WBS supplementary notes
 Share
The version of the browser you are using is no longer supported. Please upgrade to a supported browser.Dismiss

 
View only
 
 
Still loading...
ABCDEFGHIJKLMNOPQRST
1
ReferenceTitleDescriptionResourceScheduled Delivery Date
2
1Build a houseContainern/aTBC
3
1.1Lay foundationContainern/aTBC
4
1.1.1.Dig TrenchA trench will need to be dug circa 1.2m deep and 0.5m wide which will subsequently be filled with cement to form a foundation for the block work which will form the fabric of the buildingThis will be done by in-house resources pulled from the general resourcing poolTBC
5
1.1.2Pour cementWhen the trench has been finished, cement will be poured into the trench. The cement will take 3 days to set +/- 1 day depending on the weather.A supplier will be contracted to undertake this activityTBC
6
1.1.3Building control approvalWhen the cement has set, insapectors in the employ of the local council will attend site to verify that the foundation have been correctly instated. This approval must precede further building work.This is at the discretion of the local councilTBC
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
80
81
82
83
84
85
86
87
88
89
90
91
92
93
94
95
96
97
98
99
100
Loading...
 
 
 
Sheet1