38
39
40
41
42
43
Contractor RepresentativePlanning Engineer
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
80
81
82
83
84
85
86
87
88
89
90
91
92
93
94
95
96
97
98
99
100