1 | Risk Category | Task | Description | Low Budget | High Budget | Min Time (days) | Max Time (days) | Standard Risk | ||||||||||||||
2 | Site Control | Letter of Intent | Sign LOI with landowner | 0 | 0 | 30 | 60 | 4 | ||||||||||||||
3 | Interconnection | Preapplication (Informal Request) | Request electric system information, give utility contact a call | 0 | 0 | 5 | 9 | 1 | ||||||||||||||
4 | Permitting | Initial AHJ Consultation | Initial consultation with AHJ to confirm understanding of ordinance + permitting process | 0 | 0 | 5 | 9 | 5 | ||||||||||||||
5 | Interconnection | Preapplication (Formal Request) | Nonrefundable fee for preapplication report | 500 | 1,000 | 10 | 18 | 3 | ||||||||||||||
6 | Site Control | Site Visit | Vist property to speak with landowner, form relationship | 200 | 500 | 3 | 5 | 2 | ||||||||||||||
7 | Design | Initial Concept Plan | High level layout of project with current understanding of site restrictions (all desktop), single line diagram | 1,000 | 1,000 | 7 | 14 | 1 | ||||||||||||||
8 | Interconnection | Standard Interconnection Application | Submit filled-out application form. Requires Appendix H (landowner consent form). | 750 | 750 | 7 | 30 | 1 | ||||||||||||||
9 | Interconnection | Preliminary Review | Discuss interconnection request and preliminary interdependency determination. | 0 | 1,000 | 14 | 28 | 10 | ||||||||||||||
10 | Interconnection | CESIR Study Application | Confirm that you want to proceed with CESIR study and submit requisite information | 0 | 0 | 7 | 14 | 1 | ||||||||||||||
11 | Environmental | Preliminary Wetlands Assessment | Perform a site visit to confirm the presence or absence of freshwater wetlands and waters on the project site prior to full delineation. | 2,750 | 5,000 | 18 | 24 | 4 | ||||||||||||||
12 | Site Control | Lease Area and Easement Plan | Prepare a Lease Area Plan showing the area access and utility easements required, certified by a professional surveyor | 3,500 | 3,500 | 20 | 40 | 6 | ||||||||||||||
13 | Site Control | Title Policy Report | Title policy and report containing essential information about the property's title, including any recorded claims, encumbrances, and other matters | 1,000 | 1,000 | 20 | 40 | 3 | ||||||||||||||
14 | Site Control | Execute Lease Agreement | Negotiate and execute lease agreement with landlord | 2,000 | 3,000 | 30 | 180 | 12 | ||||||||||||||
15 | Interconnection | CESIR Payment | Submit payment. Have 14 days after app is submitted + invoice received to determine whether to spend money. | 15,000 | 25,000 | 1 | 14 | 1 | ||||||||||||||
16 | Interconnection | CESIR Study | Utility does the study | 0 | 0 | 80 | 96 | 3 | ||||||||||||||
17 | Environmental | Wetland Delineation Report | Requires a site visit, review of federal, state, and local documents, and identification of any wetlands and their flood hazard potential. | 10,000 | 12,500 | 110 | 130 | 10 | ||||||||||||||
18 | Environmental | Ecological Assessment | Evaluation of habitat and wildlife impacts, including mitigation strategies. | 5,000 | 15,000 | 30 | 120 | 6 | ||||||||||||||
19 | Environmental | Environmental Site Assessment (ESA) Phase I | Preliminary investigation that identifies potential or existing environmental contamination liabilities on a property through historical research, site inspection, and regulatory review. | 4,000 | 5,500 | 30 | 40 | 3 | ||||||||||||||
20 | Design | Boundary & Topographic Property Survey | A full Boundary Survey of the perimeter of the parcel whichshall include any necessary deed and plan research | 17,000 | 25,000 | 60 | 90 | 3 | ||||||||||||||
21 | Environmental | Cultural Resource Survey | Assessment of potential impacts of a project on historic/cultural properties or archaeological resources. SHPO analysis. | 5,000 | 15,000 | 30 | 120 | 6 | ||||||||||||||
22 | Design | Geotechnical Analysis | Conduct field borings and testing to ensure subsurface can support solar farm | 26,500 | 26,500 | 60 | 90 | 3 | ||||||||||||||
23 | Interconnection | CESIR Study Review | Review cost determinations | 0 | 0 | 14 | 90 | 15 | ||||||||||||||
24 | Interconnection | NY Standardized Interconnection Contract (IA) | Come to terms on exact costs of upgrade and sign agreement | 0 | 0 | 5 | 14 | 5 | ||||||||||||||
25 | Permitting | Pre-Application Meeting | Pre-application meeting with the code enforcement officer to obtain recommended procedures, and technical assistance for the permitting process. Meet with other local stakeholders | 0 | 0 | 7 | 7 | 5 | ||||||||||||||
26 | Site Control | Record Lease Memorandum | A Memorandum of Lease is a recordable document that provides public notice of a lease's existence | 1,000 | 1,000 | 7 | 7 | 1 | ||||||||||||||
27 | Permitting | Decommissioning Agreement | Agree on LO & applicant obligations, and pay financial security of 150% of est. removal cost | 1,000 | 3,000 | 7 | 7 | 1 | ||||||||||||||
28 | Permitting | Prepare Site Plan + Special Use Permit Application Package | Landscaping Plan, Stormwater Management Plan, abutter consent, Site Plan Design for site plan - Property Maintenance Plan, Glare Study, Noise Study, Construction Plan, PILOT Agreement, Decomissioning Plan + Agreement, Visual Resource Assessment, SEQR | 39,000 | 77,000 | 90 | 120 | 3 | ||||||||||||||
29 | Permitting | Community Engagement Meeting | Hold a public meeting before the Planning Commission's public hearing. Notify the zoning administrator and adjacent property owners in writing and advertise the meeting in a newspaper of record. | 0 | 0 | 7 | 30 | 8 | ||||||||||||||
30 | Permitting | Public Hearing | A public hearing will be held, allowing parties in interest and citizens to be heard. Notice of the hearing will be published in a newspaper with general circulation in the county. | 0 | 10,000 | 14 | 30 | 8 | ||||||||||||||
31 | Permitting | Town Board Review | The Planning Commission reviews the application and provides a report to the Board of Supervisors. If the Planning Commission does not act within 100 days, the application is considered approved. | 0 | 0 | 14 | 30 | 10 | ||||||||||||||
32 | Interconnection | 25% Interconnection Deposit | Make 25% payment of total cost quoted in IA | 130,000 | 130,000 | 14 | 90 | 3 | ||||||||||||||
33 | ||||||||||||||||||||||
34 | ||||||||||||||||||||||
35 | ||||||||||||||||||||||
36 | ||||||||||||||||||||||
37 | ||||||||||||||||||||||
38 | ||||||||||||||||||||||
39 | ||||||||||||||||||||||
40 | ||||||||||||||||||||||
41 | ||||||||||||||||||||||
42 | ||||||||||||||||||||||
43 | ||||||||||||||||||||||
44 | ||||||||||||||||||||||
45 | ||||||||||||||||||||||
46 | ||||||||||||||||||||||
47 | ||||||||||||||||||||||
48 | ||||||||||||||||||||||
49 | ||||||||||||||||||||||
50 | ||||||||||||||||||||||
51 | ||||||||||||||||||||||
52 | ||||||||||||||||||||||
53 | ||||||||||||||||||||||
54 | ||||||||||||||||||||||
55 | ||||||||||||||||||||||
56 | ||||||||||||||||||||||
57 | ||||||||||||||||||||||
58 | ||||||||||||||||||||||
59 | ||||||||||||||||||||||
60 | ||||||||||||||||||||||
61 | ||||||||||||||||||||||
62 | ||||||||||||||||||||||
63 | ||||||||||||||||||||||
64 | ||||||||||||||||||||||
65 | ||||||||||||||||||||||
66 | ||||||||||||||||||||||
67 | ||||||||||||||||||||||
68 | ||||||||||||||||||||||
69 | ||||||||||||||||||||||
70 | ||||||||||||||||||||||
71 | ||||||||||||||||||||||
72 | ||||||||||||||||||||||
73 | ||||||||||||||||||||||
74 | ||||||||||||||||||||||
75 | ||||||||||||||||||||||
76 | ||||||||||||||||||||||
77 | ||||||||||||||||||||||
78 | ||||||||||||||||||||||
79 | ||||||||||||||||||||||
80 | ||||||||||||||||||||||
81 | ||||||||||||||||||||||
82 | ||||||||||||||||||||||
83 | ||||||||||||||||||||||
84 | ||||||||||||||||||||||
85 | ||||||||||||||||||||||
86 | ||||||||||||||||||||||
87 | ||||||||||||||||||||||
88 | ||||||||||||||||||||||
89 | ||||||||||||||||||||||
90 | ||||||||||||||||||||||
91 | ||||||||||||||||||||||
92 | ||||||||||||||||||||||
93 | ||||||||||||||||||||||
94 | ||||||||||||||||||||||
95 | ||||||||||||||||||||||
96 | ||||||||||||||||||||||
97 | ||||||||||||||||||||||
98 | ||||||||||||||||||||||
99 | ||||||||||||||||||||||
100 |