| A | B | C | D | E | F | G | I | J | K | L | M | N | O | P | Q | R | S | T | U | V | W | X | Y | Z | AA | AB | AC | AD | AE | AF | AG | AH | AI | AJ | AK | AL | AM | AN | AO | AP | AQ | AR | AS | AT | AU | AV | AW | AX | AY | AZ | BA | BB | BC | BD | BE | BF | BG | BH | BI | BJ | BK | BL | BM | BN | BO | BP | BQ | BR | BS | |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1 | Create a Project Schedule in this worksheet. Enter title of this project in cell B1. Information about how to use this worksheet, including instructions for screen readers and the author of this workbook is in the About worksheet. Continue navigating down column A to hear further instructions. | INTERIOR FITOUT PROJECT @ LOCATION | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
2 | PROJECT SCHEDULE | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
3 | Project Start: | Mon, 12/5/2022 | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
4 | The Display Week in cell E4 represents the starting week to display in the project schedule in cell I4. The project start date is considered Week 1. To change the display week, simply enter a new week number in cell E4. The starting date for each week, starting with the display week from cell E4, starts in cell I4 and is auto calculated. There are 8 weeks represented in this view from cell I4 through cell BF4. You should not modify these cells. Display Week: label is in cell C4. | Display Week: | 1 | Dec 5, 2022 | Dec 12, 2022 | Dec 19, 2022 | Dec 26, 2022 | Jan 2, 2023 | Jan 9, 2023 | Jan 16, 2023 | Jan 23, 2023 | Jan 30, 2023 | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
5 | Cells I5 through BL5 contain the day number for the week represented in the cell block above each date cell and are auto calculated. You should not modify these cells. Today's date is outlined in Red (hex #AD3815) from today's date in row 5 through the entire date column to the end of the project schedule. | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 23 | 24 | 25 | 26 | 27 | 28 | 29 | 30 | 31 | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 23 | 24 | 25 | 26 | 27 | 28 | 29 | 30 | 31 | 1 | 2 | 3 | 4 | 5 | ||||||
6 | This row contains headers for the project schedule that follows below them. Navigate from B6 through BL 6 to hear the content. The first letter of each day of the week for the date above that heading, starts in cell I6 and continues through cell BL6. All project timeline charting is auto generated based on the start and end dates entered, using conditional formats. Do not modify content in cells within columns after column I starting with cell I7. | ACTIVITY NAME | DURATION | PROGRESS | START | END | M | T | W | T | F | S | S | M | T | W | T | F | S | S | M | T | W | T | F | S | S | M | T | W | T | F | S | S | M | T | W | T | F | S | S | M | T | W | T | F | S | S | M | T | W | T | F | S | S | M | T | W | T | F | S | S | M | T | W | T | F | S | S | |
9 | Civil & Interior | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10 | Cell B9 contains the sample task "Task 1." Enter a new task name in cell B9. Enter a person to assign the task to in cell C9. Enter progress of the task in cell D9. A progress bar appears in the cell and is shaded according to the number in the cell. For example, 50 percent progress would shade half of the cell. Enter task start date in cell E9. Enter task end date in cell F9. A status bar shaded for the dates entered appears in blocks starting from cell I9 through BL9. | Issuance of LOI/PO | 1 | 0% | 5-Dec | 5-Dec-22 | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
11 | Rows 10 through 13 repeat the pattern from row 9. Repeat the instructions from cell A9 for all task rows in this worksheet. Overwrite any sample data. A sample of another phase starts in cell A14. Continue entering tasks in cells A10 through A13 or go to cell A14 to learn more. | Team Mobilization | 4 | 0% | 6-Dec-22 | 9-Dec-22 | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
12 | Issuance of GFC drawing details | 1 | 0% | 5-Dec-22 | 5-Dec-22 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
13 | Issuance of Partition Marking layout | 1 | 0% | 6-Dec-22 | 6-Dec-22 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
14 | Issuance of Finishes Schedule | 1 | 0% | 7-Dec-22 | 7-Dec-22 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
15 | Issuance of workstation marking layout | 1 | 0% | 7-Dec-22 | 7-Dec-22 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
16 | Approval of workstation marking | 1 | 0% | 8-Dec-22 | 8-Dec-22 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
17 | Approval of partition marking | 1 | 0% | 9-Dec-22 | 9-Dec-22 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
18 | Temporary power and water arrangements | 2 | 0% | 7-Dec-22 | 9-Dec-22 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
19 | Temporary light arrangements | 2 | 0% | 8-Dec-22 | 9-Dec-22 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
20 | Prominent display of HSE posters and establishment of safety infrastructure at site | 1 | 0% | 10-Dec-22 | 10-Dec-22 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
21 | Preparation of all packages MEP drawings | 3 | 0% | 6-Dec-22 | 9-Dec-22 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
22 | Submission and approval of MEP drawings | 1 | 0% | 9-Dec-22 | 10-Dec-22 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
23 | Submission of interior finishes samples and approval | 2 | 0% | 8-Dec-22 | 10-Dec-22 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
24 | Submission and Approval of MEP samples/TDS for all works | 3 | 0% | 10-Dec-22 | 13-Dec-22 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
25 | POP punning/Surface preparation works complete in open office | 5 | 0% | 10-Dec-22 | 15-Dec-22 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
26 | Supply and installation of tiles | 18 | 0% | 10-Dec-22 | 28-Dec-22 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
27 | Partition frameworks complete | 3 | 0% | 10-Dec-22 | 13-Dec-22 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
28 | Single side single skin boarding works complete for MEP clearance | 2 | 0% | 13-Dec-22 | 15-Dec-22 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
29 | Column cladding/Long wall panelling framework complete | 7 | 0% | 10-Dec-22 | 17-Dec-22 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
30 | MEP clearances for partition board closing | 4 | 0% | 17-Dec-22 | 21-Dec-22 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
31 | Acoustic fill and double skin second side board closing | 5 | 0% | 21-Dec-22 | 27-Dec-22 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
32 | All columns/wall Panelling works closing complete | 10 | 0% | 17-Dec-22 | 27-Dec-22 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
33 | Completion of PHE services | 13 | 0% | 13-Dec-22 | 26-Dec-22 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
34 | All partitions gypsum surface preparation with 2 coats primer and 2 coats putty | 8 | 0% | 27-Dec-22 | 4-Jan-23 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
35 | All type ceiling framework and boarding complete with finishing - MEP coordiantion | 5 | 0% | 4-Jan-23 | 9-Jan-23 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
36 | Reception table/Board room/Table and site made joinery carcass complete | 15 | 0% | 10-Dec-22 | 25-Dec-22 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
37 | Reception table/Board Room/Tables finishing works complete | 10 | 0% | 26-Dec-22 | 5-Jan-23 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
38 | Factory made items delivery at site | 12 | 0% | 2-Jan-22 | 14-Jan-22 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
39 | Lacquered glasses and acoustic boards,wall paper, sanitary fittings supply | 18 | 0% | 13-Dec-22 | 31-Dec-22 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
40 | All partitions second coat paint complete | 3 | 0% | 10-Jan-23 | 13-Jan-23 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
41 | Installation of all grid ceiling tiles with final alignment | 2 | 0% | 12-Jan-23 | 14-Jan-23 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
42 | Supply of carpet material | 45 | 0% | 7-Dec-22 | 21-Jan-23 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
43 | Completion of carpet installation | 2 | 0% | 22-Jan-23 | 24-Jan-23 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
44 | Supply of workstation and tables | 45 | 0% | 7-Dec-22 | 21-Jan-23 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
45 | Completion of workstation installation | 4 | 0% | 22-Jan-23 | 27-Jan-23 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
46 | Transition Profile installations | 2 | 0% | 24-Jan-23 | 27-Jan-23 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
47 | Loose Furniture | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
48 | Submission and approval of samples/Finishes | 2 | 0% | 7-Dec-22 | 9-Dec-22 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
49 | Supply of loose furniture material | 35 | 0% | 10-Dec-22 | 14-Jan-23 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
50 | Transporting and shifting | 3 | 0% | 14-Jan-23 | 17-Jan-23 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
51 | Installation and handover | 1 | 0% | 18-Jan-23 | 18-Jan-23 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
52 | Electrical | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
53 | Completion of raceway marking, cutting | 4 | 0% | 10-Dec-22 | 14-Dec-22 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
54 | Raceway, junction box supply & installation | 8 | 0% | 12-Dec-22 | 20-Dec-22 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
55 | Supply of conduit, cable tray, wires, DBs | 12 | 0% | 10-Dec-22 | 22-Dec-22 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
56 | Completion of conduit and cable tray | 4 | 0% | 23-Dec-22 | 27-Dec-22 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
57 | Supply of main incomer & outgoing panel | 20 | 0% | 10-Dec-22 | 30-Dec-22 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
58 | Installation of DBs and main panel | 3 | 0% | 31-Dec-22 | 3-Jan-23 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
59 | Completion of cable laying and termination | 5 | 0% | 4-Jan-23 | 9-Jan-23 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
60 | Supply of light fixtures | 20 | 0% | 10-Dec-22 | 30-Dec-22 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
61 | Installation of light fixtures | 3 | 0% | 8-Jan-22 | 11-Jan-22 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
62 | Modular furniture sockets termination complete | 2 | 0% | 27-Jan-23 | 29-Jan-23 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
63 | Data all IO termination complete | 2 | 0% | 27-Jan-23 | 29-Jan-23 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
64 | Electrical testing and commissioning | 1 | 0% | 30-Jan-23 | 30-Jan-23 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
65 | HVAC | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
66 | Supply of AHU, CSU, Cassette unit and accessories | 30 | 0% | 13-Dec-22 | 12-Jan-23 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
67 | Supply of PUF Duct | 21 | 0% | 13-Dec-22 | 3-Jan-23 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
68 | Installation of duct, plenum | 5 | 0% | 4-Jan-23 | 9-Jan-23 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
69 | Installation of AHU, CSU,cassette unit and pipe | 5 | 0% | 12-Jan-23 | 17-Jan-23 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
70 | Commissioning of HVAC system | 1 | 0% | 17-Jan-23 | 18-Jan-23 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
71 | Air Balancing | 1 | 0% | 18-Jan-23 | 18-Jan-23 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
72 | Safety & Security | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
73 | Supply of Materials | 28 | 0% | 13-Dec-22 | 10-Jan-23 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
74 | Installation of conduit, detector, speaker and cable laying | 20 | 0% | 25-Dec-22 | 14-Jan-23 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
75 | Commissioning of Safety and security system | 2 | 0% | 16-Jan-23 | 18-Jan-23 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
76 | Pendent sprinkler installation and final testing | 5 | 0% | 12-Jan-23 | 17-Jan-23 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
77 | Network | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
78 | Supply of Materials | 15 | 0% | 13-Dec-22 | 28-Dec-22 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
79 | Cable laying and termination | 10 | 0% | 30-Dec-22 | 9-Jan-23 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
80 | Data all IO termination complete | 2 | 0% | 27-Jan-23 | 29-Jan-23 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
81 | BMS | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
82 | Supply of materials | 30 | 0% | 13-Dec-22 | 12-Jan-23 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
83 | Installation of DDC, controller, cable laying and termination | 4 | 0% | 12-Jan-23 | 16-Jan-23 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
84 | Testing and commissioning | 1 | 0% | 16-Jan-23 | 17-Jan-23 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
85 | AV | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
86 | Supply of Materials | 20 | 0% | 13-Dec-22 | 2-Jan-23 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
87 | Installation of fixing support and painting clearance | 2 | 0% | 11-Jan-23 | 13-Jan-23 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
88 | Testing and commissioning | 1 | 0% | 16-Jan-23 | 17-Jan-23 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
89 | Deep cleaning and house keeping | 2 | 0% | 18-Jan-23 | 20-Jan-23 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
90 | Handover - Training & Documents Submission, snag & de-snag | 3 | 0% | 30-Jan-23 | 2-Feb-23 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
91 | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
92 | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
93 | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
94 | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
95 | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
96 | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
97 | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
98 | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
99 | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
100 | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||