Risk CategoryTaskDescriptionLow BudgetHigh BudgetMin Time (days)Max Time (days)Standard Risk
2
Site Control Letter of Intent Sign LOI with landowner 0030604
3
InterconnectionPreapplication (Informal Request)Request electric system information, give utility contact a call 00591
4
PermittingInitial AHJ ConsultationInitial consultation with AHJ to confirm understanding of ordinance + permitting process00595
5
InterconnectionPreapplication (Formal Request)Nonrefundable fee for preapplication report5001,00010183
6
Site Control Site Visit Vist property to speak with landowner, form relationship 200500352
7
DesignInitial Concept PlanHigh level layout of project with current understanding of site restrictions (all desktop), single line diagram 1,0001,0007141
8
InterconnectionStandard Interconnection Application Submit filled-out application form. Requires Appendix H (landowner consent form). 7507507301
9
InterconnectionPreliminary ReviewDiscuss interconnection request and preliminary interdependency determination.01,000142810
10
InterconnectionCESIR Study Application Confirm that you want to proceed with CESIR study and submit requisite information 007141
11
EnvironmentalPreliminary Wetlands Assessment
Perform a site visit to confirm the presence or absence of freshwater wetlands and waters on the project site prior to full delineation.
2,7505,00018244
12
Site Control Lease Area and Easement Plan
Prepare a Lease Area Plan showing the area access and utility easements required, certified by a professional surveyor
3,5003,50020406
13
Site Control Title Policy Report
Title policy and report containing essential information about the property's title, including any recorded claims, encumbrances, and other matters
1,0001,00020403
14
Site Control Execute Lease AgreementNegotiate and execute lease agreement with landlord2,0003,0003018012
15
InterconnectionCESIR PaymentSubmit payment. Have 14 days after app is submitted + invoice received to determine whether to spend money. 15,00025,0001141
16
InterconnectionCESIR StudyUtility does the study 0080963
17
EnvironmentalWetland Delineation Report
Requires a site visit, review of federal, state, and local documents, and identification of any wetlands and their flood hazard potential.
10,00012,50011013010
18
EnvironmentalEcological Assessment Evaluation of habitat and wildlife impacts, including mitigation strategies.5,00015,000301206
19
EnvironmentalEnvironmental Site Assessment (ESA) Phase I
Preliminary investigation that identifies potential or existing environmental contamination liabilities on a property through historical research, site inspection, and regulatory review.
4,0005,50030403
20
DesignBoundary & Topographic Property SurveyA full Boundary Survey of the perimeter of the parcel whichshall include any necessary deed and plan research17,00025,00060903
21
EnvironmentalCultural Resource Survey
Assessment of potential impacts of a project on historic/cultural properties or archaeological resources. SHPO analysis.
5,00015,000301206
22
DesignGeotechnical Analysis Conduct field borings and testing to ensure subsurface can support solar farm 26,50026,50060903
23
InterconnectionCESIR Study ReviewReview cost determinations 00149015
24
InterconnectionNY Standardized Interconnection Contract (IA)Come to terms on exact costs of upgrade and sign agreement 005145
25
PermittingPre-Application Meeting
Pre-application meeting with the code enforcement officer to obtain recommended procedures, and technical assistance for the permitting process. Meet with other local stakeholders
00775
26
Site Control Record Lease MemorandumA Memorandum of Lease is a recordable document that provides public notice of a lease's existence1,0001,000771
27
PermittingDecommissioning AgreementAgree on LO & applicant obligations, and pay financial security of 150% of est. removal cost1,0003,000771
28
Permitting
Prepare Site Plan + Special Use Permit Application Package
Landscaping Plan, Stormwater Management Plan, abutter consent, Site Plan Design for site plan - Property Maintenance Plan, Glare Study, Noise Study, Construction Plan, PILOT Agreement, Decomissioning Plan + Agreement, Visual Resource Assessment, SEQR
39,00077,000901203
29
PermittingCommunity Engagement Meeting
Hold a public meeting before the Planning Commission's public hearing. Notify the zoning administrator and adjacent property owners in writing and advertise the meeting in a newspaper of record.
007308
30
PermittingPublic Hearing
A public hearing will be held, allowing parties in interest and citizens to be heard. Notice of the hearing will be published in a newspaper with general circulation in the county.
010,00014308
31
PermittingTown Board Review
The Planning Commission reviews the application and provides a report to the Board of Supervisors. If the Planning Commission does not act within 100 days, the application is considered approved.
00143010
32
Interconnection25% Interconnection Deposit Make 25% payment of total cost quoted in IA 130,000130,00014903
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
80
81
82
83
84
85
86
87
88
89
90
91
92
93
94
95
96
97
98
99
100