| A | B | C | D | E | F | G | H | I | J | L | M | N | O | P | Q | R | S | T | U | V | W | X | Y | Z | |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1 | Bill of Quantity (BOQ) | ||||||||||||||||||||||||
2 | F.Y. 2080/81 | ||||||||||||||||||||||||
3 | Name of the Programme : Construction of Deep Tube well for WAN/NWSC in Lahan Municipality, Siraha District | ||||||||||||||||||||||||
4 | Name of Work : Construction of 300/200mm dia two Deep Tubewell to a depth of 175 m each | ||||||||||||||||||||||||
5 | Location : Matiharwa, Lahan Municipality, Siraha District | Method: Rotary/Percusion Drilling | |||||||||||||||||||||||
6 | Tender No: | ||||||||||||||||||||||||
7 | S. No | Details of work | Unit | Quantity | Per Unit Rate (Nrs) | Total Amount (Nrs) | Remarks | ||||||||||||||||||
8 | In figure | In word | |||||||||||||||||||||||
9 | 1 | Mobilisation/Demobilisation of Drilling Equipment, Manpower & preparation for temporary access road for rig machine & other vehicles for the tubewell drilling site | Job | 1 | |||||||||||||||||||||
10 | 2 | Site Clearance Cutting uprooting & disposal of grass, with light compaction levelling, cleaning the site, Plate form preparation for rig, compressor & pump, and mudpits | Job | 1 | |||||||||||||||||||||
11 | 3 | Supply and Delivery of 300 mm (12") MS Casing Pipe of min. 7mm thickness with Ring as per specification | mtr | 60 | |||||||||||||||||||||
12 | 4 | Supply and Delivery of 200 mm (8") MS Casing Pipe of min. 6mm thickness with Ring as per specification | mtr | 91 | |||||||||||||||||||||
13 | 5 | Supply and Delivery of 200 mm (8") Stainless Steel screen Pipe (SS304) with ring as per specification | mtr | 24 | |||||||||||||||||||||
14 | 6 | Well cap with flange (12" Ø) and nut bolts | set | 1 | |||||||||||||||||||||
15 | 7 | Centraliser | LS | 2 | |||||||||||||||||||||
16 | 8 | Crossbar | mtr | 6 | |||||||||||||||||||||
17 | 9 | Sinking Guide pipe 24" dia all complete | mtr | 6 | |||||||||||||||||||||
18 | 10 | 300/200 mm Reducer | set | 1 | |||||||||||||||||||||
19 | 11 | Drilling of pilot hole by 9*7/8" dia. Drilling Bit | mtr | 175 | |||||||||||||||||||||
20 | 12 | Electrical Resistivity Logging, Plotting and Design | mtr | 175 | |||||||||||||||||||||
21 | 13 | 1st Reaming of Pilothole by 13*1/2 " dia. Drilling Bit | mtr | 175 | |||||||||||||||||||||
22 | 14 | 2nd Reaming of Pilothole by 20" dia. Drilling Bit | mtr | 175 | |||||||||||||||||||||
23 | 15 | Recondition of bore hole | mtr | 175 | |||||||||||||||||||||
24 | 16 | Lowering of Pipe Assembly as per Approved Design | mtr | 175 | |||||||||||||||||||||
25 | 17 | Supply of gravel as per specification | m3 | 26 | |||||||||||||||||||||
26 | 18 | Bentinote required to Seal using Bentonite Pellete/Balls/Chips upto 35 m from surface | kg | 3000 | |||||||||||||||||||||
27 | 19 | Packing of gravel and Bentonite as per Instruction of Expert | m | 31 | |||||||||||||||||||||
28 | 20 | Well Development by Backwashing, Inner washing, Compressor/Surging/Jetting etc. as per the instruction of Expert | Hr | 48 | |||||||||||||||||||||
29 | 21 | Well Development by Pump | Hr | 48 | |||||||||||||||||||||
30 | 22 | Pump Test (Time-Drawdown Test) | Hr | 24 | |||||||||||||||||||||
31 | 23 | Recovery Test | Hr | 24 | |||||||||||||||||||||
32 | 24 | Pump Test (Step Drawdown test) | Hr | 24 | |||||||||||||||||||||
33 | 25 | Cementation for Sanitary Protection & Well Support Work (up to 1.5 m depth) by Concrete of M-20 Grade with pipe or iron bar as required with all complete | LS | 1 | |||||||||||||||||||||
34 | 26 | Drilling Report Preparation and Submission | LS | 1 | |||||||||||||||||||||
35 | Sub Total (A) | ||||||||||||||||||||||||
36 | Insurance against of work, third party & accident of workman (b) @.50% of A=B | ||||||||||||||||||||||||
37 | Sub Total(Single Tubewell ) | ||||||||||||||||||||||||
38 | Sub Total(Two Tubewell ) | ||||||||||||||||||||||||
39 | VAT @ 13 % | ||||||||||||||||||||||||
40 | Total | ||||||||||||||||||||||||
41 | |||||||||||||||||||||||||
42 | Name and Address of the Firm: | ||||||||||||||||||||||||
43 | Authorised Person of the Firm: | ||||||||||||||||||||||||
44 | Signature of Authorised Person of the Firm: | ||||||||||||||||||||||||
45 | Seal of the Firm: | ||||||||||||||||||||||||
46 | |||||||||||||||||||||||||
47 | |||||||||||||||||||||||||
48 | |||||||||||||||||||||||||
49 | |||||||||||||||||||||||||
50 | |||||||||||||||||||||||||
51 | |||||||||||||||||||||||||
52 | |||||||||||||||||||||||||
53 | |||||||||||||||||||||||||
54 | |||||||||||||||||||||||||
55 | |||||||||||||||||||||||||
56 | |||||||||||||||||||||||||
57 | |||||||||||||||||||||||||
58 | |||||||||||||||||||||||||
59 | |||||||||||||||||||||||||
60 | |||||||||||||||||||||||||
61 | |||||||||||||||||||||||||
62 | |||||||||||||||||||||||||
63 | |||||||||||||||||||||||||
64 | |||||||||||||||||||||||||
65 | |||||||||||||||||||||||||
66 | |||||||||||||||||||||||||
67 | |||||||||||||||||||||||||
68 | |||||||||||||||||||||||||
69 | |||||||||||||||||||||||||
70 | |||||||||||||||||||||||||
71 | |||||||||||||||||||||||||
72 | |||||||||||||||||||||||||
73 | |||||||||||||||||||||||||
74 | |||||||||||||||||||||||||
75 | |||||||||||||||||||||||||
76 | |||||||||||||||||||||||||
77 | |||||||||||||||||||||||||
78 | |||||||||||||||||||||||||
79 | |||||||||||||||||||||||||
80 | |||||||||||||||||||||||||
81 | |||||||||||||||||||||||||
82 | |||||||||||||||||||||||||
83 | |||||||||||||||||||||||||
84 | |||||||||||||||||||||||||
85 | |||||||||||||||||||||||||
86 | |||||||||||||||||||||||||
87 | |||||||||||||||||||||||||
88 | |||||||||||||||||||||||||
89 | |||||||||||||||||||||||||
90 | |||||||||||||||||||||||||
91 | |||||||||||||||||||||||||
92 | |||||||||||||||||||||||||
93 | |||||||||||||||||||||||||
94 | |||||||||||||||||||||||||
95 | |||||||||||||||||||||||||
96 | |||||||||||||||||||||||||
97 | |||||||||||||||||||||||||
98 | |||||||||||||||||||||||||
99 | |||||||||||||||||||||||||
100 | |||||||||||||||||||||||||