Create a Project Schedule in this worksheet.
Enter title of this project in cell B1.
Information about how to use this worksheet, including instructions for screen readers and the author of this workbook is in the About worksheet.
Continue navigating down column A to hear further instructions.
INTERIOR FITOUT PROJECT @ LOCATION
2
PROJECT SCHEDULE
3
Project Start:Mon, 12/5/2022
4
The Display Week in cell E4 represents the starting week to display in the project schedule in cell I4. The project start date is considered Week 1. To change the display week, simply enter a new week number in cell E4.
The starting date for each week, starting with the display week from cell E4, starts in cell I4 and is auto calculated. There are 8 weeks represented in this view from cell I4 through cell BF4.
You should not modify these cells.
Display Week: label is in cell C4.
Display Week:1Dec 5, 2022Dec 12, 2022Dec 19, 2022Dec 26, 2022Jan 2, 2023Jan 9, 2023Jan 16, 2023Jan 23, 2023Jan 30, 2023
5
Cells I5 through BL5 contain the day number for the week represented in the cell block above each date cell and are auto calculated.
You should not modify these cells.
Today's date is outlined in Red (hex #AD3815) from today's date in row 5 through the entire date column to the end of the project schedule.
56789101112131415161718192021222324252627282930311234567891011121314151617181920212223242526272829303112345
6
This row contains headers for the project schedule that follows below them.
Navigate from B6 through BL 6 to hear the content. The first letter of each day of the week for the date above that heading, starts in cell I6 and continues through cell BL6.
All project timeline charting is auto generated based on the start and end dates entered, using conditional formats.
Do not modify content in cells within columns after column I starting with cell I7.
ACTIVITY NAMEDURATIONPROGRESSSTARTENDMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSS
9
Civil & Interior
10
Cell B9 contains the sample task "Task 1."
Enter a new task name in cell B9.
Enter a person to assign the task to in cell C9.
Enter progress of the task in cell D9. A progress bar appears in the cell and is shaded according to the number in the cell. For example, 50 percent progress would shade half of the cell.
Enter task start date in cell E9.
Enter task end date in cell F9.
A status bar shaded for the dates entered appears in blocks starting from cell I9 through BL9.
Issuance of LOI/PO10%5-Dec5-Dec-22
11
Rows 10 through 13 repeat the pattern from row 9.
Repeat the instructions from cell A9 for all task rows in this worksheet. Overwrite any sample data.
A sample of another phase starts in cell A14.
Continue entering tasks in cells A10 through A13 or go to cell A14 to learn more.
Team Mobilization40%6-Dec-229-Dec-22
12
Issuance of GFC drawing details10%5-Dec-225-Dec-22
13
Issuance of Partition Marking layout 10%6-Dec-226-Dec-22
14
Issuance of Finishes Schedule10%7-Dec-227-Dec-22
15
Issuance of workstation marking layout10%7-Dec-227-Dec-22
16
Approval of workstation marking10%8-Dec-228-Dec-22
17
Approval of partition marking 10%9-Dec-229-Dec-22
18
Temporary power and water arrangements20%7-Dec-229-Dec-22
19
Temporary light arrangements20%8-Dec-229-Dec-22
20
Prominent display of HSE posters and establishment of safety infrastructure at site10%10-Dec-2210-Dec-22
21
Preparation of all packages MEP drawings30%6-Dec-229-Dec-22
22
Submission and approval of MEP drawings10%9-Dec-2210-Dec-22
23
Submission of interior finishes samples and approval20%8-Dec-2210-Dec-22
24
Submission and Approval of MEP samples/TDS for all works30%10-Dec-2213-Dec-22
25
POP punning/Surface preparation works complete in open office50%10-Dec-2215-Dec-22
26
Supply and installation of tiles 180%10-Dec-2228-Dec-22
27
Partition frameworks complete30%10-Dec-2213-Dec-22
28
Single side single skin boarding works complete for MEP clearance20%13-Dec-2215-Dec-22
29
Column cladding/Long wall panelling framework complete70%10-Dec-2217-Dec-22
30
MEP clearances for partition board closing40%17-Dec-2221-Dec-22
31
Acoustic fill and double skin second side board closing50%21-Dec-2227-Dec-22
32
All columns/wall Panelling works closing complete100%17-Dec-2227-Dec-22
33
Completion of PHE services130%13-Dec-2226-Dec-22
34
All partitions gypsum surface preparation with 2 coats primer and 2 coats putty80%27-Dec-224-Jan-23
35
All type ceiling framework and boarding complete with finishing - MEP coordiantion50%4-Jan-239-Jan-23
36
Reception table/Board room/Table and site made joinery carcass complete150%10-Dec-2225-Dec-22
37
Reception table/Board Room/Tables finishing works complete100%26-Dec-225-Jan-23
38
Factory made items delivery at site120%2-Jan-2214-Jan-22
39
Lacquered glasses and acoustic boards,wall paper, sanitary fittings supply180%13-Dec-2231-Dec-22
40
All partitions second coat paint complete30%10-Jan-2313-Jan-23
41
Installation of all grid ceiling tiles with final alignment20%12-Jan-2314-Jan-23
42
Supply of carpet material450%7-Dec-2221-Jan-23
43
Completion of carpet installation20%22-Jan-2324-Jan-23
44
Supply of workstation and tables450%7-Dec-2221-Jan-23
45
Completion of workstation installation40%22-Jan-2327-Jan-23
46
Transition Profile installations20%24-Jan-2327-Jan-23
47
Loose Furniture
48
Submission and approval of samples/Finishes20%7-Dec-229-Dec-22
49
Supply of loose furniture material350%10-Dec-2214-Jan-23
50
Transporting and shifting30%14-Jan-2317-Jan-23
51
Installation and handover10%18-Jan-2318-Jan-23
52
Electrical
53
Completion of raceway marking, cutting40%10-Dec-2214-Dec-22
54
Raceway, junction box supply & installation80%12-Dec-2220-Dec-22
55
Supply of conduit, cable tray, wires, DBs120%10-Dec-2222-Dec-22
56
Completion of conduit and cable tray40%23-Dec-2227-Dec-22
57
Supply of main incomer & outgoing panel200%10-Dec-2230-Dec-22
58
Installation of DBs and main panel30%31-Dec-223-Jan-23
59
Completion of cable laying and termination50%4-Jan-239-Jan-23
60
Supply of light fixtures200%10-Dec-2230-Dec-22
61
Installation of light fixtures30%8-Jan-2211-Jan-22
62
Modular furniture sockets termination complete20%27-Jan-2329-Jan-23
63
Data all IO termination complete20%27-Jan-2329-Jan-23
64
Electrical testing and commissioning10%30-Jan-2330-Jan-23
65
HVAC
66
Supply of AHU, CSU, Cassette unit and accessories300%13-Dec-2212-Jan-23
67
Supply of PUF Duct210%13-Dec-223-Jan-23
68
Installation of duct, plenum50%4-Jan-239-Jan-23
69
Installation of AHU, CSU,cassette unit and pipe50%12-Jan-2317-Jan-23
70
Commissioning of HVAC system10%17-Jan-2318-Jan-23
71
Air Balancing10%18-Jan-2318-Jan-23
72
Safety & Security
73
Supply of Materials280%13-Dec-2210-Jan-23
74
Installation of conduit, detector, speaker and cable laying200%25-Dec-2214-Jan-23
75
Commissioning of Safety and security system20%16-Jan-2318-Jan-23
76
Pendent sprinkler installation and final testing 50%12-Jan-2317-Jan-23
77
Network
78
Supply of Materials150%13-Dec-2228-Dec-22
79
Cable laying and termination100%30-Dec-229-Jan-23
80
Data all IO termination complete20%27-Jan-2329-Jan-23
81
BMS
82
Supply of materials300%13-Dec-2212-Jan-23
83
Installation of DDC, controller, cable laying and termination40%12-Jan-2316-Jan-23
84
Testing and commissioning10%16-Jan-2317-Jan-23
85
AV
86
Supply of Materials200%13-Dec-222-Jan-23
87
Installation of fixing support and painting clearance20%11-Jan-2313-Jan-23
88
Testing and commissioning10%16-Jan-2317-Jan-23
89
Deep cleaning and house keeping20%18-Jan-2320-Jan-23
90
Handover - Training & Documents Submission, snag & de-snag30%30-Jan-232-Feb-23
91
92
93
94
95
96
97
98
99
100
101
102