PVFF Action Plan
 Share
The version of the browser you are using is no longer supported. Please upgrade to a supported browser.Dismiss

 
View only
 
 
ABCEFGHIJKLMN
1
ID
Relates to ID
Date Raised
Parish
Assigned To (Organisation)
Assigned To (Person)
Original Due Date
Latest Due Date
Action
Last Updated
StatusStatus NotesFlood Forum Comments
2
3201/01/2014
Stanford Dingley
TWTW Stanford Dingley strategy
Determine location of ingress to sewer network in Stanford Dingley.
23/01/2018In progressDepth logger data has been reviewed but  not conclusive for points of ingresss. TW have confirmed they will now be trying smoke testing.

24/01/2017 work to line a sewer to be completed by 02/2017. However there remain problems in SD that require regular tanker visits and thus TW are carrying out further investigations via manhole lifting. 2 of 4 loggers are still working.

23/05/2017 TW to carry out an IAS survey when we have a wet winter. New Flygt pumps to be implement this summer in SD station.

26/09/2017 Flygt pumps installed July 2017 (and a 2nd in Nov 2017) but damage done to 'ducks foot' base during installation. Repair due to start 26th Oct and due to take two days. All manhole covers on Jennetts Hill have been replaced and the impermeable survey has been completed showing no misconnections in the Frilsham area, which further narrows the area of search. The data logger is still to be moved around but there is a wider programme of depth monitoring in the Thames Valley area so we are looking to move these but also see if we can install some flow monitors/data loggers that feed directly into our modelling software. We have also completed flow monitoring on the rising main in June which gave us information on the pump rate through the rising main.

23/01/2018 Ducks foot (bases for the pumps) have been replaced and thus second Flygy pump installed. Still trying to narrow where the ingress is happening. Data loggers are still to be moved. Track to sewer pumping station needs attention.
Smoke test completed. As a result 4 pieces of work have now been raised by TW (3 in Frilsham and 1 in Stanford D) and now done.

18/5/2017 Meeting held in SD with BC, MH, KL and Andrew Hagger TW, Denise Kinsella TW and James Hoar TW.Maps of sewage pipework discussed and it was agreed that two flow monitors near Frilsham that were key to locating point of ingress were not working properly and possibly needed replacing. One data logger on Jennetts Hill to be moved up to Frilsham area to triangulate location of ingress. Some manholes still needing to be replaced on Jennetts Hill. An impermeable area survey was due to be done in Frilsham in approx 2-3 weeks time.  It was noted that it may still take some time to locate point of ingress and it may not be possible to do so until next winter and return of wetter weather. TW were keen to get to bottom of problem as SD was one of only two areas that had confounded them.
3
454115/09/2015
All Parishes
PVFF01/10/2015Devise a village-centric account of causes, consequences and escalating risk levels. Mapping stage 212/01/2016On holdThis activity should be phase 2 of the Pang Valley flood risk mapping exercise
4
4815/09/2015West IlsleyWBCS Clark01/03/201631/03/2016West Ilsley to East Ilsley Road - investigate new road crossing at EA pump station.26/09/2017On holdTo be investigated in the 15/16 FY. No progress yet as of 12/01/2016.

20/09/2016 update: A pipe has been found. WBC to investigate opening up the pipe, liaising with the landowner on either side. This could not be done in FY16/17 as budget is committed.

24/01/2017 SC aims to look for funds in 17/18. PVFF Tech group will include this area in their slow sections.

23/05/2017 Pending suitable funds and staff availability.

26/09/2017 Currently on hold
No progress as at 18/05/2017.  Road crossing is the re-instatement of an existing culvert under Windmill Road. see 48.1 No Progress as at 26/9/2017
5
5015/09/2015West IlsleyWBCS Clark01/03/201631/03/2016WBC West Ilsley drainage scheme.
Capital investigation into the upgrade of the surface water system through West Ilsley (Defra funded feasibility)
26/09/2017In progressSite meeting held with consultant on 24th November. Feasibility has been completed. Level survey to be completed. To progress further SC must meet consultant on the cost of feasibility.

24/01/2017 This study is in progress and study should complete by end of 03/2017.

23/05/2017 Feasibility study in progress.

26/09/2017 Business case submitted to the EA. It is likely that the recommendation will be for property level protection.
SC is still working on the business case.  Not 100% sure there is a viable solution but will carry on with the current proposal and submit the business case in June 2017. If we do have a viable scheme SC would look to do the detailed design next year (2018)and construct the year after (2019). 26/09/2017 Business case submitted to the EA
6
51.15112/01/2016West IlsleyTW01/01/2017TW West Ilsley strategy.
TW to create a whole drainage strategy for West Ilsley
23/01/2018In progressWest Ilsley Drainage strategy is within East Ilsley Drainage Strategy as the name is based on the location of the sewage treatment works. Stage 1 is on the TW website. Stage 2 due 1/9/2016

23/05/2017 Survey conducted in Compton but then it was dry. Not the best data. Awaiting wetter weather.

26/09/2017 Groundwater remains low. No progress.

23/01/2018 With regards to the update / holding reports, these have been delayed, the aim is now to have them published in February 2018 Apologies for the delay.
Now there won't be a Stage 2 report - there will be a combined Stage 2 and 3.  DK and TS will update us on progress at the next meeting. 23/01/2018 With regards to the update / holding reports, these have been delayed, the aim is now to have them published in February 2018 Apologies for the delay.,
7
5815/09/2015
Hampstead Norreys
WBCS Clark01/03/2016WBC Hampstead Norreys scheme.
Investigate a permanent overflow channel around Hampstead Norreys as provided during the flooding.
23/01/2018In progress1. Overflow swale in field
2. Blockage on bridge on B4009(underground channel to water meadow) – this wasn’t part of the WBC bid and there is a restriction below the B4009
3. Sewage ingress was missed. WBC resubmitted a project mandate for the works - pending a response.

23/05/2017 Preliminary Design and Business Case 2017/18, Detailed design 2018/19, construction 2019/20

26/9/2017 Preminary design and Business Case in progress

23/01/2018 Still in progress.
Hampstead Norreys – Preliminary Design and Business Case 2017/18, Detailed design 2018/19, construction 2019/20. 26/9/2017 Preminary design and Business Case in progress
8
5915/09/2015
Stanford Dingley
WBCS Clark01/03/2016WBC Stanford Dingley bypass scheme.
Bid submitted to Defra (RFCC Grant Funding) for permanent bypass channel around Stanford Dingley.
23/01/2018In progressBid submitted through EA, awaiting confirmation of RFCC programme. Funding awarded for the investigation and feasibility in the 2015/16 financial year. UPDATE - The estimated cost of the study is higher than the grant allocation. Application for additional grant money submitted to the EA. It is Surface Water flooding. WBC have found money to conduct the study, design and create the PAR (aka the business case). PAR work has started with consultant working on this.

20/09/2016: when the consultants have a design and a model, SC to share with Stanford Dingley (Mark) by end of 03/2017

23/05/2017 PAR would allow 75 year protection. Business case stacks up.

26/09/2017 Detailed design in progress.

23/01/2018 WBC agents (Dalcour Maclaren) have visited the village. Next steps should involve a topographical survey. Indicated that diggers might arrive this year (2018).
.The scheme has been allocated 215k this year in the current EA Medium term programme. SC will begin the detailed design June 2017 . The current cost estimate for design and construction is 450k which includes the cost of lowering existing utilities underneath road. SC will need to discuss whether further funds will be available to take the scheme forward but the business case still stacks up. 26/09/2017 Detailed design in progress
9
6612/01/2016ComptonTW01/01/2017TW Compton strategy.
TW to create a whole drainage strategy for Compton
23/01/2018In progressCompton Drainage Strategy Stage 1 on TW website

20/09/2016: TW will implement flow monitors in Compton to see if there is infiltration. Also planning to do CCTV work. Depth monitors in place, also in Hampstead Norreys.

24/01/2017 Update is the same for 20/09/2016 - current low water levels prevent data gathering. TW to share trigger level for groundwater level when leaks might start into the sewer system. Installing rising main monitors East Ilsley pumping station and HN pumping station (budget is committed).

23/05/2017 CCTV surveys scheduled, but need more groundwater for the work to succeed.

26/09/2017 CCTV surveys scheduled, but need more groundwater for the work to succeed. TW will create a holding document update for WI, EI, Co, HN assessments.

23/01/2018 3 Flow Monitors were installed in Compton from the 24/03/2017 to the 08/05/2017 (that have now been removed), during a fairly dry period, as such no signs of infiltration were seen / expected. This is now available as a good baseline for when the higher ground water levels return. With regards to the update / holding reports, these have been delayed, the aim is now to have them published in February 2018. TW to send link when reports are published to PVFF.
The next step will be a combined Stage 2 and 3.  DK and TS will update on progress at the next PVFF meeting.
10
7724/01/2017
All Parishes
PVFFPAPVFF website - emergency details.
Add to website the EA emergency contact details
21/01/2018In progress21/01/2018 Completed. Now on PVFF homepage.

23/01/2018 PA to add TW phone number
11
78.27823/01/2017
Pangbourne
EAMWPangbourne and Tidmarsh flood modelling.
EA to share results of the CH2M modelling for the Pang and Sulham Brook in the Pangbourne and Tidmarsh areas.
23/01/2018In progressMeeting to be arranged with Pangbourne project team re modelling CH2M

26/09/2017 Meeting held on 7th July in Pangbourne with site visit including Moor Copse and Tidmarsh. Notes from meeting are on website. Further photos and information subsequesntly sent to CH2M to assist with their modelling. Update awaited. Phase 1 modelling by Ch2m has been updated with new information provided by PVFF people - this now matches what happened in 2007 and 2014. This means that EA will fund further modelling.
Option then to be considered:
1. Home Farm bypass
2. Flood Storage area
3. Raise banks along the Pang

Review meeting to be arranged after stage 2 modelling is complete.

23/01/2018 Rashmi Krishnan is new Project manager for this. CH2M have successfully managed to create a flood model that represents what happened in 2007. This took longer than expected. A non-technical reason for this delay is because they couldn’t adjust one of the gauging stations to reflect what happened in 2007. I think this was the Tidmarsh gauge. This has now been resolved. The next step is to update the hydrology to show the changes that have happened since 2007. These are the things such as the flood wall, channel maintenance and the other improvements that were shared with us at the site meeting back in the Summer. The consultants are going to inform us how they plan to do this in January. We can then identify if anything has been missed.

23/01/2018 EA to invite PVFF Pangbourne and Tidmarsh reps to review the model and options for a scheme.
Meeting held on 7th July in Pangbourne with site visit including Moor Copse and Tidmarsh. Notes from meeting are on website. Further photos and information subsequesntly sent to CH2M to assist with their modelling. Update awaited. 23/01/2018 Rashmi Krishnan is new Project manager for this. CH2M have successfully managed to create a flood model that represents what happened in 2007. This took longer than expected. A non-technical reason for this delay is because they couldn’t adjust one of the gauging stations to reflect what happened in 2007. I think this was the Tidmarsh gauge. This has now been resolved. The next step is to update the hydrology to show the changes that have happened since 2007. These are the things such as the flood wall, channel maintenance and the other improvements that were shared with us at the site meeting back in the Summer. The consultants are going to inform us how they plan to do this in January. We can then identify if anything has been missed.
12
7924/01/2017
Pangbourne
WBCPangbourne mill clearing.23/01/2018In progressThe build up of slit downstream of the mill has been removed. A budget estimate to clear and remove silt immediately upstream of the mill would be about £5k, plus another £4k to replace the trash screen.

23/05/2017 It may be that further work is not needed. Initial clearing may have helped. Pangbourne PC to observe.

26/09/2017 WBC to show Thames Water (mill owners) where extra silt removal should be done upstream.

23/01/2018 No progress.
13
8024/01/2017
All Parishes
WBCJacobs report - impact of climate change.
WBC to investigate if the Jacobs report might change if the rain levels were increased by 30%
18/05/2017On hold18/05/2017 No progress yet.
23/05/2017 Put on hold until National Goundwater study is published.
23/01/2018. Peter to check if this has been published.
14
8224/01/2017
All Parishes
PVFFG DavidsonPVFF Flood Warden leaflet.
Draft a flood warden role document to circulate across the forum
21/01/2018In progress26/09/2017 GD has created a draft. Now all PVFF reps should review.

21/03/2018 WBC have been included and the updated document is now published on the PVFF website (and linked to from the homepage). Kay and Stephen to tweak and make extra user friendly.
15
8424/01/2017TidmarshPVFFTidmarsh bank strengthening.
Bank strengthening work was done. The work was not done well and needs to be completed and to be fenced off. Kay to raise with them.
23/01/2018In progressCL has checked the re-instated bank 20/5/2017 and happy that it is now re-vegetating and it also appears to be partly fenced off by BBOWT staff. However at the lasher weir the trash screen is still missing.  CL to follow up with BBOWT.  The logs on the bank also need to be secured with hoops of rebar.  GD and CL will do this.

23/01/2018 GD and CL still to complete.
16
87.18723/01/2017
All Parishes
PVFFPeter McGeehinGroundwater project.
PM to seek written confirmation on whether WBC, TW will commit funding to assist further research beyond the MSC (as EA (DB) confirmed that they would if the others did).
21/01/2018In progressMSC is due to finish on 23/08/2017. PM to receive the MSC thesis that can then be shared.

21/01/2018 MSc Thesis complete. Copy sent to PMcG and Tech Sub Group.
MSc Thesis complete. Copy sent to PMcG and Tech Sub Group.
17
8926/09/2017
Pangbourne Parish Council
John HiggsThames Path.
Kay to contact WBC (Carolyn) and follow up whether the Thames Path work has been completed.
23/01/2018Pending SignOff23/01/2018 Some work done. JH to and PPC to liaise with National Trails Officer and Elaine Cox at WBC if further work needed
18
9326/09/2017PVFFAll parishesParish Donations.
Each PVFF rep to ask their local parish council to donate a recurring amount of £100 per annum
23/01/2018In progress23/01/2018 £100 received from Compton PC. Emails have been sent to each parish council.
19
9426/09/2017PVFFAll parishes2007 and 2014 reports.
Each PVFF rep to look at the 2007 and 2014 reports for their parish to see what was recommended.
23/01/2018In progress23/01/2018 KL provided spreadsheets for each parish, with their recommendations and a request for comments and notes as to whether completed. Stuart and Carolyn will now review and revert to the Flood Forum with an update as to why recommendations not completed, whether they have been superceded or whether they can be added to the Action Plan
20
9523/01/2018PVFFPangbournePangbourne flood depths.
Pangbourne parish council to collect flood depth levels from 2014 and 2007 flood properties.
23/01/2018New
21
9623/01/2018EAD. DukesSluice management in emergencies.
Does the EA have contact details for sluice / water management structures on the Pang which might be needed in emergency? EA to confirm with its emergency control room what information it needs and how it would access it.
23/01/2018New
22
9723/01/2018PVFFPiersUpdate the sluice operating procedures are in a consistent form, based on triggers23/01/2018New
23
9823/01/2018PVFFKayEA Maintenance Plan.
EA to re-provide the PVFF recommendations for areas to maintain and not to maintain. Kay to contact and brief Sophie (replacement for Rachel)
23/01/2018New
24
9923/01/2018EARiver maintenance results.
Each year (in Jan) EA to present what maintenance was actually done in the previous year (with a MAP)
23/01/2018New
25
10023/01/2018WBCReview 2007 and 2014 actions.
WBC to review the consolidated 2007 and 2014 action list from the PVFF and present back at next meeting.
23/01/2018New
26
10123/01/2018BuckleburyEABucklebury flood channel.
PA to provide Mel/Diamond with details of the need to remove the 'lump'.
23/01/2018New
27
10223/01/2018ComptonEAEA to investigate possible further watercourse improvements downstream of Aldworth Road23/01/2018New
28
10323/01/2018ComptonPVFFPeterCompton Channel Maintenance.
Peter to ensure that Compton PC maintain the watercourse where they are a riparian owner.
23/01/2018New
29
10423/01/2018ComptonPVFFPeterCompton Channel Maintenance.
Peter to contact to Yattendon Estate re riparian responsibilities.
23/01/2018New
30
10523/01/2018
Hampstead Norreys
EAEA to inspect downstream of the B4009 bridge to ensure that the river channel is not being restricted by garden extensions.23/01/2018New
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
80
81
82
83
84
85
86
87
88
89
90
91
92
93
94
95
96
97
98
99
100