ABCDEFGHIJKLMNOPQRSTUVWXYZ
1
`DayDateWeekly PlanDaily StuffPeople IMPACTsWISHLIST
2
Saturday1 JanuaryVerenaFew days of electron beam in January/February
3
Sunday2 JanuaryAWAKE1 week of WDL installation in January/February/March
4
1Monday3 JanuaryAccess
5
Tuesday4 January
6
Wednesday5 JanuaryCERN OPEN. Optical fiber installation this week (Ben Slater)Eloïse away
185303 (fiber, 3 days)
7
Thursday6 JanuaryEloïse away
8
Friday7 JanuaryCentral timing interventionnEloïse away
9
Saturday8 January
10
Sunday9 January
11
2Monday10 JanuaryAccess. Recover from shutdown
Maintenance access system (access is possible). Finish optical fibers.
182933 ( 3 days, access)
12
Tuesday11 JanuaryPossible RF access this week
13
Wednesday12 JanuaryInstall PC for CV in next few days (187011)
14
Thursday13 JanuaryElevator Maintenance 10-12. Vacuum intervention
186278 (lift, 10 to 12)
15
Friday14 JanuaryVacuum intervention
16
Saturday15 January
17
Sunday16 January
187387 (WDL, 1 week)
18
3Monday17 JanuaryWDL187398 (1h)
19
Tuesday18 JanuaryScafolding assembly (1h)
20
Wednesday19 January
21
Thursday20 JanuaryLaser restart (Edu, Miguel)
22
Friday21 January
23
Saturday22 January
24
Sunday23 January
25
4Monday24 JanuaryAccess
No access in the morning (8h to 13h). Scafolding disassembly at 14h
26
Tuesday25 January
9.30am Electron Gun crane inspection. Visit to TE80, TZ80, etc.
Eugenio BTV
187853 (visit, 2h)
27
Wednesday26 JanuaryRP access pm. Test alarms TT40 6 to 8 am
188013 (RP) + 187996 (TT40)
28
Thursday27 January
No access (https://indico.cern.ch/event/1085949/). TAG41 patrol 9am
29
Friday28 JanuaryAccess system test. No access
30
Saturday29 January
31
Sunday30 January
32
5Monday31 JanuaryPatrol. Restart Electrons.Access System should be fully functional and TAG42 will stay closed
Fiber installation TSG4
Eloïse away188177 (IT)
33
Tuesday1 FebruaryMagnet modification probably postponed (Philip Schwarz). Electron Gun crane AM
183514 (magnets, 4 days in next 10)
34
Wednesday2 FebruaryMaintenance PR-782 in TCC4. Quick access to Laser Room 9am (188455, Eugenio will meet Ben Slater))
Tube relocation TSG41 at 9h30
187919 (3h)
35
Thursday3 February
36
Friday4 February
Patrol of SPS. Possible access to TAG42. Electron Gun crane 2pm. CNGS visit PM (188679)
37
Saturday5 February
38
Sunday6 February
39
6Monday7 FebruaryElectrons and LaserMaintenance lift 15h to 17hEloïse RPE
187242 (magnet support, 07/02 to 28/03)
they will call if passage through TI8 needed
40
Tuesday8 FebruaryEPC power supply troubleshooting (PM)Eloïse RPE
41
Wednesday9 FebruaryVacuum access to TSG4 (AM, 188968)
42
Thursday10 February
43
Friday11 February
44
Saturday12 February
45
Sunday13 February
46
7Monday14 February
Gio away this week
47
Tuesday15 FebruaryUPS maintenanceEloïse RPE
48
Wednesday16 February
49
Thursday17 February
50
Friday18 FebruaryRF access+visit (morning)
51
Saturday19 February
52
Sunday20 February
53
8Monday21 FebruaryEloïse RPE
54
Tuesday22 February
55
Wednesday23 February
56
Thursday24 FebruaryJan/Sam/Eugenio IS1/IS2 cameras
57
Friday25 FebruaryVisit TSG4
58
Saturday26 February
59
Sunday27 February
60
9Monday28 February
61
Tuesday1 MarchAmplitude visit to fix Laser. Remote PXI reset ( 189963)Eloïse RPE
62
Wednesday2 March
DSO tests of TAG42 (Ridewood email). Maybe electron beam ML
63
Thursday3 March
64
Friday4 March4.30pm: magnets stop (P. Schwartz)
65
Saturday5 March
66
Sunday6 March
67
10Monday7 MarchMaybe BI vacuum interventionEloïse RPE
68
Tuesday8 MarchDismantling striplines (1 or 2 days)Eloïse RPE
69
Wednesday9 March
70
Thursday10 March
71
Friday11 MarchEloïse away
72
Saturday12 March
73
Sunday13 March
74
11Monday14 MarchBI vacuum intervention. New cathode installation.
This week: puisard access (2 days, 189572). Cathode Exchang
Shielding TSG45, 1 week
Eloïse away
190398 (shielding, 1 week)
75
Tuesday15 MarchThis week: BCT cabling (3 days, 189571)
76
Wednesday16 MarchThis week: potential CTU upgrade (Barrientos email)
77
Thursday17 March
78
Friday18 MarchVisit AWAKE 3.30pm
79
Saturday19 March
80
Sunday20 March
81
12Monday21 MarchElectron/Laser commissioning
5pm magnet tests in TCC4. Cathode QE. Possible magnet tests (close TAG41) 2 half-days this week (Gilles email)
Eloïse RPE
82
Tuesday22 MarchEloïse RPE
83
Wednesday23 MarchTAG41 closed PM for magnet tests.
84
Thursday24 MarchEloïse away
85
Friday25 March
DSO tests TAG41 ~25 March in conjunction with LHC DSO tests (Ridewood email)
86
Saturday26 March
87
Sunday27 March
88
13Monday28 MarchElectron/Laser commissioningPM: UV damage checks.Eloïse RPE
89
Tuesday29 March
90
Wednesday30 MarchFabian visits at 9am and 4pm. Eloise cleaning visit 9am.
91
Thursday31 MarchPROTONS
92
Friday1 April
93
Saturday2 April
94
Sunday3 April
95
14Monday4 AprilElectron/Laser commissioninglaser
96
Tuesday5 Aprillaser
97
Wednesday6 Aprilelectrons
98
Thursday7 Aprillaser
99
Friday8 AprilEloïse away
100
Saturday9 April